Planning Test 2 Flashcards

(169 cards)

1
Q

Competing constraints include

Schedule
Budget
Resources
All of the above

A

All of the above

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

During the planning phase, auditors review processes and procedures and help control how they are implemented. Project ______ can have unforeseen effects on timely completion.

results
risks
ethics
approach

A

risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Which of the following documents is a very sensitive document that must not be shared outside the project management team?

Stakeholder engagement plan
Communication management plan
Change management plan
Scope management plan

A

Stakeholder engagement plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The below organizational process assets are inputs to the Plan Stakeholder Engagement process. Which of the following organizational process assets is of particular importance to this process?

Templates
Policies and procedures
Configuration management knowledge base
Lessons learned from past similar projects

A

Lessons learned from past similar projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Which of the following indicates project stakeholders current and desired engagement levels?

Stakeholder register
Stakeholder assessment matrix
Power/influence grid
Salience model

A

Stakeholder assessment matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Stakeholder engagement levels include:

Aggressive
Passive
Supportive
Risky

A

Supportive

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When a project manager participates in networking, connections, and alliances, they are exhibiting

Relational power
Persuasive power
Ingratiating power
Personal power

A

Relational power

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Another name for positional power for project managers is

informal
formal
expert
punitive

A

formal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The ability to understand and manage people is an example of what type of personality trait?

Social
Systemic
Political
Managerial

A

Social

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The imposition of obligation or sense of duty by the project manager is an example of what type of power?

Guilt-based
Avoiding
Persuasive
Ingratiating

A

Guilt-based

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The ability to invoke discipline is an example of what kind of power?

Guilt-based
Reward-oriented
Referent
Punitive

A

Punitive

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The use of flattery is an example of what type of power?

Pressure-based
Ingratiating
Avoiding
Referent

A

Ingratiating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The ability to think abstractly and to innovate is an example of what personality trait?

Authentic
Cultural
Creative
Political

A

Creative

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When the project manager explains the essential business aspects of a project they are exhibiting

technical project management skills
leadership skills
strategic and business management skills
control feedback

A

strategic and business management skills

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

A _______ would be a subsidiary plan included in the project management plan

project control plan
risk management plan
project scope statement
project charter

A

risk management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

In Develop Project Management Plan, expert judgment is used to

tailor the process
develop technical details
determine resources
all of the above

A

tailor the process
develop technical details
determine resources
all of the above are correct.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Enterprise Environmental Factors used in developing the Project Management Plan include:

governmental standards
risk register
quality management
all of the above

A

governmental standards

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

The Project Management Plan documents planning process outputs, such as

how changes will be monitored and controlled.
communication techniques among stakeholders.
how work will be executed to accomplish objectives.
all of the above.

A

how changes will be monitored and controlled.
communication techniques among stakeholders.
how work will be executed to accomplish objectives.
all of the above are correct.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What document defines how the project will be executed, monitored, and controlled?

T & M contract
The WBS
The Project Management Plan
SPI

A

The Project Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Project files containing project scope, cost, schedule, and performance baselines are part of the organizational processes and procedures used for

developing histograms
avoiding risk
developing the project management plan
none of the above

A

developing the project management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Which of the following is not a tailoring consideration in Project Integration Management?

Change
Governance
The cost baseline
Benefits

A

The cost baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

The project scope statement

details the needs of the project.
is a statement of ‘what needs to be done’.
states the project objective.
defines the potential risks that might deter success.

A

is a statement of ‘what needs to be done’.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Tools and techniques used to define scope include

product review.
expert judgment.
alternative factors.
all of the above.

A

expert judgment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

A work package is

a risk-mitigating component of the WBS.
A group of work components performed during the course of a project.
a document that defines and describes each component in the WBS.
a project work component at the lowest level of the WBS.

