PMP Flashcards

1
Q

Cultural norm

A

Describes the culture and style of how an organization operates. The accepted practices, culture, ideas, vision, and nature of an organization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Fast tracking

A

A schedule compression technique that allows phases to overlap in order to compress the schedule and finish the job faster. Fast tracking does increase project risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Phase-end review

A

Ensures that all the phase obligations have been met to allow the project to move onto the next phases of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Adaptive project life cycle

A

changes happen often

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Kill point

A

An opportunity to halt the project based on project performance in the previous phase. Kill point typically come at the end of a project phase and are also known as phase gates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Deliverable

A

Something that can be verified and measures.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Projectized structure

A

Group of employees, collocated or not, by activities on a particular project. The project manager in a projectized structure may have complete, or very close to complete, power over the project team.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Level of failing for the project

A

Projects are most likely to fail at the start of the project. As the project moves closer to the project completion, its odds of finishing successfully increase.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Functional organization

A

PM has little to no power and the functional manager has all of the power.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Weak matrix organization

A

The functional manager has the power over the project funding. In a weak matrix, the functional manager is likely to be the project sponsor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Application areas

A

The areas of discipline that a project may center upon.. Consider technology, law, sales, marketing, and construction among many others.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Assumption log

A

A document that clearly identifies and track assumptions that are made in the project. All assumptions need to be tested for their validity and the outcome of the test should be recorded.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Autocratic

A

The project manager makes all of the decisions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Avoidance

A

This is one response to a risk event. The risk is avoided by planning a different technique to remove the risk from the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Benchmarking

A

A process of using prior projects within or external to performing organization to compare and set standards for processes and results.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Benefit measurement methods

A

Project selection methods that compare the benefits of projects to determine which project the organization should select for investment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Adjourning

A

The final stage of the team development; once the project is done, the team moves onto other assignments either as a unit or the project team ream is disbanded and individual team members to onto other work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Affinity diagram

A

Clusters like ideas together and allow for decomposition of ideas to compare and contrast project requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Analogous estimating

A

This relies on historical information to predict estimates for current projects. Analogous estimating is also known as top-down estimating and is a form of expert judgment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Activity on node

A

A network diagramming approach that places the activities on a node in the project network diagram.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Activity sequencing

A

The process of mapping the project activities in the order in which the work should be completed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Actual cost

A

The amount funds the project has spent to date. The difference between actual costs and the earned value will reveal the cost variance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

360-degree appraisal

A

A performance review completed by a person’s peers, managers, and subordinates. It’s called a 360-degree appraisal as it’s a circle of reviews by people at different levels of an organization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Acceptance

A

This is a response to a risk event, generally made when the probability of the event and/or impact are small. It is used when mitigation, transference, or avoidance are not selected.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Active listening

A

This occurs when the receiver confirms that message is being received by feedback, questions, prompts for clarity, and other signs of having received the message.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Activity attributes

A

Activities that special conditions, requirements, risks, and other conditions should be documented.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Activity cost estimates

A

The cost of resources including materials, services, and when warranted, labor should be estimated.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Activity list

A

A listing of all of the project activities required to complete each project phase or the entire project. This list is an input to the project network diagram.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Benefit/cost analysis

A

The process of determining the pros and cons of any project, process, product, or activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Benefit/cost ratios

A

Shows the proportion of benefits to costs; for example 4:1 would equate to four benefits and just one cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Bid

A

A document from the seller to the buyer. Used when price is the determining factor in the decision-making process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

Bidder conferences

A

A meeting with prospective sellers to ensure all sellers have a clear understanding of the product or services to be procured. Bidder conferences allow sellers to query the buyer on the details of the product to help ensure that the proposal the seller creates is adequate and appropriate for the proposed agreement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

Bottom-up estimating

A

A technique where an estimate for each component in the WBS is developed and then totaled for an overall project budget, but it provides the most accurate estimate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

Brainstorming

A

The most common approach to risk identification; it is performed by a project team to identify the risks within the project. A multidisciplinary team, hosted by a project facilitator, can also perform brainstorming.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

Budget at completion

A

The predicted budget for the project; what the project should cost when it is completed. Budget at completion represents 100% of the planned value for the project’s completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

Cause-and-effect diagrams

A

Used for root cause analysis of what factors are creating the risks within the project. The goal is to identify and treat the root of the problem, not the symptom.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

Centralized contracting

A

All contracts for all projects need to be approved through a central contracting unit within the performing organization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

Change Control Board

A

A group of decision makers that review proposed project changes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

Change Control system

A

A predefined set of activities, forms, and procedures to entertain project change requests.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

Change log

A

As changes to the project time, cost, or scope enter the project they should be recorded in the change log for future reference.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

Change management plan

A

When changes are approved for a project, including time, cost, scope, or contract, then there needs to be a plan on how the project team will manage these new changes within the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

Chart of accounts

A

A coding system used by the performing organization’s accounting system to account for the project work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

Checklists

A

A listing of activities that workers check to ensure the work has been completed consistently; used in quality control.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

Closing

A

The fifth of five project management process groups. It contains the processes responsible for closing a project, a project phase, or the procurement relationships.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

