Contract Admin Flashcards

(34 cards)

1
Q

What documents are including within tender?

A
  • Form of Tender
  • Preliminaries
  • Drawings
  • Pricing Document
  • Pre-construcion Information
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is Partial Possession?

A

The employer agrees with the contractor to take control of site at various stages (CONSENT)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is Sectional Completion?

A

The agreed works are handed over in various stages (CONTRACTUAL)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is defined Provisonal Sum

A

Enough detail is provided to enable the contractor to include within their programme and pricing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Process for non completion of Works

A

Certificate of non completion to be issued
Any implications of EOT?
Client deducts LEDS from payment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What happens if the client fails to pay the contractor under JCT

A

Clause 4.6.1 allows for interest on late payments, set at 5%

Clause 4.7 right to suspend performance under HGRA for non payment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are Insurance options under JCT MW

A

5.4 (A) - use for new buildings and taken out by contractor

5.4(B) - use for existing buildings taken out by employer

5.4(C) - parties agree there own insuarnce options

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

If a contractor submitted an obvious error in their submission, what would do?

A
  • Details provided and contractor has option to confirm or withdraw their submission
  • Details provided and options to correct error
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Is the contractors programme part of the contract documentation under JCT MW

A

No mention but PCI should form part of the tender docs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Name some legislation in relation to Contract Admin

A

CDM 2015
HGRA 1996

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a pay less notice?

A

Issued either to the employer of contractor noting the intention to pay less than the valued amount

Issued no later than 5 days before final date for payment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What clause covers a non completion certificate

A

Not required under a minor works contract but should be in writing that the contractor isn’t going to recah PC date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a relevant Matter

A

Matter for which the client is reponsible that materially affects the progress of the works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is Collateral Warranty

A

Binding agreement that gives third parties contractual rights where previously a contract did not exist

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Types of JCT Contracts and when would you use them

A

JCT MW - simple in nature under 500k

JCT intermediate - BOQ and sectional completion.

JCT SBC - large scale projects, without boq

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Difference between PC sum and Provisional sum?

A

PC sum provided by nominated contractor for works // adds overhead and profit

Prov Sum -Lump price as works unknown

17
Q

Describe the process with LADS?

A
  • Ca to issue cert of non completion
  • CA must recognise no EOT request
  • Employer to give notice to dedcut LAD’s in writing
18
Q

What is loss and Expense?

A
  • Enables contractor to be reimbursed for loss and expenses
  • Caused by delay of info, waiting, loss of profit
19
Q

What is a defect Liability Period?

A

Commences at PC, liable for making good any defects at PC, typical 3 or 6 months

20
Q

How can payment be made for materials on site? Aspects to be in place?

A

Materials for the works & delivered to programme.

Require a vesting certificate - prooff of ownership

21
Q

Typical retention in a JCT contract?

22
Q

What is a performance Bond?

A

provided by banks to give the employee a guarantee for payment should they suffer a loss - usually 10%

23
Q

What is a Parent Company Guarantee?

A

Contractual performance is underwritten by members of that cooperate year

24
Q

Describe the sections of Contract Admin Guidance Note 2016 1st edition

A
  • Outlines best practices for professionals acting as Contract Administrator
    1. Introduction and scope
      1. Role of CA - pre contract duties and post contract duties
      2. Terms of Appointment
      3. Tasks of CA - inspections, certs, EOT
      4. Legal and Regulatory compliance - CDM, building Safety
25
What is a contract administrator
person who administrates the contract between the client and contractor. prepare tender docs, issuing certs
26
Explain the role of contract Administator
- issuing instructions - Certifying Payment - Monitoring progress -
27
What are standard forms of contract
Pre-drafted agreements used on projects in construction
28
Name some standard forms of contract
-JCT -NEC - FIDIC -RIBA
29
Advantages of standard forms of contract
- Saves time and costs without having the need to draft new contracts - Familiarity - Consistency
30
What is a JCT minor works contract and key mechanisms?
- Contract designed for small, simple projects under 500k - Mechanisms: payment provisions, instructions, EOT, delay and dispute resolution
31
Purpose of issuing Practical Completion Certificate
Signify works are complete par minor snags. - half of retention is released - handover of possession - start of defects liability period
32
how to determine replacement of flooring was required at liffey ave
- Replacement was better option as water had affected subfloor and insulation. - damage of a certain period of time
33
What is the make up of a suspended timber floor?
mineral wool inulation between joists dpc placed between sleeper walls and joists floorboards,
34