The annual range clearance plan will be collaborative effort between the ROA and associate EOD unit and finalized how far prior to the first clearance activity?

6 months prior

2

♦ ROA scheduling and EOD RST support should b done at least __ before start of the clearance op?

45 days prior

3

Range clearance ops include removal of all ordnance inrt debris normally down to ___ inches in size

4 inches

4

a waiver approved by ___ may allow UXO qualified personnel to perform limited explosives operations in areas of ranges that have never been used for live munitions?

AF/A30-AR

5

T/F range clearance ops are prohibited when snow covers the ground?

TRUE

6

T/F range maintenance (placement of new targets, removal replacement) may be authorized during snowy season?

TRUE

7

Control burning will not be used to accomplish UXO clearance, but may be used to support UXO clearance if environment and safety requirements are met? T/F?

TRUE

8

how far in advance should mapping of UXO locations/debris be accomplished prior to finalize of clearance planning?

two weeks

9

AFMAN 33-363 requires maintain records of what four range procedures?

expenditures, mishaps, all operations, UXO areas

10

live munition areas will be identified as?

"extremely hazardous contaminated hazard Areas"

11

aircraft fly over Low-strafe angle targets within how far?

500 ft

12

replace low-strafe angle target within how many scored rounds or ___ use days for non-scored targets?

15000 rounds, 12 days

13

after max accumulation amount is achieved clear ICM(improved conventional munitions) aka CBU ,targets to a radius where the debris density factor is less that ___ items per acre and at least ___ form target?

5 items per acre , within 500 ft from target

14

♦ clear the access ways to target and the area ___ feet on either side of primary target access roads?

50ft

15

clear the area around each DMPI associated target used for weapons expenditure to a radius of __ ft either side, A)after __ months or ___ use days or B) after ___ weapons have been expended

150 ft per side, 6 months, 150 use days, or 20000 rounds

16

clear targets not used for live munitions to either a radius of ____ ft or 5 items/acre ?

300 ft

17

♦ clear live HE munition targets (inlcude White phorposus) to a radius of ___ ft or 5 times/acre

500 ft

18

range maintenance working crews must have a ___ ___ in the even an uninformed flight crew attempts to use the range

signaling device

19

when range maintenance personnel are present the aircraft will remain at or above _____ ft AGL?

3,000 ft

20

when explosives ops are planned the aircraft will remain at or above ___ AGL ?

10,000 ft AGL

21

Chaff and flares are prohibited over range maintenance and clearance operations? t/f?

True, no chaff

22

do not conduct supersonic flight below ____ AGL? within ___ NM of EOD ops

10000 ft AGL, 5 NM

23

Decennial require to clear around a target used for weapons to a radius of ___ ft less than 5/acre

1000 ft

24

R3?

Range residue removal

25

semiannnually or after 150 day use clear area aronud DPI assoicated with high-use targets to how many ft?

150ft

26

clear targets used for practice, inert, pyrotechnic, illum, or smoke to a radius of? >5 items/arce

300ft

27

♦ All non-EOD will receive briefings on?

markings used for live practice and inert ord found & Explosive safety hazards

28

All EOD will receive orientation on?

ord to be expected.encountered, range cehicle ops, and emergency procedures

29

how often will pers manually remove visible DU ?

annually

30

how often do need to review and update the decommissioning plan?

biennially and provide copy to the RIC

31

♦ When range clearance requirements exceed capability manage shortfalls through?

EODIMS RST(range support tasking)

32

♦ MPPEH processing aka R3 (range residue removal) is normally done by who?

UXO qualified contractors