A

a project work component at the lowest level of the WBS.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
What Define Scope output details the project's deliverables and the work required to create the deliverables? The project charter. The project boundaries. The project scope statement. The project scope management plan.
The project scope statement.
26
When developing the product scope description, the project management team must describe deliverables at a summary level or greater detail. define the process and criteria for accepting products. list and describe specific project constraints associated with the project scope that limit options toward product development. provide sufficient detail to support later project scope planning.
provide sufficient detail to support later project scope planning.
27
Items in the project scope statement include The scope baseline. The WBS dictionary. the WBS. Project constraints.
Project constraints.
28
A project manager uses the WBS To see how planned activities are related to overall performance. To see how planned activities are related to overall budgeting and scheduling. To see who is responsible for designated planned activities. All of the above.
All of the above.
29
Project Requirements can include security requirements. business requirements. technical requirements. all of the above.
all of the above.
30
Scheduled work, cost estimates, and work to be monitored and controlled, are contained in the WBS dictionary. the lowest level WBS components. work performance reports. the scope baseline.
the lowest level WBS components.
31
Imposed dates for specific activity completion or project deliverables are called completion dates. schedule activities. schedule milestones. delivery date.
schedule milestones.
32
Components of the scope baseline include: SBS WBS dictionary Product scope none of the above
WBS dictionary
33
The project scope baseline contains the initial WBS. Capital investment control. Human resources Project procedures.
the initial WBS.
34
A WBS is A hierarchy that defines and organizes project work. A technique for evaluating a component or product during a project phase. A common approach to implementing a quality improvement project program. A contractual component that designates how activity time and materials are used throughout the duration of the project.
A hierarchy that defines and organizes project work.
35
Resources used to define scope include: consultants stakeholders industry groups all of the above
all of the above
36
Requirements documentation includes Quality requirements Acceptance criteria Training requirements all of the above
all of the above
37
What type of sequence dependencies involve physical limitations, such as having to complete one activity before the next one can begin? External. Mandatory. Internal. Discretionary.
Mandatory.
38
The foundation has to be built before the house framing can begin. This is an example of an external dependency. soft or preferred logic. hard logic. discretionary dependency.
hard logic.
39
A logical relationship in which a successor activity cannot start until a predecessor activity has finished is Start-to-Start Start-to-Finish Finish-to-Start Finish-to-Finish
Finish-to-Start
40
What type of precedence relationship is the most commonly used? Start-to-Finish. Finish-to-Start. Start-to-Start. Finish-to-Finish.
Finish-to-Start.
41
In Schedule Management, scaling factors to consider for agile environments include all except team size geographical distribution regulatory compliance industrial landscape
industrial landscape
42
Earned value, red-yellow-green, and percentage complete are examples of progress tracking product novelty project complexity pace
progress tracking
43
Types of dependencies, or precedence relationships, PDM uses include: Start-to-Finish. Beginning-to-Completion. Start-to-Interval-to-End. Start-to-Phase-to-Phase-to-Finish.
Start-to-Finish.
44
Inputs to Estimate Activity Durations include all except Activity attributes Change log Assumptions log Activity list
Change log
45
Discretionary dependencies usually are based on best practices. involve both project and non-project activities. are referred to as hard logic. never rely on historical project data.
are based on best practices.
46
Testing schedule activity software is dependent upon delivery of the hardware. Conducting an environmental impact study must be done before a project is constructed near a wetlands area. These are examples of Soft logic dependencies. Forgone dependencies. External dependencies. Internal dependencies.
External dependencies.
47
What helps to minimize scope creep? Punitive measures Lassiez-faire management Task alignment Time-boxing
Time-boxing
48
What characterizes the Start-to-Start dependency? The successor activity depends on the initiation of the predecessor activity. Initiation of the successor activity depends upon the completion of the predecessor activity. Initiation of the successor activity depends upon the initiation of the predecessor activity. Completion of the successor activity depends upon the completion of the predecessor activity.
Initiation of the successor activity depends upon the initiation of the predecessor activity.
49
