Formulae Flashcards

(27 cards)

1
Q

PV (Present Value)

A

FV/((1 + i)^n)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

EAD (Expected Activity Duration) - Triangular

A

(O+M+P)/3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

EAD (Expected Activity Duration) - Beta/PERT

A

(O+4M+P)/6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

SD (Standard Deviation)

A

(P-O)/6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

AV (Activity Variance)

A

SD^2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Range of Activity Duration

A

EAD +/- SD

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

EF (Early Finish)

A

 ES + Duration - 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

LS (Late Start)

A

 LF - Duration + 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Total Float

A

 LS - ES, or LF - EF

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Rough Order of Magnitude

A

-25% to +75%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Definitive estimate

A

-5% to +10%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

CP (Critical Path)

A

 Sum of longest duration path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

CV (Cost Variance)

A

EV - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

SV (Schedule Variance)

A

EV - PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

CPI (Cost Performance Index)

A

EV / AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

SPI (Schedule Performance Index)

17
Q

EAC (Estimate At Completion), using the most accurate method

A

AC + Bottom-up ETC

18
Q

EAC (Estimate At Completion), assuming variances are typical

19
Q

EAC (Estimate At Completion), assuming variances are atypical

A

AC + (BAC - EV)

20
Q

EAC (Estimate At Completion), assuming poor cost performance and a need to hit a firm completion date

A

AC + ((BAC - EV) / (CPI * SPI))

21
Q

ETC (Estimate To Complete)

22
Q

VAC (Variance At Completion)

23
Q

TCPI (To Complete Performance Index), Standard Method

A

(BAC - EV) / (BAC - AC)

24
Q

TCPI (To Complete Performance Index), assumes original budget is not possible

A

(BAC - EV) / (EAC - AC)

25
Communication Channels
N \* (N - 1) / 2
26
EMV (Expected Monetary Value)
Probability \* Impact
27
POTA (Point Of Total Assumption)
[(Ceiling Price - Target Price) / Buyers Share Ratio] + Target Cost