Coercive power

A

The project manager uses fear and threats to manage the project team.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

Collective bargaining agreements

A

These are contractual agreements initiated by employee groups, unions, or other labor organizations; they may act as constraint on the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

Communications formula

A

The formula “N(N-1)/2” shows the number of communication channels in a project. N represents the total number of stakeholders.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

Communications management plan

A

A plan that documents and organizes the stakeholder needs for communication. This plan covers the communications system, its documentation, the flow of communication, modalities of communications, schedules for communications, information retrieval, and any other stakeholder requirements for communications.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

Composite structure

A

An organization structure that uses a blend of the functional, matrix, or projectized organization to operate and manage projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

Compromising

A

A conflict resolution method; this approach required both parties to give up something. The decision ultimately made is a blend of both sides of the argument. Because neither party completely wins, it is considered a lose-lose solution.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

Confidentiality

A

A project manager should keep certain aspects of a project confidential; consider contract negotiations, human resource issues, and trade secrets of the organization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

Configuration management

A

The control and documentation of the project’s product features and functions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

Conflict of interest

A

A situation where the project manager could influence a decision for personal gain.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

Constrained optimization methods

A

Complex mathematical models to determine the likelihood of a projects’ success. These models are used to determine which project an organization should chose for investment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

Constaints

A

Anything that limits the project manager’s options; for example, time, cost, and scope are always project constraint.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

Contingency reserve

A

A time or dollar amount allotted as a response to risk events that may occur within a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

Continuous process improvement

A

A goal of quality assurance to improve the project’s processes and deliverables; meshes with the project’s Process Improvement Plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

Contract

A

A legal, binding agreement, preferably written, between a buyer and seller detailing the requirements and obligations of both parties. Must include the offer, an acceptance, and consideration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

Contract administration

A

The process of ensuring that the buyer and the seller both perform to the specifications within the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
60
Q

Contract change control system

A

Defines the procedures for how contracts may be changed. Includes the paperwork, tracking, conditions, dispute resolution procedures, and the procedures for getting the changes approved within the performing organization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
61
Q

Contract closeout

A

A process for confirming that the obligations of the contract were met as expected. The project manager, the customer, key stakeholder, and, in some instances, the seller complete the product verification together to confirm the contract has been completed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
62
Q

Contract file

A

A complete indexed set of records of the procurement process incorporated into the administrative closure process. These records include financial information as well as information on the performance and acceptance of the procured work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
63
Q

Control charts

A

These illustrate the performance of a project over time. They map the result of inspections against a chart. Control charts are typically used in projects or operations that have repetitive activities such as manufacturing, test series, or help desk functions. Upper and lower control limits indicate if values are within control or out of control.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
64
Q

Cost baseline

A

This shows what the project is expected to spend. It’s usually shown in an S-curve and allows the project manager and management to predict when the project will be spending monies and over what duration. The purpose of the cost baseline is to measure and predict project performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
65
Q

Cost budgeting

A

A process of assigning a cost to an individual work package. This process shows costs over time. The cost budget results in an S-Curve that becomes the cost baseline for the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
66
Q

Cost change control

A

This is part of the Integrated Change Control System and documents the procedures to request, approved, an incorporate changes to project costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
67
Q

Cost control

A

An active process to control causes of cost change, to document cost changes, and to monitor cost changes, and to monitor cost fluctuations within the project. When changes occurs, the cost baseline must be updated.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
68
Q

Cost estimating

A

The process of calculating the costs, by category, of the identified resources to complete the project work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
69
Q

Cost management plan

A

Explains how variances to the costs of the project will be managed. The plan may be based on a range of acceptable variances

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
70
Q

Cost of conformance

A

The cost of completing the project work to satisfy the project scope and the expected level of quality. Examples include training, safety measures, and quality management activities. Also known as the cost of quality.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
71
Q

Cost of nonconformance

A

The cost of not completing the project with quality; includes wasted time for corrective actions, rework, wasted materials. This could mean loss of business, loss of sales, lawsuits. Also known as the cost of poor quality.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
72
Q

Cost performance index

A

The process of calculating the costs, by category, of the identified resources to complete the project work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
73
Q

Cost plus award fee

A

This contract requires the buyer to pay for all the project costs and give the seller an award fee based on the project performance, meeting certain project criteria, or other goals established by the buyer. The award fee can be tied to any factor the buyer determines and the factor doesn’t have to be exact.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
74
Q

Cost variance

A

The difference between the earned value and the actual costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
75
Q

Cost-reimbursable contracts

A

A contract that pays the seller for the product. In the payment to the seller, there is a profit margin the difference between the actual costs of the product and the sales amount.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
76
Q

Crashing

A

A duration compression technique that adds project resources to the project in an effort to reduce the amount of time allotted for effort-driven activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
77
Q

Critical chain method

A

A network diagramming approach that considers the availability or project resources and the project’s promised end date to determine the critical path(s) in the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
78
Q

Critical path method

A

A network diagramming approach that identifies the project activities which cannot be delayed or the project completion date will be late.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
79
Q

Culture shock

A

The initial reaction a person experiences when they’re in a foreign environment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
80
Q