What type of precedence relationship completion of the successor activity depends on the initiation of the predecessor activity? Start-to-Finish. Finish-to-Start. Start-to-Start. Finish-to-Finish.
Start-to-Finish.
50
Given a finish-to-start dependency, the project manger finds he has to build in a 28-day _____ period into the project schedule to ensure a concrete foundation has cured. lead gap break lag
lag
51
_______is/ are updated to include the defined logical relationships and any associated leads and lags. The project schedule network diagrams The activity list Activity attributes Requested changes
Activity attributes
52
What type of precedence relationship is the least used? Start-to-Finish. Finish-to-Start. Start-to-Start. Finish-to-Finish.
Start-to-Finish.
53
A logical relationship in which a successor activity cannot finish until a predecessor activity has finished is: Start-to-Start Start-to-Finish Finish-to-Finish Finish-to-Start
Finish-to-Finish
54
Tools and Techniques used in Estimate Activity Durations include all except Associative estimating Analagous estimating Three-point estimating Bottom-up estimating
Associative estimating
55
Tools used to sequence activities include: PDM frequency determination sequence tags all of the above
PDM
56
A Plan Quality Management technique that involves a group of members and general data gathering, used to identify risks or solutions, is brainstorming. decision-making. analysis. flowcharting.
brainstorming.
57
A Quality Management Plan may be formal informal detailed all of the above
all of the above
58
What quality planning technique helps optimize products and processes by identifying which factors may influence specific products or processes under development or production? Performance designing. Design of experiments. Issue logging. Design of experience.
design of experiments.
59
What quality planning technique creates a visual diagram of system process inputs, process actions, and outputs for a project? Affinity diagramming. Decision-making. Analysis. Flowcharting.
Flowcharting.
60
To be effective, a planned recognition and rewards system should be based on ________ under a person's control. activities and schedules schedule and performance activities and performance behavior and activities
activities and performance
61
What should be considered when planning the acquisition of project team members? Budget. Available sources. Internal and external assistance. All of the above.
All of the above.
62
______ determines the method and timing of releasing team members, to effect smooth project phase transitions, improve morale, and optimize time and budget. Staff release plan Schedule management A timetable Resource management
Staff release plan
63
The resource management plan must be updated when roles and responsibilities change. when there are changes in the project scope. weekly. after each project.
when roles and responsibilities change.
64
A RACI chart is seldom used used to ensure clear assignment of roles and responsibilities only used on programs is similar to a histogram
used to ensure clear assignment of roles and responsibilities
65
What is the purpose of having resource calendars? To make changing the staffing management plan easier. To improve cohesiveness within the team. To update the project charter more effectively. To create a reliable final schedule.
To create a reliable final schedule.
66
What information is contained in the communications management plan? Information to be communicated. General level of noise factors. Required communication management skills. Methods of reporting risk.
Information to be communicated.
67
A communication management plan can be: formal informal detailed all of the above
all of the above
68
_____ risks determines which risks might affect the project and documents their characteristics. Identify Analyze Plan Monitor and control
Identify
69
______ contribute to the effectiveness and quality of risk identification Risk categories Budgeting factors Budgeting categories Roles and responsibilities
Risk categories
70
What enterprise environmental factor inputs are used in Identify Risks? Commercial databases. Benchmark information. Industry studies. All of the above.
All of the above.
71
What organizational process assets are used in Identify Risks? The project scope statement. Previous project files. Schedule and cost information. Plans, assumptions, and constraints information.
Previous project files.
72
The period of time that may elapse after a risk has occurred before its impact is discovered is Urgency Proximity Connectivity Dormancy
Dormancy
73
The risk management plan includes reasoning methodology cost none of the above
methodology
74
The ______ hierarchically organizes identified project risks arranged by risk category and subcategory that identifies the areas and causes of potential risks. WBS PBS RRS RBS
RBS
75
The quality and credibility of the qualitative risk analysis process requires varying levels of the risk______ duration and significance to the project. scope and degree. probabilities and impacts. significance and impact.
probabilities and impacts.
76
The ______ scale reflects the significance of negative threats or positive opportunities on each project objective. impact relative impact non-linear impact matrix
