Contracts Flashcards
(108 cards)
What needs to be in place for a contract to be valid
"Offer Acceptance Consideration Intent Legality Capacity"
What is the difference between expressed and implied terms
“Expressed terms - Explicitly agreed by both parties and can be oral or in writing
Implied - A term that hasn’t been agreed expressly by either party, but that has been implied by the other terms of the contract”
Can you tell me what a typical D&B contract would consist of
"It is 5 parts; 1. JCT 2. Amendments 3. Employers Requirements Consisting of: Prelims, Design specs & Appendices 4. Contractors Proposals 5. CSA"
What are Prelims
The purpose of preliminaries is to describe the works as a whole, and to specify general conditions and requirements for their execution, including such things as subcontracting, approvals, testing and completion
What are a couple of types of contract asides from lump sum
“Lump sum - Fixed price for works only extras are instructed change/ change not included e.g. ground risk
Re-measurable - based on approximate quantities or schedule of rates
Cost reimbursable - Contractor gets actual costs plus an agreed percentage for OH&P”
Are you aware of the NEC suite of contract
NEC is New Engineering Contract:
What are the NEC options
“Option A-F:
NEC – Option A Priced contract with activity schedule
NEC – Option B Priced contract with Bill of quantities
NEC – Option C Target cost with activity schedule
NEC – Option D Target cost with BOQ
NEC – Option E Cost reimbursable
NEC – Option F Management contract
NEC – ECC Short Contract “
You note about EOT & L&E what are the timescales in the JCT D&B contract to review
“EOT:
Contractor must notify when it becomes reasonably apparent
Must provide causes which is a relevant event
Must provide particulars of effect including estimated delay
Must supply information the employer may reasonably require
Shall notify within 12 weeks of receipt or when reasonably practicable
L&E:
Notify employer as soon a reasonably practicable
Provide assessment of L&E
Must supply information the employer may reasonably require
Within 28 days of receipt of initial assessment and information and 14 days of each subsequent update the Employer shall notify the contractor of L&E incurred. Insufficient detail to allow the contractor to understand the differences”
What clauses in the contract deal with EOT & L&E
“Relevant Event - EOT 2.23-2.26
Relevant Matter - L&E 4.19-4.23”
How many Relevant Events are there
14
How many Relevant Matter are there
5
If a scheme was in delay and the client wished to levy damages following expiration of the contract completion date how would you go about that
“Issue notice of non-completion
Calculate value of omission
Issue this to the client for them to issue
5 day before due date as payless
What signs would you look for in order to understand if a contractor was in trouble of insolvency
“Not paying the supply chain
Falling cashflow
Inactivity on site
Demanding swift payment
Withdraw of labour”
What would you advise the client to do if a contractor went insolvent
“Withhold payments and the release of retention monies
Secure the site and make it safe
Secure both contractors’ and subcontractors’ materials and plant.
Employ a security firm on a visiting or permanent basis.
Ensure the project has adequate interim insurance
Make an inspection of the site and record the progress accurately.
What is the difference between assignment and novation
“Assignment is where the benefit (service) is transferred but the burden to pay remains with the client.
Where the benefit (service) and burden (cost) is transferred”
Would you advise the client to execute the contract under hand or as a deed
“As a deed as it has limitations period of 12 years
Under hand is 6 years”
What are the standard timescales for payment in a JCT D&B contract
“IVD is noted in the contract
7 days to the due date
5 days to issue the Payment certificate
14 days from the due date to pay”
What is the difference between an EA/CA
“Employers Agent - Acts on behalf of the client
CA - must act independent and have an agency function”
What is the risk to a client if the don’t pay by the final date for payment
“If the failure continues for 7days after notice to the employer of intention to suspend has been issued they can suspend performance
It also entitled the contractor to Relevant Event
And will be reimbursed for reasonable costs for suspension
If the default continues for 14 days following notice the contractor can on or within 21 days from expiry of the 14 days terminate the contract
What is the importance of a base date
“It sets the reference date from which conditions are deemed known by the contractor so are reflected in their price.
If a change happens after this date it is not considered to be included in the price
This affects a divergence”
For a single stage tender process what would the typical base date be
Date of tender
What is a nominated sub contractor
“Sub contractor who the employer instructs the contractor to employ.
Performance remains employers responsibility”
Do you know what a Performance bond is
It is an insurance back surety which provides generally 10% of the contract sum should the contractor fail in their insurance.
When woulda Performance Bond typically expire
“PC
end of 12 months defects”