Decision tree analysis

A

A type of analysis that determines which of two decisions is the best. The decision tree assists in calculating the value of the decision and determining which decision costs the least.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
81
Q

Decoder

A

This is a part of the communications model; it is the inverse of the encoder. If a message is encoded, a decoder translates it back to the usable format.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
82
Q

Decomposition

A

The breakdown of the project scope statement into the project’s work breakdown structure. The smallest item of the project’s decomposition into the WBS is called the work package.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
83
Q

Deliverable

A

A thing that a project creates; projects generally create many deliverables as part of the project work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
84
Q

Delphi technique

A

A method to query experts anonymously on foreseeable risks within the project, phase, or component of the project. The results of the survey are analyzed and organized and then circulated to the experts. There can be several rounds of anonymous discussions with the Delphi technique. The goal is to gain consensus on project risks, and the anonymous nature of the process ensures that no one expert’s advice overtly influences the opinion of another participant.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
85
Q

Democratic

A

The project team is involved in the decision making process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
86
Q

Design of experiments

A

This relies on statistical “what-if” scenarios to determine which variables within a project will result in the best outcome; it can also be used to eliminate a defect. The design of experiments approach is most often used on the product of the project, rather than the project itself.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
87
Q

Dictatorship

A

A group decision process where the person with the most power forces the decision even though the rest of the group may oppose the decision.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
88
Q

Direct costs

A

Costs incurred by the project in order for it to exist. Examples include equipment needed to complete the project work, salaries of the project team, and other expenses tied directly to the project’s existence.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
89
Q

Discretionary dependencies

A

The order of the project activities do not have to completed in a particular order so they can be done in the order of the project manager or the project team’s discretion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
90
Q

Duration estimates

A

The prediction of how long the project work will take to complete.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
91
Q

Earned value

A

The value of the work that has been completed and the budget for that work; EV=%Complete X BAC.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
92
Q

Earned value management

A

Earned value management integrates scope, schedule, and cost to give an objective, scalable point-in-time assessment of the project. EVM calculates the performance of the project and compares current performance against plan. EVM can also be an harbinger of things to come. Results early in the project can predict the likelihood of the project’s success of failure.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
93
Q

Effective listening

A

The receiver is involved in the listening experience by paying attention to visual clues by the speaker and to para-lingual intentions and by asking relevant questions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
94
Q

Encoder

A

Part of the communications model; the device or technology that packages the message to travel over the medium.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
95
Q

Enhance

A

To enhance a risk is to attempt to modify it probability to and/or its impacts to realize the most gains from the identified risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
96
Q

Estimate at completion

A

A hypothesis of what the total cost of the project will be. Before the project begins, the project manager completes an estimate for the project deliverables based on the WBS. As the project progresses, there will likely be some variances between what the cost estimate was and what the actual cost is. The EAC is calculated to predict what the new estimate at completion will be.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
97
Q

Estimate to complete

A

Represents how much more money is needed to complete the project work: ETC = EAC-AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
98
Q

Estimating publications

A

Typically a commercial reference to help the project estimator confirm and predict the accuracy of estimates. If a project manager elects to use one of these commercial databases, the estimate should include a pointer to this document for future reference and verification.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
99
Q

Ethics

A

Describes the personal, cultural, and organizational interpretation of right and wrong; project managers are to operate ethically and fairly.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
100
Q

Ethnocentrism

A

Happens when individuals measure and compare a foreigner’s action against their own local culture. The local typically believe their own culture is superior to the foreigner’s culture.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
101
Q

Evaluation criteria

A

Used to rate and score proposals from sellers. In some instances, such as a bid or quote, the evaluation criterion is focused just on the price the seller offers. In other instances, such as a proposal, the evaluation criteria can be multiple values: experience, references, certifications, and more.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
102
Q

Exceptional

A

The project manager only pays attention to the top ten percent of the project performers and the bottom ten percent of the project team performers.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
103
Q

Executing

A

The project management process group that carries out the project management plan to create the project deliverables.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
104
Q

Expectancy theory

A

People will behave on the basis of what they expect as a result of their behavior. In other words, people will work in relation to the expected reward of the work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
105
Q

Expert power

A

A type of power where the authority of the project manager comes from experience with the area that he project focuses on.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
106
Q

Exploit

A

The organization wants to ensure that the identified risk does happen to realized the positive impact associated with the risk event.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
107
Q

Facilitated workshops

A

A collection of stakeholders from around the organization that come together to analyze, discuss, and determine the project requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
108
Q

Feedback

A

Sender confirmation of the message by asking questions, requesting a response, or other confirmation signals.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
109
Q

Finish-to-finish

A

A relationship between project activities where the predecessor activities must finish before successor activities may finish.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
110
Q

Finish-to-start

A

A relationship between project activities where the predecessor activities mush finish before the successor activities may start; this is the most common network diagramming relationship type.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
111
Q

Fixed costs

A

Costs that remain the same throughout the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
112
Q

Fixed price with economic price adjustment contracts

A

A contract for long-term projects that may span years to complete the project work. The contract does define a fixed price with caveats for special categories of price fluctuation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
113
Q