impact
77
The Probability and Impact Matrix chart is used To determine the degree of risk impact compared to similar past project risk impacts. To prioritize risks. To see causes of risks. To determine probability.
To prioritize risks.
78
Risks are typically prioritized by Time impact. Potential time and cost expenditures. Impact to project objectives. organization's and stakeholders' criteria.
Impact to project objectives.
79
The risk management plan reporting formats describe the ______ which defines how the outcomes of the process will be documented, analyzed, and communicated. risk identification output qualitative and quantitative analysis scope of risk content and format of the risk register
content and format of the risk register
80
Who should be responsible for risk identification activities? The project manager, project team members, and those responsible for directly managing project risks. The organization and stakeholders. Risk management experts. All project personnel.
All project personnel.
81
Risk identification is an iterative process because it typically leads to risk response analysis new risks become known as the project progresses. it can be used in qualitative analysis. it guarantees effective risk response.
new risks become known as the project progresses.
82
A grid that maps the probability of each risk occurrence and its impact on project objectives if that risk occurs is: impact relative impact probability and impact matrix impact matrix
probability and impact matrix
83
Cost-plus-incentive-fee contracts reimburse the seller for allowable costs for performing the contract work plus a fixed percentage for meeting or exceeding contract requirements. a graduated fee based on early schedule completion milestones. a fee calculated as an agreed-upon percentage of costs. a predetermined fee based on achieving certain performance objectives.
a predetermined fee based on achieving certain performance objectives.
84
______ contracts involve payment to the seller for the seller's actual costs, plus a fee, which typically represents the seller's profit Cost-plus Lump sum Fixed-price Cost-reimbursable
Cost-reimbursable
85
"Buy" decision analyses include both direct and indirect costs. The buy-side of the analysis includes out of pocket costs to purchase costs for risk analysis cost avoidance cost estimates
out of pocket costs to purchase
86
______ contracts reimburse the seller for allowable costs for performing the contract work plus a fixed fee payment calculated as a percentage of the estimated project costs. Cost-plus-fixed-fee. Cost-plus-incentive-fee. Cost-plus-percentage-of-cost-fee. Time and materials
Cost-plus-fixed-fee.
87
____ are "hard costs" that include labor, subcontractors, and materials Project overhead Company overhead Direct costs Indirect costs
Direct costs
88
_______ contracts may include incentive clauses where the seller receives an incentive or bonus payment if project objectives are met or exceeded. Cost-reimbursable Cost-plus-incentive Cost-plus-fixed price Cost-plus
Cost-reimbursable
89
A contract that only pays the majority of the fee based on satisfaction of certain broad subjective performance criteria is: Time and materials Cost plus award fee Cost plus incentive fee Cost plus fixed fee
Cost plus award fee
90
Any project budget constraints are _____ the make-or-buy decision. separate from subtracted from divisions of factored into
factored into
91
_______ contracts are hybrid contractual agreements that are combined cost-reimbursable and fixed-price contracts based on duration of performance and the exact quantity of items to be delivered. Cost-plus-fixed-fee Time and materials Cost-plus-incentive-fee Cost-plus-percentage-of-cost-fee
Time and materials
92
Jack was in the process of creating the WBS for a project, when Joe informed him of some discrepancies he'd found in the scope statement. Jack agreed the scope was not properly defined and proceeded with the SBS for the project, because the scope statement was already approved. to speak with the project sponsor and customer about the gaps in the scope statement. to create an informal proposal for a separate project, which would provide for the gap in the current project scope. to include task recommendations by Joe in the WBS.
to speak with the project sponsor and customer about the gaps in the scope statement.
93
The basic responsibilities of all managers are controlling and monitoring. planning and supervision. communicating and organizing. all of the above
all of the above
94
"Good" objectives should be flexible. achievable. abstract. substantial.
achievable.
95
Project managers are generally responsible for team relations and details of project phases. project performance and completion. project assignments and delegation. project technology and final documentation.
project performance and completion.
96
Plans are characterized and classified according to their function duration objectives all of the above
all of the above
97
What is the first step in developing an action planning model, or project plan? Determine the people who should be involved in furthering the plan. Identify the planning purpose and the direction of the plan. Determine tasks to be done. Develop a timeline for the planned operations and project.
