Dimensions and Project Delivery Flashcards

1
Q

Why is over-dimensioning a problem in construction documents?

A

It can lead to inconsistencies when changes occur, making drawings harder to interpret and risking construction errors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a recommended practice when using dimension strings in a plan?

A

Leave one segment of the dimension string blank to allow flexibility and avoid discrepancies.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When should you use ‘align’ or ‘centerline’ instead of exact dimensions?

A

When the design intent is alignment or centering rather than fixed distances.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What does ‘VIF’ mean in dimensions?

A

Verify in field – it means the dimension must be checked on-site.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What should dimensions always reference?

A

Known elements like column lines, exterior walls, or fixed shafts (e.g., stairwells).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Where should vertical dimensions be shown?

A

On elevations or sections, not on plans.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the proper reference point for vertical dimensions?

A

Top of structural floor, not finished floor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Why avoid dimensioning to finished floor?

A

Because finish materials can change, affecting accuracy.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are two schools of thought for dimensioning walls?

A

To framing (e.g., stud edges) or to finish (e.g., drywall surface).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Why must one dimensioning method be used consistently?

A

To maintain accuracy and prevent confusion during construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a door schedule used for?

A

To organize and present detailed door information such as size, location, type, and hardware.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is typically included in a door schedule?

A

Door mark, room location, size, manufacturer, type, hardware, fire rating, frame info, finishes, and remarks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Why include a ‘remarks’ column in a schedule?

A

To note unique features or additional instructions not covered by other columns.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are key stages in producing contract documents?

A

Design Development (DD), 50% CDs, 90% CDs, and 100% CDs for construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the focus at 50% CDs?

A

Coordination between architect and consultants.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the goal at 90% CDs?

A

Ensure full coordination and verify code compliance, program, and consultant alignment.

17
Q

What is the purpose of the 100% CD set?

A

Used for bidding; must be clear and complete for accurate, comparable bids.

18
Q

How does design/bid/build work?

A

Client hires architect → full design → competitive bidding → GC builds.

19
Q

How is design/build different?

A

One contract for design and construction; contractor involved early.

20
Q

What is unique about fast track delivery?

A

Construction begins before design is complete via phased packages.

21
Q

What challenge does fast track present?

A

Increased risk of errors and rework due to evolving design.

22
Q

What is the core idea of integrated project delivery (IPD)?

A

All parties (owner, architect, contractor) collaborate from the start as one team.

23
Q

What role does a construction manager (CM) play?

A

Acts on owner’s behalf, offers early cost control, and influences final drawings.

24
Q

When does the CM gain control of project decisions?

A

After design development, when pricing is locked.

25
How do project delivery methods affect drawings?
They influence who controls design, when contractors are involved, and how drawings are formatted.