Fixed-price contracts

A

Fixed-priced contracts are also known as Firm-Fixed-Price and Lump-Sum contracts. These contracts have a pre-set price that the vendor is obligated to perform the work or provide materials for the agreed price.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
114
Q

Float

A

A generic term to describe the amount of time an activity may delayed without delaying any successor activities start date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
115
Q

Flowcharting

A

A chart that illustrates how the parts of a system occur in sequence.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
116
Q

FNET

A

A project constraint that requires an activity to finish no earlier than a specific date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
117
Q

Focus groups

A

A conversation of stakeholders led by a moderator to elicit project requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
118
Q

Force majeure

A

A powerful and unexpected event, such as a hurricane or other disaster.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
119
Q

Forcing

A

A conflict resolution method where one person dominates or forces their point of view or solution to a conflict.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
120
Q

Forecasting

A

An educated estimate of how long the project will take to complete. Can also refer to how much the project may cost to complete.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
121
Q

Formal power

A

The type of power where the project manager has been assigned by senior management to be in charge of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
122
Q

Forming

A

The initial stage of team development; the project team meets and learns about their roles and responsibilities on the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
123
Q

Fragnets

A

A portion of the project that is usually contracted to a vendor to complete yet the project work is still represented in the project network diagram.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
124
Q

Function analysis

A

Related to value engineering, this allows team input to the problem, institutes a search for a logical solution, and tests the functions of the product so the results can be graphed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
125
Q

Functional managers

A

The managers of the permanent staff in each organizational department, line of business, or function as sales, finance, technology. Project managers and functional manages interact on project decisions that affect function, projects, and operations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
126
Q

Functional structure

A

An organization that group staff according to their expertise. Entities that have a clear division regarding business units and their associated responsibilities. Project manages in functional organization have little power and report to the functional managers and the project team all exist within one department.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
127
Q

Future value

A

A formula to predict the current amount of funds into a future amount of funds. The formula is: Future value = Present value(1+i)n where i is the value of return and n is the number of time periods.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
128
Q

Halo effect

A

When one attribute of a person influence a decision.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
129
Q

Hard logic

A

The project activities must be completed in a particular order; this is also known as mandatory dependencies.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
130
Q

Herzberg’s theory of motivation

A

Posits that there are two catalysts for workers: hygiene agents and motivating agents. Hygiene agents do nothing to motivate, but their absence demotivate workers. Hygiene agents are the expectation all workers have: job security, paychecks, clean and sage working conditions, a sense of belonging, civil working relationships, and other basic attributes associated with employment. Motivating agents are components such as reward, recognition, promotion, and other values that encourage individuals to succeed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
131
Q

Histogram

A

A bar chart; A Pareto diagram is an example of a histogram.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
132
Q

Historical information

A

Any information created in the past that can help the current project succeed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
133
Q

Human resources plan

A

Defines the management of the project human resources, timing of use, and enterprise environmental factors the project manager must adhere to in the organization when it comes to human resources management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
134
Q

Inappropriate compensation

A

The project manager is avoiding compensation, such as bribes. The project manager is to act in the best interest of the project and the organization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
135
Q

Indirect costs

A

These costs can be shared across multiple projects tha use the same resources – such as for a training room or piece of equipment.

136
Q

Influence diagram

A

An influence diagram charts out a decision problem. It identifies all of the elements, variables, decisions, and objectives – and how each factor may influence another.

137
Q

Initiating

A

The start an authorization of the project; the project manager is identified, the project is authorized through the charter, and the stakeholders are identified.

138
Q

Initial rate of return

A

A benefit measurement formula to calculate when the present value of the cash inflow equals the project’s original investment.

139
Q

Interviews

A

A requirements elicitation process to collect requirements from the project stakeholders.

140
Q

Invitation for bid

A

A document from the buyer to the seller. Requests the seller to provide a price for the procured product or service.

141
Q

Iron Triangle

A

A term used to describe the three constraints of every project: time, cost, and scope. The sides of the iron triangle must be kept in balance or the quality of the project will suffer.

142
Q

ISO 9000

A

An international standard that helps organization follow their own quality procedures. ISO 9000 is not a quality system, but a method of following procedures created by an organization.

143
Q

Issue log

A

Issues are decision that are usually in disagreement among tow or more parties. Issues are recorded in the issue log along with an issue owner designation, an issue date for resolution, and the eventual outcome of the issue.

144
Q

Issues

A

Any point of connection, debate, or decision that has not yet been made in the project that may affect the project’s success.

145
Q

Iterative relationships of project phases

A

Ideal for projects like research. The next phase of the project is not planned until the current phase of the project is underway. The direction of the project change based on the current work in the project, market conditions, or as more information is discovered.

146
Q

Knowledge areas

A

There are 10 knowledge areas within project management; each knowledge area is a specific portion of the project, and all 10 project mangement knowledge areas are interrelated.

147
Q

Lag

A

Time added to a project activity to delay its start time; lag time is considered positive time and it is sometimes called waiting time.

148
Q

Laissez faire

A

The project manager has a hands-off policy and the team entirely self-led regarding the decision-making process.