Identify the planning purpose and the direction of the plan.
98
Tailoring considerations in project scope management include Validation and control Limits and balances Source management The WBS
Validation and control
99
The scope baseline includes WBS WBS dictionary project scope statement all of the above
all of the above
100
The _________ is built upon the major deliverables, assumptions, and constraints project scope statement project charter project scope control product scope
project scope statement
101
A tool used in creating the WBS is: work histogram composition decomposition decentralization
decomposition
102
The project team uses scope definition techniques such as product breakdown, value engineering, and systems analyses for stakeholder analyses. to determine product scope. for product analyses. to determine project requirements.
for product analyses.
103
The account where scope, budget, actual cost, and schedule are integrated at a management control point and compared to earned value to measure performance, is a planning account. control account. performance account. planning package.
control account.
104
"Rolling wave planning" is the interaction among the processes within the Planning Process. progressive detailing of the project management plan. the facilitation of activities across multiple processes. the continual process of evaluation and refining the project scope.
progressive detailing of the project management plan.
105
________ are tools and techniques used to define project scope. Expert judgment and meetings Templates, forms, and the scope baseline The PMIS and baseline Established monitoring and controls
Expert judgment and meetings
106
What information is used to develop the project management plan and detailed project scope? Historical information Project charter information The preliminary project scope statement All of the above.
All of the above.
107
The project charter and the stakeholder register are _____ for collect requirements. risks assets outputs inputs
inputs
108
Brainstorming is a technique the management team uses to identify stakeholder expectations and how to most effectively accomplish them. determine the least risky methods and procedures in project execution. develop feasibility, overcome constraints, and achieve assumptions. generate alternative approaches to performing work and executing the project.
generate alternative approaches to performing work and executing the project.
109
Based on project needs, the project scope management plan may be formal or informal. formal. informal and concise. formal and highly detailed.
formal or informal.
110
The ________ addresses and documents project deliverables, boundaries, control, and acceptance project charter project plan contract project scope
project scope
111
A ______ is a WBS planning component below the control account but above the work package, used for planning known work that does not have detailed activities planning account. control package. performance account. planning package.
planning package.
112
The project scope management plan is intended to: Help the management team define and document project scope. provide guidance on how project scope should be managed and controlled. enable the creation of the WBS. All of the above.
All of the above.
113
The SOW references business need project stakeholders tactical approach merger expansion
business need
114
An automaker building more fuel-efficient cars due to gas shortages is an example of what type of business case? organizational need customer request market demand ecological impacts
market demand
115
What is a "precedence relationship? A dependency. The interaction that determines the logical successor activity. The end result of the schedule network. The result of a logical relationship.
A dependency.
116
The activity list provides the project team members a detailed description of the work to be completed overlapping application areas dependencies among schedule activities activity risks
a detailed description of the work to be completed
117
Activity attributes are used To ensure project accuracy. To establish risk milestones. To develop the project schedule. To decide begin and end project dates.
To develop the project schedule.
118
The schedule model is also referred to as the durations dependencies other planning information all of the above
all of the above
119
Project schedule management processes include: define activities sequence activities estimate activity durations all of the above
all of the above
120
Activity attributes for each schedule activity can include the time lag. resource requirements. person responsible for executing the work. any of the above.
any of the above.
121
Inputs to estimate activity durations include activity charter resource histogram activity attributes project document updates
activity attributes
122
What distinguishes schedule activities from other milestones or deliverables? They are ongoing. They have an estimated duration and cost. They measure schedule performance. They involve software, which is used in conjunction with manual methods to perform schedule networks.
