Misc Flashcards

1
Q

What method does PMIS use to build schedule?

A

Precedence Diagramminng

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What kind of costs can be scaled down and reduced?

A

Direct, Variable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What tool is used to validate scope?

A

Inspection

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What can a critical path have? (possible, not necessary)

A

Zero, Posititive, or Negative Float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What process is a fishbone diagram used for?

A

Identify Risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

REAM

A

Resource Assignment Matrix. shows what work is assigned to who

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

SEAM

A

Stakeholder Engagement Assessment Matrix, assess how to engage each stakeholder

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Project team assignments are an output of what excuting process?

A

Acquire Resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What close is not associated with a project close?

A

Procurement Close (often done with control procurements)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the 3 most common sources of conflict?

A

Schedule, Priorities, Resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Unplanned Training

A

Training executed through conversation, observation, & project performance appraisals

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Cost Plus Percentage of Cost (contract)

A

Buyers pay all & costs are not limited. Highest risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Who is accountable for enforcing the team charter?

A

The team, they created it

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the best process for adding requirements/features in an agile project?

A

ensure sufficient detail on user stories and add to Sprint Backlog

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Getting insurance for a storm is an example of what type of risk

A

Transfer - risk is now in the hands of insurance company

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Quality Audits

A

structured, independent process to determine if activities comply with an organization’s policies & procedures.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Transformational Leadership

A

Empowers, encourages, and inspires.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Transactional Leadership

A

Performance-focused. Goal and objective-oriented

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Laissez-faire Leadership

A

Allows the team to make their own decisions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Interactional Leadership

A

Combines transactional, transformational, and charismatic qualities to suit the group dynamics.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Charismatic Leadership

A

Energetic, inspiring, and passionate about convictions but may be motivated by personal goals.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is the last thing that should be done in the Close Project process?

A

Release project resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

When is the PM assigned?

A

Project manager is assigned during project initiating & project charter creation, not after it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What are outputs of Define Scope?

A

-Project Scope Statement
-Updates to project docs including: stakeholder register, requirements docs, and the requirements traceability matrix

25
Resource Leveling
schedule network analysis technique. It is applied to a schedule that has already been analyzed by the critical path method. -necessary when resources are over allocated -keeps resource usage at a constant level
26
6 Steps of Change Request
1.Document the change and analyze it for feasibility 2.Determine the costs and benefits of the change 3.Submit a change request 4.Perform the Integrated Change Control Process 5.Update the project management plan and project documents 6.Communicate the status of the change to relevant stakeholders
27
What is 90% of the PMs time spent doing?
Communications
28
Where are all delays tracked?
Issue Log delays in overall schedule may warrant change request
29
Who can add to the Product Backlog?
PM, Product Manager, Project Team, Customer
30
When a change request is approved, what process is used to implement the change?
Direct & Manage Project Work
31
Where are exclusions to scope noted?
Scope Statement
32
Resolving conflict is done through which process?
Manage Team
33
Crashing
scheduled compression method where you add more resources to complete a project sooner
34
Fast Tracking
Running activities in parallel to complete a project sooner
35
Is CPI is overbudget and SPI is ahead of schedule, what is taking place?
Crashing
36
Cost Aggregation
Tool used in Determine Budget Done after costs are assigned (Estimate Costs is completed)
37
Which process applications do not increase cost?
Fast Tracking Resource Leveling
38
Where is positive risk accounted for?
Risk Register NOT included in Risk Management plan
39
Attribute Sample
measurement that is pass/fail or good/bad
40
Statistical Independence
outcome of 2 events cannot affect eachother
41
Mutually Exclusive
2 events that cannot happen at the same time
42
Project Team Assisgnments
Recording of the team members and their roles and responsibilities for the project. Documented in PM directory, Project Org chart and/or schedule
43
What best describes the role of a sponsor in a project?
Helping to avoid unnecessary changes to the project objectives
44
Whose job is to prioritize project changes?
Project Manager
45
The most important thing to focus on in contract negotiations is:
To negotiate a deal that both parties are comfortable with.
46
In an agile project, who owns quality?
Cross Functional Team
47
Single-Source Seller
means there is only one seller the company wants to do business with.
48
What is the preferred method for settlement of all claims and disputes in a contract?
Negotiation
49
Acceptance (Risk)
choosing to deal with it when and if it occur ex) sandbags for flooding from a storm
50
which is the document that will list all possible threats and opportunities that could occur during the project?
Risk Register
51
what is NOT included in the cost baseline?
Management Reserves (but they are included in budget)
52
What is true of the schedule management plan?
Can be formal or informal, highly detailed or broad in nature depending on the project. Is a key input to "Define Activities"
53
Who assists the PM in managing difficult stakeholders as needed?
Project Sponsor
54
Risk Owner
-Responsible for planning a response plan, ensuring the plan is implemented when needed, and taking any corrective actions needed to handle the risk during the implementation of the plan.
55
What mindset contains 4 paired values + 12 principles?
Agile Manifesto
56
Velocity
average number of story points an Agile team is completing in their sprints
57
When conducting an Agile Suitability Assessment, What three areas are you looking at?
Culture, project itself, & the team
58
Monte Carlo Simulation.
A method of identifying the potential impacts of risk and uncertainty using multiple iterations of a computer model to develop a probability distribution of a range of outcomes that could result from a decision or course of action
59
Net Promoter Score
An index that measures the willingness of customers to recommend an organization’s products or services to others.