Case Study Flashcards
(103 cards)
Why no PTE for Tower B?*
Late receipt of IFT
MC produces BQ (Client not want to pay us to duplicate BQ and then price)
Had I been granted time to do PTE, could take 1m,
and would be my estimate of cost overrun,
and did not want to delay procurement
Go to market would prove cost overrun, and would have fit-out VE expertise
Note:
- No PTE for MW package but probably don’t mention that
- furthermore, no indication of cost overrun (as assume designed to budget)
Opt C - VE:
How is VE incorporated into the LOA, and prioritised above outdated Spec and Drawings?
LOA is prioritised alongside PTC’s and VE
2 LOA, PTC schedules, VE 3 CoSC, 4 Spec, 5 Dwgs, 6 BQ 7 Any other
Note:
1 Subcontract agreement (not used on OZ)
Opt A - Redesign high cost items:
Did I propose this option to Client?
No, discussion with PM as time issues
The tenderers are requested to comply B2B with main contract, why is this?
B2B terms benefits MC
- Monthly administration of multiple packages
- Known risk allocation, can pursue at B2B costs
Did you consider D+B procurement route?
For early start on site
but the compromise is quality
Fixed as Traditional FPLS in the PS expenditure guidelines
Note:
Agreed before my time
Ignoring design development creep, the DD cost plan was 2017, do I think accurate if tendered now?
If tendered today, TPI may be cheaper re Covid
Notes: Tender Price Index (TPI) - Cost to Client - Inflation from the estimate to TR date - Tender Returns
Okay, so the ID was not developed since SD - what level of detail would you expect at DD?*
DD Specs, dwgs, door schedules
Enough to prepare a priced BQ (PTE) on
Enough to tender (not use PS)
Note:
- Detailed measurement of finishes (for schedules)
Is it really schematic if it’s just a general arrangement plan with no specification? Is this not more concept?
Agreed.
It is more akin with Concept. However, the drawings were titled as SD
I spoke with ID Consultant, who said its more SD, hence I used the term in my report
Why not wait for full design for Tower B ID?*
Client eager to early appointment of Contractor, and commence structural works
PS used to overlap design and construction.
Note:
- I appreciate it is best practice to await full design
- “General construction process i.e. certain packages always lag behind, for example, there’s little point developing ID to DD until structure is frozen. That’s why you’ll find nearly always, ID, MEP and landscaping are less developed and often end up being provisional sums”
Opt C - VE:
Can you provide an example of cost cutting?
Stone to cheap vinyl in resi corridors.
Note:
- Stone to carpet in resi corridors
- WLC - I advised carpet is cheaper but consider replacement costs over 20 years
How is this case study different to your daily activity on tender return overbudget, what makes it a ‘critical’ analysis/ case study?
Time critical
- No time for PTE
- On the critical path (of its Sectional Completion)
- Could of delayed tender process
Is MC entitled to loss of profit if PS reduced?
No. The Main Contract states that Prov Sums “may be used in whole, in part, or not at all”
Opt C - VE:
What is the VE process on OZ/ Tower B?
The tenderers submit proposals in PTC stage (without samples)
I collate and issue consolidated unpriced VE register to SC for tech review
Agreed VE implemented into award amount (and LOA - prioritised above Spec and dwgs)
Preparation - The ITT (invitation to tender) consisted of?
- General project details
- tender docs
- key contractual terms,
- project duration
- deadlines (TQ and tender return)
Note:
To receive the ITT the subbie has already been prequalified
Budget per m2 for residential apt?
AED 2,400/m2
Note:
=(AED 107m / 45 floors @ 1000m2 per floor)
What happens if discrepancy between mine and MC tender report numbers?
Happens. I discuss with Contractor and detail changes in my tender report
Why was single-stage tendering strategy chosen, for procuring Prov Sums?
We now have full structural design
employer can control design with the ID consultants engaged, who are developing design
Note:
- two-stage not require MC design development
- negotiation would be harder to achieve and demonstrate value
What is Dutch auctioning?
Unethical way to reduce tenders
Approach each bidder and say another tenderer will do it for X, can you beat this
You mention IFT was late, when was it due?
Resi fit out IFT - due Nov 18 (few months before)
Note:
- DD budget - approved Nov 17
- Resi fit out IFT - received Jan 19
Opt C - VE:
Definition of Value Engineering?*
Obtain best value, without impacting
- quality/ aesthetics
- performance/ functionality
- may be cost increase (but last longer LCC)
Reactive - corrective decisions when over budget
Notes:
Consider WLC - may cost more if e.g. high performance vinyl over cheap as specified
How many PS in Contractor’s initial procurement strategy?
57
Didn’t you have time to do a PTE after the tender docs were issued, prior to the tender return date 6 weeks later?*
Would of took me several weeks, at expense of other packages being procured
However, would of only shown cost overrun estimate. No time for redesign. Delay procurement.
So better to tender, confirm cost overrun, then have VE expertise on board to streamline process.
Note:
If IFT and Contractor BQ ready, I can and did PTE some packages
What are the risks of provisional sums?
Cost certainty
For undefined
- not priced in Contractor prelims
- no time allowed in programme
Recommendation - Package value started at, and end at?
Start AED 108m,
ended at 99m
= 9% saving