149
Q

Lead

A

Time added to activity to allow its start time to begin earlier than scheduled; lead time is negative time as it moves the activities closer to the project’s start date.

150
Q

Lessons learned

A

Ongoing collection of documentation about what has and has not worked in the project; the project manager and the project team participate in lessons learned creation.

151
Q

Letter of intent

A

Expresses the intention of the buyer to procure products or services from the seller. This is not a contract, but express intent to purchase so the seller can prepare for the work.

152
Q

Majority

A

A group decision process where a vote is offered and the majority wins.

153
Q

Make-or-buy analysis

A

Used in determining what part of the project scope to make and what part to purchase.

154
Q

Management by projects

A

An organization that uses projects to move the company forward is using the management-by-projects approach. These project-centric entities could manage any level of their work as a project.

155
Q

Mandatory dependencies

A

Project activities must happen in a particular order due to the nature of the work; also known as hard logic.

156
Q

Maslow’s Hierarchy of Needs

A

A theory that states that there are five layers of needs for all humans; physiological, safety, social, esteem, and the crowning jewel, self-actualization.

157
Q

Matrix structure

A

An organization that groups staff by function but openly shares resources on project teams throughout the organization. Project managers in a matrix structure share the power with functional management. There are 3 types of matrix structures: weak, balanced, and strong to describe the amount of authority for the project manager.

158
Q

MClelland’s Theory of Needs

A

People have three needs: achievement, affiliation, and power. One of the needs drives the person’s actions.

159
Q

McGregor’s Theory of X and Y

A

This theory states that “X” people are lazy, don’t want to work, and need to be micromanaged. “Y” people are self-led, motivated, and strive to accomplish.

160
Q

Medium

A

Part of the communications model; this is the path the message takes from the sender to the receiver. This is the modality in which the communication travels typically refers to an electronic model, such as email or the telephone.

161
Q

Mind mapping

A

A visual representation of like and opposing ideas, thoughts, and project requirements.

162
Q

Mitigation

A

Reducing the probability or impact of a risk.

163
Q

Monitoring and controlling

A

The project management process group responsible for ensuring that the project execution is completed according to the project management plan and expectations.

164
Q

Monte Carlo analysis

A

A what-if scenario to determine how scenarios may work out given any number of variables. The process doesn’t actually create out a specific answer, but a range of possible answers. When Monte Carlo is applied to a schedule, it can present, for example, the optimistic completion date, and the most likely completion date for each activity in the project.

165
Q

Murder boards

A

A group of decision makers that may determine to “kill” a proposed project before it is officially launched based on the board’s findings of the likelihood of the project’s success.

166
Q

Net present value

A

A benefit measurement formula used for project that span multiple years or quarters. NPV calculates the present value for each year or quarter of the project.

167
Q

Network templates

A

A network diagram based on previous similar projects that is adapted for the current project.

168
Q

Nominal group technique

A

A group creativity technique that follows the brainstorming model but ranks each brainstorm idea.

169
Q

Nonverbal

A

Approximately 55% of oral communication is non-verbal. Facial expression, hand gestures, and body language contribute to the message.

170
Q

Norming

A

Project team members go about getting the project work, begin to rely on one another, and generally complete their project assignments.

171
Q

Observation

A

A requirements elicitation process where the observer shadows a person to understand how they complete a process. Observers may be a participant observer or an invisible observer.

172
Q

Obligopoly

A

A market condition where the actions of one competitor affects the actions of all the other competitors.

173
Q

Operational definitions

A

The quantifiable terms and value used to measure a process, activity, or work result. Operational definitions are also known as metrics.

174
Q

Operations

A

The ongoing work of the business. Operations are a generic way to describe the activities that support the core functions of a business entity.

175
Q

Operations management

A

Operation managers deal directly with the income-generating products or services the company provides. Projects often affect the core business so these managers are stakeholders in these projects.

176
Q

Organizational breakdown structure

A

Though these chars are similar to the WBS, the breakdown is by department, units, or by team.

177
Q

Organizational charts

A

These show how an organization, such as a company or large project team, is ordered, reporting structures, and the flow of information.

178
Q

Ouchi’s Theory Z

A

This theory posits that workers are motivated by a sense of commitment, opportunity, and advancement. Workers will work if they are challenged and motivated.

179
Q

Overlapping relationship of phases

A

Allows project phases to overlap to compress the project duration. This is also known as fast track.

180
Q

Paralingual

A

The pitch, tone, and inflections in the senders’s voice affect the message being sent.

181
Q

Parametric estimating

A

Ideal for projects with repetitive work where a parameter, such as five hours per unit, is used to estimate the project duration.

182
Q

Parametric modeling

A

A mathematical model based on known parameters to predict the cost of a project. The parameters in the model can vary based on the type of work being done. A parameter can be cost per cubic yard, cost per unit, and so on.

183
Q

Pareto diagrams

A

A Pareto diagram is related to Pareto’s Law: 80% of the problems come from 20% of the issues (this is also known as the 80/20 rule). A Pareto diagram illustrates problems by assigned cause, from smallest to largest.