They have an estimated duration and cost.
123
Which diagramming method uses four types of dependencies? schedule network diagram template (SNT) arrow diagramming method (ADM) precedence diagramming method (PDM) dependency diagramming network (DDN)
precedence diagramming method (PDM)
124
Progressive elaboration planning, where short-term work is planned in detail and future work is planned as the project progresses, is schedule control. rolling wave planning. scope planning. progressive term planning.
rolling wave planning.
125
The activity list includes the activity identifier and scope of work for each schedule activity. _______ is/are an example of the schedule activity's scope of work. In accordance with r905.82 of Residential Code, 2006. Sheets 7 and 8 of 14 274 cy 2000psi concrete All of the above
All of the above
126
Decomposition applied to activity definition involves subdividing project work packages into subsets. units. modules. activities.
activities.
127
Sequence activity outputs include updating the following project documents activity list activity attributes assumption log all of the above
all of the above
128
What input is required to develop activity sequencing? Activity attributes. Work performance information. Deliverables. Schedule network templates.
Activity attributes.
129
What impact does the project scope statement have on activity sequencing? Product cost can add constraints. Product characteristics can affect activity sequencing. Imposed time can affect sequencing sub-activities. Project risks can require more logical relationships.
Product characteristics can affect activity sequencing.
130
Schedule activities are logically sequenced using PDM PMD RDM ADT
PDM
131
What process involves identifying and documenting the logical relationship among schedule activities? Precedence. Dependency scheduling. Activity sequencing. Activity resource estimating.
Activity sequencing.
132
A mandatory milestone is one that is based on project requirements. is based on historical information. is required by the contract. is used in the cost schedule.
is required by the contract.
133
A general cost estimating rule is: When the project experiences a negative risk event, the cost of the project will almost always require the schedule be expedited. decrease and delay the schedule. increase and delay the schedule. increase which will require project or phase replanning.
increase and delay the schedule.
134
______ are budgets that are not included in the project cost baseline, but are included in the budget for unplanned changes to the project scope and cost Management reserves Parametric reserves Cost aggregation allowances Funding reconciliation accounts
Management reserves
135
Cost budgeting involves Identification of various costing alternatives. Aggregating estimated costs of work packages for a cost baseline. Monitoring impacts to cost and managing changes. Estimating how to obtain the most productivity for the least capital outlay.
Aggregating estimated costs of work packages for a cost baseline.
136
Schedule activity duration estimates affect cost estimates that use resources such as materials not prone to seasonal price variations. fixed overhead allowances. union labor. staff and regular employees.
union labor.
137
The cost estimating technique that produces a higher degree of accuracy using a statistical relationship between historical data and the targeted variable, is performing a vendor bid analysis. reserve analysis. parametric cost estimating. resource costing.
parametric cost estimating.
138
A quantitative assessment of likely costs of all resources required to complete schedule activities is Cost budgeting Cost management The cost estimate The cost aggregate
The cost estimate
139
Tools for estimating costs include bottom-down estimating top-up estimating bottom-up estimating risk factors
bottom-up estimating
140
The project estimator determines resource cost rates, such as the unit cost price for topsoil purchased by the cubic yard by requesting and comparing price quotes. obtaining data from commercial databases. obtaining data from published seller price lists. Any of the above.
Any of the above.
141
________ cost estimating uses expert judgment, is less costly than other cost estimating techniques, and is frequently used to estimate costs when there is a limited amount of detailed information about a project. Attribute Analogous Bottom-up Parametric
Analogous
142
Parametric models are mathematical models used to predict total project costs. They are simple, and most reliable when only current information is used to develop the model. funds expenditures can be reconciled. the model is scalable. the model is specific and used for small projects.
the model is scalable.
143
Contingency reserves are Funds used at the discretion of the project manager to deal with unknowns related to the project scope. Estimated costs allocated by contractors in the event they overrun the project budget. Estimated costs the contractor holds in reserve to pay for project delays. A project buffer dedicated for litigations.
Funds used at the discretion of the project manager to deal with unknowns related to the project scope.
144
