What is the priority order for stairwell pressurization at a HRFPMD by the Vent Support group?
What due truck is the Vent support unit?
Attack Stair
Evacuation stair
Public Hallway
6th Truck Company
FFP 6.19.2
What is the tool assignment for the first due roof man at a fire in a HRFPMD?
Halligan
Hydra Ram
KO Curtain
How does the 1st due roof man access the floor above at a fire in a HRFPMD?
attack stair
How does the LCC access the roof in a HRFPMD?
via evacuation stairway
At a fire in a HRFPMD, who ensures elevators are recalled and searched?
2nd Ladder
Who searches 5 floors above the fire floor at a HRFPMD fire?
2nd Ladder
What is the tool assignment for the 2nd due Roof at a HRFPMD fire ?
Halligan, Maul, LSR, Life Belt
What is the tool assignment for the 3rd due truck at a HRFPMD fire?
Where should they operate?
Normal Compliment of tools and KO curtain
floor above the fire
Who initially ensures the evacuation doors are closed on the fire floor at a HRFPMD?
2nd due truck
What is the responsibilities of the 3rd due truck at a HRFPMD?
Confirmation the evac stairwell doors are closed on the fire floor, and are maintained in the closed position. This may be accomplished by positioning members on the stairwell side of the door
When can an 1 3/4” hose be stretched for a fire in a LRFPMD?
When every apartment door is within 50’ of every stairway on that floor.
What is the tool assignment for the Ov/Lcc team at a fire in a LRFPMD?
Ov- Halligan, Halligan Hook
Lcc- Halligan, Axe
Tool assignment for the roof FF at a fire in a LRFPMD?
Where do they operate?
Halligan, Halligan Hook, LSR, Life Belt
Roof
What is the priority order for roof access for the roof man at a fire in a LRFPMD?
Stairway in an attached adjoining building
An enclosed evacuation stairway
Aerial Ladder or Tower Ladder
What is the roof access for a fire in an isolated LRFPMD where there is only 1 open interior stair?
If the stairwell is not an IDLH- roof man to roof via interior stairs as long as the door is maintained closed by ladder officer.
If stairwell is an IDLH- roof man must be teamed up with another member. Roof man must communicate to officer that they are safely on the roof. Door must be controlled
What is the tool assignment for the 2nd due inside team for a fire in a LRFPMD?
Where do they operate?
Normal compliment of tools plus KO curtain
Apartment directly above
Also responsible for all floors and stairs above the fire floor.
Where does the 2nd due inside team operate for a top floor fire in a LRFPMD?
VES of fire floor (top floor) with 1st ladder company
Who brings the KO curtain at a top floor fire in a LRFPMD?
2nd Due Roof
Tool assignment for 2nd due roof man at a fire in a LRFPMD?
Halligan hook, Halligan, LSR.
If top floor fire, take KO curtain in lieu of LSR
Who takes the LSR for a fire not on the top floor of a LRFPMD?
Both the 1st due roof and the 2nd due roof
What is the color and size of the vacant building marking ?
lime yellow reflective paint, 18” X 18” square
lines 2” wide. made alongside the from entrance a height that is in line with the front entrance.
Location of the first line in a cellar fire in a taxpayer?
Stretched into the occupancy above the fire to prevent vertical extension.
Responsibilities of the 2nd engine company at a cellar fire in a taxpayer?
assist with initial line
supply sprinkler system
after supplying sprinkler, stretch second line
Who ensures the sprinkler is supplied at a taxpayer fire?
3rd Engine company