184
Q

Parkinson’s Law

A

Work expands to fill the amount of time allotted to it.

185
Q

Paypack period

A

The duration of time it takes a project to earn back the original investment.

186
Q

Performance reports

A

These formal reports define how the project is performing on time, cost, scope, quality and any other relevant information.

187
Q

Performing

A

If a project team can reach the performing stage of team development, they trust one another, work well together, and issues and problems get resolved quickly and effectively.

188
Q

Planned value

A

The worth of the work that should be completed by a specific time in the project schedule.

189
Q

Planning

A

The iterative process group where the intention of the project is determined and documented in the project management plan.

190
Q

Plurality

A

A group decision process approach allows the biggest section of a group to win even if a majority doesn’t exist.

191
Q

PMBOK Guide

A

The abbreviate definition for PMI’s A Guide to the Project Management Body of Knowledge.

192
Q

PMI Code of Ethics and Professional Conduct

A

A PMI document that defines the expectations of its members to act responsibly, respectfully, fairly, and honestly in their leadership of projects and programs.

193
Q

PMIS

A

A project management information system is typically a software system, such as MS Project, to assist the project manager in managing the project

194
Q

PMP

A

A PMP is certified by the Project Management Institute as a Project Management Professional.

195
Q

Portfolio management review board

A

A collection of organizational decision makers, usually executives, that review proposed project and programs for their value and return on investment for the organization.

196
Q

Precedence diagramming method

A

The most common method of arranging the project work visually. The PDM puts the activities in boxes, called nodes, and connects the boxes with arrows. The arrows represent the relationship and the dependencies of the work packages.

197
Q

Present value

A

A benefit measurement formula to determine what a future amount of funds is worth today. The formula is Present Value=Future Value/(1+i)n where i is the value of return and n is the number of time periods.

198
Q

Problem solving

A

The ability to determine the best solution for a problem in a quick and efficient manner.

199
Q

Process adjustments

A

When quality is lacking, process adjustment are needed for immediate corrective actions or for future preventative actions to ensure that quality improves. Process adjustment may qualify for a change reques and be funneled through the Change Control System as part of integration management.

200
Q

Procurement documents

A

All of the documents for purchasing, such as request for quotes, invitation to bid, request for proposal, and the response are stored as part of the project documentation.

201
Q

Product life cycle

A

A unique life, duration, and support of the thing a project creates. Product life cycles are separate from the project life cycle.

202
Q

Product scope

A

The attributes and characteristics of the deliverables the project is creating.

203
Q

Program manager

A

Coordinates the efforts of multiple projects working together in the program. Programs are comprised of projects, so the program manager is a stakeholder in each of the constituent projects within the program.

204
Q

Programs

A

A collection of projects working in unison to realize benefits that could not be achieved by managing each project independently of one another.

205
Q

Progress report

A

These provide current information on the project work completed to date.

206
Q

Progressive elaboration

A

The process of starting with a large idea and through incremental analysis, actions, and planning the idea becomes more and more specific. Progressive collaboration is the generally-accepted planning process for project management, wherein the project management team start very broad and work toward a specific, detailed plan.

207
Q

Project

A

An undertaking outside of normal operations to create a unique product, services, condition, or result. Projects are temporary while operations are ongoing.

208
Q

Project baselines

A

There are 3 baselines in a project which are used to measure project performance: cost, schedule, and scope.

209
Q

Project calendar

A

A calendar that defines the working times for the project. For example, a project may require the project team to work nights and weekends so as not to disturb the ongoing operations of the organization during working hours. In addition, the project calendar accounts for holidays, working hours, and work shifts the project will cover.

210
Q

Project charter

A

A document that authorizes the project, defines the high-level requirements, identifies the project manager and the project sponsor, and provide initial information about the project.

211
Q

Project communications management

A

One of the ten project management knowledge areas; it is the planning and management of communication among project stakeholders.

212
Q

Project cost management

A

One of the ten project management knowledge areas;; it is the estimating, budgeting, and controlling of the project expenses.

213
Q

Project customer/end user

A

The person or group that will use the project deliverable. In some instances, a project may have many different customers.

214
Q

Project funding requirements

A

In larger projects, this document identifies the timeline of when capital is required for the project to move forward. This document defines the amount of funds a project needs in order to reach its objectives and when the project funds are needed.

215
Q

Project governance

A

Defines the rules for a project and it’s up to the project manager to enforce the project governance to ensure the project’s ability to reach its objectives. The project management plan defines the project governance and how the project manager, the project team, and the organization will all follow the rules and policies within the project.

216
Q

Project human resource management

A

One of the ten project management knowledge areas;; projects are completed by people and the project manager generally oversee the management of the human resources on the project team.

217
Q

Project integration management

A

One of the ten project management knowledge areas;; this knowledge area coordinates the activities and completeness of the other 8 knowledge areas.

218
Q

Project life cycle

A

Unique to each project and comprised of phases of work. Project life cycle typically create a milestone and allow subsequent phases to begin.

219
Q

Project management

A

The management of the projects within an organization. It is the initiation, planning, executing, monitoring and controlling, and closing of the temporary endeavor of the project.

