Atlas Methods of Compensation 3 Flashcards

1
Q

Guarantee to enter into a contract if awarded

A

Proposal bond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Guarantee to execute the work in accordance with the terms of the contract (15% of the contract amount, upon contract signing)

A

Performance bond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Guarantee to pay all obligations arising from the contract (15% of contract amount upon contract signing)

A

Payment bond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Guarantee workmanship and quality of materials and equipment for 1 year (30% of the contract amount)

A

Guarantee bond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Change after the signing of the contract

A

Change order

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Shop drawings

Conditions in the preparation of shop drawings

A

At the contractor’s expense

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Shop drawings

Checking drawings of sub-contractors

A

Contractor to check

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Shop drawings

To be numbered and dated containing the name of the project, descriptive names of equipment/material, and location of installation

A

Identification

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Shop drawings

In duplicate

A

Letter of transmittal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Shop drawings

Corrections, changes, and variations

A

Architect’s approval needed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Shop drawings

Responsibility for accuracy

A

Contractor’s responsibility

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Protection of adjacent property and existing utilities

  • Contractor’s sole responsibility
  • Existing utilities
A

Art. 17

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
  • Proposal
  • Tender documents
  • Invitation to bid
  • Bid bulletin
  • Instruction to bidders
A

Bidding documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
  • Evaluate
  • Review
  • Recommend
  • Notice to award
A

Architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
  • Approve
  • Awarding
  • Proceeding
A

Client

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Assist the owner in obtaining proposals from contractors, analyzes bid results, and prepare abstract of bids, notice of award, notice to proceed, and other construction contracts

A

AoR (SPP Doc. 202)

17
Q

Soil boring test price

A

Php 35k per hole

18
Q

Geodetic engineer price

A

Php 5k (simple residential/4 sides) or per ha.

19
Q

Construction stakes and reference mark

A

Owner’s responsibility (lot lines, easements, benchmarks)

Contractor (other grades, lines, levels, and benchmark)

20
Q

Services of a licensed surveyor

A

Contractor’s responsibility to check column centers, piers, walls, pits, trenches, pipework, culvert utility lines, etc.

21
Q

Changes in the work

Changes ordered by owner

A

In writing

22
Q

Changes in the work

Adjustments of contract

A

In cost and time; consent of sureties and additional performance bond

23
Q

Changes in the work

Value of extra work

A

By estimate in a lump sum; by unit prices not exceeding 25% of original work contract; by actual direct cost + 15% profit, overhead, and tax

24
Q

Notice to proceed

A

After execution of contract agreement

25
Contract time
7th day from NTP receipt
26
Contractor to submit a schedule of construction work in critical path method or other forms acceptable to architect; Architect can order the contractor to take steps to ensure completion within the timeframe.
Schedule of completion
27
CARI
Contractor's All-Risk Insurance
28
Contractor's insurance and bonds
Art. 31
29
Contractor's insurance and bonds Protection for bodily injury, death, or property damage
Contractor's liability insurance
30
Contractor's insurance and bonds From work performed by sub-con where guarantees are required; contractor to secure warranties from sub-con
Contractor's guaranty warranty
31
- Contractor's liability insurance - Contractor's fire insurance - Contractor's performance and payment bonds - Contractor's guarantee bond - Contractor's guaranty warranty - Contractor warrants and/or guarantees for one year
Contractor's insurance and bonds
32
CFEI
Certificate of Final Electrical Inspection
33
Other requirements before final payment
- Cert. of Bldg. Occupancy - Cert. of Final Inspection - 3 copies of directory of panel boards and circuits - Original & 3 sets of as-built dwgs - 3 copies of manuals - 3 copies of keying schedule - Guarantee bond 30% of contract price good for one year (required only if owner releases performance and payment bond)
34
Contractor's responsibility for accidents and damages
Art. 30
35
- Safeguards to be undertaken by the contractor - Contractor's responsibility - Indemnity
Contractor's responsibility for accidents and damages