JCT Contract Mechanisms Flashcards
(65 cards)
What are the contract elements of JCT?
Articles of Agreement - who is involved (employer, contractor, registered offices), parties intentions to work together
Recitals - description of the works, contract drawings, specs, who parties are
Articles - what is agreed between the parties e.g. obligations of C /E, named Architect, rights to adjudication and arbitration
Contract particulars - aspects of the project that are particular to the project
Attestations - parties sign; deed or underhand
Conditions - Sections 1- 9
Schedules - 1 - 7
What is included in Contract Particulars?
Contract sum
Retention %
Interim payment method
Third Party Rights / CW’s
What is included in the conditions?
Section 1 - Definitions & interpretation
Section 2 - Carrying out the works (contractor obligations, PC, LADs, Contractors design docs)
Section 3 - Control of the works (CDM regs)
Section 4 - Payment provisions (Contract sum & adjustments, payments, notices, interim payments)
Section 5 - Variations (valuation rules)
Section 8 - Termination
Section 6 - Injury, damage and insurance
Section 7 - Assignment, Performance Bonds, PCG, Third party rights, CW’s
Section 8 - Termination
Section 9 - Settlement of Disputes
What are the schedules under a JCT SBC?
1 - Design Submission Procedure
2 - Variation and Acceleration Quotation Procedure
3 - Insurance options
4 - Code of Practice
5 - Third Party Rights
6 - Forms of Bonds
7 - Fluctuation Option A
8 - Supplemental Provisions
What are the insurance options in JCT contracts?
Option A - New buildings - all risk insurance by Contractor
Option B - New buildings - all risk insurance by Employer
Option C - Joint names insurance by Employer of existing structures
What key contract terminology is different in the JCT D&B?
- Variations are referred to as changes
- ER’s and CP’s
- EA
- Final certificate is referred to as the Final statement
Where discrepancies are found in CP’s or ER’s, what occurs in a JCT D&B?
- CP’s result in the Contractor correcting at no cost if proposed amendment is accepted
- ER’s treated as a Change with associated EoT, L&E
- ER’s take precedent over CP’s (gold tap vs brass tap!)
What bonds are available under a JCT D&B?
Advanced Payment Bond
Retention Bond
Bond for offs-site materials
Performance Bond
What are ER’s in a JCT D&B?
Provides a brief to the Contractor to produce the CP’s. Can be general or more detailed
What are CP’s in a JCT D&B?
Form part of the contract documents, contractors response to the ER’s
What is included in ER’s?
Referred to at Article 4 of CP’s
-The works
-Division of works into sections
-Site details
-Planning and other constraints
-Information about the contract
-Provisional sums
-Form and content of the CP’s
How do ER’s and CP’s differ?
-ER’s are the responsibility of the Employer whereas CP’s are the contractors responsibility.
The liability for errors lies with the respective parties.
-ER’s can have provisional sums. Within CP’s provisional sums are considered fixed sums
What is the CSA used for? JCT D&B
-DB 2016 is lump sum
-Used as a basis for calculating interim payments (Alternative B)
-Used to assess the value of changes
-Used to assess increase in price if fluctuation Option C applies
How do CDM regulations apply to a JCT D&B?
-Employers duty to appoint a principal designer and principal contractor - usually contractor for both under D&B
-Employer provides pre-construction info to Contractor
-Where Contractor is the principal contractor they must ensure construction phase plan is prepared before setting up site
-H&S file to be complied by principal designer, contractor must provide the information
-Clause 2.27 requires contractor to have complied with CDM before practical completion is issued “
How has the JCT D&B changed from the 2011 to the 2016 edition?
-Adjustment to reflect CDM 2015 regs
-Simplification of Section 4 payment provisions to introduce procedure for prompt assessment of Loss and Expense claims
-Inclusion of provisions for performance bonds and parent company guarantees
What roles are there under a JCT D&B 2016?
Architect
Employers Agent
Principle Designer
Principle Contractor
What are the roles under JCT SFC 2016?
Architect / CA
QS
Principle Designer
Principle Contractor
What are the insurance options under a JCT?
Option A - Contractor takes out in Joint Names all risk insurance
Option B - Employer takes out in Joint Names all risk insurance
Option C - Employer takes out in Joint Names all risk insurance for refurbishment or extensions to existing structures. Specified Perils insurance taken out for an existing building
Joint names = policy of insurance where insurers have no right of recourse against any person names as an insured
What are the fluctuation options in a JCT?
Option A - fluctuations in contributions, levies and taxes
Option B - fluctuations in labour, materials and taxes
Option C - some items are fixed but others are variable. Price adjusted usually using BCIS data
Default is Option A
Do all JCT contracts have fluctuation options?
Intermediate - A only
Minor works - A only
What contracts can have a CDP?
Intermediate
Minor Works
What contracts can have a PCSA?
D&B
Major Project
Intermediate
SBC w / wo quantities
When would you use a measured term contract?
When there is no full design
Works are for a package of minor or maintenance works over a set period
Not used in frameworks
When would you use an Intermediate contract? Traditional Lump Sum
‘-Where full design is available or CDP is needed
-Where works are relatively simply with out complex specialist works
-Circa £1m, straightforward works lasting less than a year
-Where detailed procedures are or named sub-contractors
-Can use a PCSA
- Where sections are needed
- Architect / CA / QS administer contract
- Employer provides BoQ / spec / work schedules
- Where lump sum is quoted to be include CSA or Schedule of Rates
- Lump sum, interim payments
- Only provides limited fluctuation provisions (contribution, levy and tax changes)
- Provisions for PB / PCG, CW