220
Q

Project management integration

A

A project management knowledge area that coordinates all of the effort of the project’s initiation, planning, executing, monitoring and controlling, and closing.

221
Q

Project Management Office (PMO)

A

Organizes and manages control over all projects within an organization. PMOs may also known as the program management office, or simply the program office. Coordinate all aspects, methodology, and nomenclature for project processes, templates, software, and resource assignment.

222
Q

Project management team

A

People on the project team that are involved with managing the project.

223
Q

Project manager

A

The person accountable for managing the project; guides the team through the project phases to completion.

224
Q

Project plan

A

A comprehensive document comprised o several subsidiary plans that communicates the intent and direction of the project.

225
Q

Project portfolio management

A

A management process to select the projects that should be invested in. Specifically, it is the selection process based on the need, profitability, and affordability of the proposed projects.

226
Q

Project procurement management

A

One of the ten project management knowledge areas; this knowledge area oversees the purchasing and contract administration for a project

227
Q

Project quality management

A

One of the ten project management knowledge areas;; this knowledge area defines quality assurance, quality control, and the quality policy for the project.

228
Q

Project risk management

A

One of the ten project management knowledge areas; creates the risk management plan, performs qualitative and quantitative risk analysis, plans risk responses, and monitors and controls the project risks.

229
Q

Project scope management

A

One of the ten project management knowledge areas;; responsible for collecting project requirements defining the project scope, create the WBS, performing scope verification, and controlling the project scope. The project scope statement includes the project scope description, product acceptance criteria, project deliverables, project exclusions, project assumptions and the project constraints.

230
Q

Project sponsor

A

Authorizes the project. This person or group ensures that the project manager has the necessary resources, including monies, to get the work done. The project sponsor is someone within the performing organization that has the power to authorize and sanction the project work, and is ultimately accountable for the project’s success.

231
Q

Project team

A

The collection of individuals that will work together to ensure the success of the project. The project manager works with the project team to guide, schedule, and oversee the project work. The project team completes the project work.

232
Q

Project time management

A

A project management knowledge area that defines the project activities, sequences project work, estimates resources and activity duration, and develops the project schedule. This knowledge area is also responsible for control the project schedule.

233
Q

Proposal

A

A document from the seller to the buyer, responding to a Request for Proposal or other procurement documents. Proposals are an expose on ideas, suggestion, recommendations, and solutions to an opportunity provided by a vendor for a seller. Proposals include a price for the work and document how the vendor would provide the service to the buyer.

234
Q

Prototypes

A

A mockup of the project deliverable to confirm, adapt, or develop the project requirements.

235
Q

Qualified seller list

A

The performing organization may have lists of qualified sellers, preferred sellers, or approved sellers. The qualified sellers list generally has contact information, history of past experience with the seller, and other pertinent information.

236
Q

Qualitative risk analysis

A

An examination and prioritization of the risks based on their probability of occurring and the impact on the project if they occur. Qualitative risk analysis guides the risk reaction process.

237
Q

Quality assurance

A

An executing process to ensure that the project is adhering to the quality expectations of the project customer and organization. QA is a prevention-driven process to perform the project work with quality to avoid errors, waste and delays.

238
Q

Quality audits

A

A quality audit is a process to confirm that the quality processes are performing correctly on the current project. The quality audit determines how to make things better for the project and other projects within the organization. Quality audits measure the project’s ability to maintain the expected level of quality.

239
Q

Quality control

A

A process in which the work results are monitored to see if they meet relevant quality standards.

240
Q

Quality function

A

A philosophy and a practice to fully understand customer needs – both spoken and implied – without gold-plating the project deliverables.

241
Q

Quality management plan

A

This document describe how the project manager an the project team will fulfill the quality policy. In an ISO 9000 environment, he Quality Management Plan is referred to as the project quality system.

242
Q

Quality policy

A

The formal policy an organization follows to achieve a preset standard of quality. The project team should either adapt the quality policy of the organization to guide the project implementation or create its own policy if one doesn’t exist within the performing organization.

243
Q

Quantitative risk analysis

A

A numerical assessment of the probability and impact of the identified risks. Quantitative risk analysis also creates an overall risk score for the project.

244
Q

Quote

A

A document from the seller to the buyer; used when price is the determining factor in the decision-making process.

245
Q

RACI chart

A

A chart designates each team member against each project activity as either Responsible, Accountable, Consult, or Inform (RACI). A RACI chart is technically a type of responsibility assignment matrix chart.

246
Q

Receiver

A

Part of the communications model: the recipient of the message

247
Q

Referent power

A

Power that is present when the project team is attracted to, or wants to work on the project or with, the project manager. Referent power also exists when the project manager references another more powerful person, such as the CEO.

248
Q

Request for proposal

A

A document from the buyer to the seller that asks the seller to provide a proposal for completing the procured work or for providing the procured product.

249
Q

Request for quote

A

A document from the buyer to the seller asking the seller to provide a price for the procured product or service.

250
Q

Requirements documentation

A

A clearly-defined explanation of the project requirements. The requirements must be measurable, complete, accurate, and signed-off by the project stakeholders.

