8 Repairs, Alterations, and Rerating of Piping Systems Flashcards
- 1 Repairs and Alterations
- 1.1 General
The principles of ________ to which the piping system was built shall be followed to the extent practical for in-service repairs
ASME B31.3 or the code
- 1 Repairs and Alterations
- 1.1 General
When ASME B31.3 cannot be followed because of its new construction coverage (such as revised or new material specifications, inspection requirements, certain heat treatments, and pressure tests), the piping engineer or inspector shall be guided by _____ in lieu of strict conformity to ASME B31.3.
API 570
- 1 Repairs and Alterations
- 1.2 Authorization
All repair and alteration work shall be done by a repair organization as defined in Section 3 and shall be authorized by the _______ prior to its commencement
inspector
- 1 Repairs and Alterations
- 1.2 Authorization
Authorization for alteration work to a piping system may not be given without prior consultation with, and approval by, the _________
piping engineer
- 1 Repairs and Alterations
- 1.3 Approval
All proposed methods of design, execution, materials, welding procedures, examination, and testing shall be approved by the _____ or by the ______, as appropriate
piping engineer
- 1 Repairs and Alterations
- 1.3 Approval
_________ approval of on-stream welding is required.
Owner/user
- 1 Repairs and Alterations
- 1.3 Approval
Welding repairs of cracks that occurred in-service should not be attempted without prior consultation with the __________ in order to identify and correct the cause of the cracking
piping engineer
- 1 Repairs and Alterations
- 1.3 Approval
The _________ shall approve all repair and alteration work at designated hold points and after the repairs and alterations have been satisfactorily completed in accordance with the requirements of API 570.
inspector
- 1 Repairs and Alterations
- 1.4 Welding Repairs (Including On-stream)
- 1.4.1 Temporary Repairs
_________ shall not be repaired in this manner unless the piping engineer has determined that cracks would not be expected to propagate from under the sleeve.
Longitudinal cracks
- 1 Repairs and Alterations
- 1.4 Welding Repairs (Including On-stream)
- 1.4.1 Temporary Repairs
The design of temporary enclosures and repairs shall be approved by the ____________
piping engineer.
- 1 Repairs and Alterations
- 1.4 Welding Repairs (Including On-stream)
- 1.4.1 Temporary Repairs
If the repair area is localized (for example, pitting or pinholes) and the SMYS of the pipe is not more than _____________, and a Fitness-for-Service analysis shows it is acceptable, a temporary repair may be made by fillet welding a properly designed split coupling or plate patch over the pitted or locally thinned area (see 8.1.4 for design considerations and Annex C for an example)
40,000 psi (275,800 kPa)
- 1.4 Welding Repairs (Including On-stream)
- 1.4.1 Temporary Repairs
When installing a fillet-welded patch adjacent to an existing fillet-welded patch, the minimum distance between the toe of the fillet weld shall not be less than:
(3)
d = 4 Rt
- 1.4 Welding Repairs (Including On-stream)
- 1.4.1 Temporary Repairs
Any leak in a Class 1 service or where a risk ranking is determined to be high, shall be first reviewed by a __________ determine if the work can be safely performed while the system remains on stream.
piping engineer
- 1.4 Welding Repairs (Including On-stream)
- 1.4.1 Temporary Repairs
Temporary repairs should be removed and replaced with a suitable permanent repair at the ___________
next available maintenance opportunity
- 1.4 Welding Repairs (Including On-stream)
- 1.4.2 Permanent Repairs
Repairs to defects found in piping components may be made by preparing a ___________ that completely removes the defect and then filling the groove with weld metal deposited in accordance with 8.2.
welding groove
- 1.4 Welding Repairs (Including On-stream)
- 1.4.2 Permanent Repairs
Insert patches (flush patches) may be used to repair damaged or corroded areas if the following requirements are met:
a) __________ groove welds are provided;
b) for _________ piping systems, the welds shall be 100 % radiographed or ultrasonically tested using NDE procedures that are approved by the inspector;
c) patches may be any shape but shall have ________corners [1 in. (25 mm) minimum radius].
a) full-penetration
b) Class 1 and Class 2
c) rounded
- 1.4 Welding Repairs (Including On-stream)
- 1.5 Nonwelding Repairs (On-stream)
The design shall include control of ________ if the piping component being enclosed is (or may become) insufficient to control pressure thrust
axial thrust loads
- 1.4 Welding Repairs (Including On-stream)
- 1.5 Nonwelding Repairs (On-stream)
During ______________, temporary leak sealing and leak dissipating devices, (e.g., wire wrapping, mechanical clamps, etc) including temporary repairs on valves, shall be removed and appropriate actions taken to restore the original integrity of the piping system.
turnarounds or other appropriate opportunities
- 1.4 Welding Repairs (Including On-stream)
- 1.5 Nonwelding Repairs (On-stream)
Temporary leak sealing and leak dissipating devices may remain in place for a longer period of time only if approved and documented by the __________
piping engineer
- 1.4 Welding Repairs (Including On-stream)
- 1.5 Nonwelding Repairs (On-stream)
Procedures that include leak sealing fluids (“pumping”) for process piping should be reviewed for acceptance by ___________
the inspector or piping engineer.
- 2 Welding and Hot Tapping
- 2.1 General
All repair and alteration welding shall be done in accordance with the principles of __________________________
ASME B31.3 or the code to which the piping system was built.
- 2 Welding and Hot Tapping
- 2.1 General
Any welding conducted on piping components in operation shall be done in accordance with _______
API 2201
- 2 Welding and Hot Tapping
- 2.2 Procedures, Qualifications, and Records
The repair organization shall use welders and welding procedures qualified in accordance with _________________
ASME B31.3 or the code to which the piping was built
- 2 Welding and Hot Tapping
- 2.2 Procedures, Qualifications, and Records
The repair organization shall maintain records of welding procedures and welder performance qualifications. These records shall be available to the inspector _____ to the start of welding.
prior