Budgeting inputs include formal periodic limitations of project funds expenditures that are contained in project charters or contracts. These constraints are part of the budget which is provided by the Project schedule Activity cost estimate Project Scope Baseline Risk Register
Project Scope Baseline
145
______ involves estimating the cost of individual work packages or schedule activities with the lowest level of detail. Vendor bid analysis. Reserve analysis. Bottom-up estimating. Monte Carlo analysis.
Bottom-up estimating.
146
The supporting documentation necessary to support the schedule cost estimate includes Documented constraints. Documented allowances, reserves, and contingencies. Documented risks. Documented retainage.
Documented constraints.
147
Inputs to estimate costs include all of the following EXCEPT code of conduct project management plan risk register project schedule
code of conduct
148
Enterprise environmental factors that are inputs into quality management include Organizational policies, procedures, and guidelines. Lessons learned and knowledge base. Quality metrics and organizational assets. government agency regulations.
government agency regulations.
149
A fundamental principle of modern quality management is quality is designed-in, not planned-in. quality is built-in, not inspected-in. quality is inspected-in, not designed-in. quality is planned-, designed-, and inspected-in.
quality is built-in, not inspected-in.
150
Plan Quality Management is performed during activity resource estimating. as part of the project development process. in parallel with other planning processes. after quality controls are in place.
in parallel with other planning processes.
151
The "cost of quality" is The cost to fix defects. The total cost of all quality-related efforts. The total cost of requested project changes and corrections. The cost of inspection resources.
The total cost of all quality-related efforts.
152
______ involves identifying which quality standards are relevant to the project and deciding how to satisfy them. Plan Quality Management Quality control Quality planning Quality management
Plan Quality Management
153
An example of a prevention cost is: Safety. Warranty work. Training. Unauthorized changes.
Training.
154
The basis for quality improvement is Plan-do-check-act cycle. TQM Six Sigma COQ
Plan-do-check-act cycle.
155
Tools for Plan Quality Management include: Cost-benefit analysis Cost of quality Control charts All of the above
All of the above
156
A project organization chart graphically displays Risk and quality assurance activities. Project networks and activities. Required work and team members. Project team members and their reporting relationships.
Project team members and their reporting relationships.
157
Matrix-based, RAM charts show relationships between roles, responsibility, and authority for projects. risk and quality planning activities. project networks and activities. required work and team members.
required work and team members.
158
Hierarchical type charts that show how project deliverables are divided into work packages, and which show high-levels of responsibility, are WBS OBS RBS BBS
WBS
159
The traditional ______ -type organizational chart shows positions and relationships in a top-down format matrix hierarchical. text-oriented flowchart
hierarchical.
160
When listing human resources roles and responsibilities needed to complete the project the following should be addressed: Alliances. Working relationships. Minority status or special considerations. Role clarity and boundaries.
Role clarity and boundaries.
161
What organizational breakdown chart would best display an organization's existing departments, units, or teams? WBS OBS RBS BBS
OBS
162
Resource breakdown structure hierarchical charts are used to break down the project by responsibilities. routines. resources. risks.
resources.
163
_______ provides information about the way teams and organizational units react and behave Project organization Organizational behavior Organizational theory Organizational process
Organizational theory
164
Resource requirements are used To determine human resource needs. To schedule human resources. To monitor human resource activities. To determine training needs.
To determine human resource needs.
165
______ are documented formats that ensure each work package has an unambiguous owner and that all team members clearly understand their roles and responsibilities Matrix templates Networks Organizational charts Schedules of work
Organizational charts
166
A "role" designates what portion on the project a person is accountable for. Project roles should be ______ to help ensure project success clear concerning authority, responsibilities and boundaries assigned and closely monitored commensurate with education and experience broad-based
clear concerning authority, responsibilities and boundaries
167
Team member responsibilities that require detailed descriptions are specified in _______ formats matrix hierarchical text-oriented flowchart
text-oriented
168
Tools used in estimate activity resources include top-down estimating synergistic estimating analogous estimating release criteria
analogous estimating
169
Which of the following is NOT a stakeholder management process?
Control Stakeholder Management