251
Q

Requirements management plan

A

Defines how requirements will manage throughout the phases o the project. This plan also defines how any changes to the requirement will be allowed, documented, and tracked through project execution.

252
Q

Requirement traceability matrix

A

A table that identifies all of the project requirements, when the requirements is due, when the requirements is created, and any other pertinent information about the requirements.

253
Q

Residual risks

A

Risk that are left over after mitigation, transference, and avoidance. These are generally accepted risks. Management may elect to add contingency costs and time to account for the residual risk within the project.

254
Q

Resource breakdown structure

A

This type of chart breaks down the project by types of resources utilized on the project no matter where the resource is being utilized in the project.

255
Q

Resource calendar

A

The resource calendar shows when resources, such as project team members, consultant, and SMEs, are available to work on the project. It takes into account vacations, other commitments within the organization, restrictions on contracted work, overtime issues, and so on.

256
Q

Resource histogram

A

A bar chart reflecting when individual employees, groups or communities are involved in a project. Often used by management to see when employees are most or least active in a project.

257
Q

Resource leveling heuristics

A

A method to flatten the schedule when resources are over-allocated or allocated unevenly. Resource leveling can be applied in different methods to accomplish different goals. One of the most common method is to ensure that workers are not overextended on activities.

258
Q

Resource requirements

A

The identification of what resources are needed to complete the project work is needed a a supporting document for planning. This includes people, materials, equipment, facilities, and services.

259
Q

Responsibility

A

The person that decides what will happen in a project about a particular area of the project.

260
Q

Responsibility assignment matrix chart

A

A chart type designates the roles and responsibility of the project team.

261
Q

Reward power

A

The project manager’s authority to reward the project team.

262
Q

Risk

A

An uncertain event that can have a positive or negative influence on the project success. It can affect the project costs, schedule, and often both. All risks and their status should be recorded in the risk register.

263
Q

Risk mangement plan

A

A subsidiary project plan for determining: how risk will be identified, how quantitative and qualitative analysis will be completed, how risk response planning will happen, how risks will be monitored, and how ongoing risks management activities will occur through the project life cycle.

264
Q

Risk owners

A

The individuals or groups responsible for a risk response.

265
Q

Risk register

A

A risk is an uncertain event or condition that can have a positive or negative effect on the project. All risks, regardless of their probability or impact, are recorded in the issue log and their status is kept current.

266
Q

Role

A

Who does what type of activities in a project.

267
Q

Roles and responsibility

A

Maps project roles to responsibility within the project; roles are positions on the project team and responsibility are project activities.

268
Q

Run chart

A

Similar to a control chart, a run chart tracks trends over time and displays those trends in a graph with each plotted data mapped to a specific date.

269
Q

Sapir-Whorf hypothesis

A

A theory that suggest there’s a linkage between the language a person (or culture) speaks and how that person or culture behaves in the world.

270
Q

Scales of probability and impact

A

Used in a risk matrix in both qualitative and quantitative risk analysis to score each risk’s probability and impact.

271
Q

Scatter diagram

A

Tracks the relationship between two or more variables to determine if the one variable affects the other. It allows the project team, quality control team, or project manager make adjustment to improve the overall results of the project.

272
Q

Schedule control

A

Part of Integrated Change Management, schedule control is concerned with three processes: the project manager confirms that any schedule changes are agreed upon; the project manager examines the work results, conditions, conditions to know if the schedule has changed; and the project manager manages the actual change in the schedule.

273
Q

Schedule management plan

A

A subsidiary plan of the overall project plan. It is used to control changes to the schedule. A formal Schedule Management Plan has procedures that control how changes to the project plan can be proposed, accounted for, and then implemented. Identifies circumstances that may change the project schedule, such as the completion of project phases or the reliance on other projects and outside resources.

274
Q

Schedule performance index

A

This reveals the efficiency of work. The closer the quotient is to 1, the better: SPI = EV/PV

275
Q

Schedule variance

A

The differences between the planned work and the earned work.

276
Q

Scope baseline

A

Comprised of the project scope statement, the work breakdown structure, and the WBS dictionary.

277
Q

Scope management plan

A

Explains how the project scope will be managed and how scope changes will be factored into the project plan. Based on the conditions of the project, the project work, and the confidence of the project scope, the scope management plan should also define the likelihood of changes to the scope, how often the scope may change, and how much the scope can change.

278
Q

Scope verification

A

An inspection-driven process led by the project customer to determine the exactness of the project deliverables. Scope verification is a process that leads to customer acceptance of the project deliverables.

279
Q

Scoring models

A

A project selection method that assigns categories and corresponding values to measure project’s worthiness of investment.

280
Q

Secondary risks

A

Risks that stem from risk responses. For example, the response of transference may call for hiring a third party to management an identified risk. A secondary risk caused by the solution is the failure of the third party to complete its assignment as scheduled. Secondary risks must be identified, analyzed, and planned for just as any identified risk.

281
Q

Sellers and business partners

A

Vendors, contractor, and business partners that help projects achieve their objectives. These business partners can affect the project’s success and are considered stakeholders in the project.

282
Q

Sellers list

A

A listing of the vendors an organization does business with. You might know this document as a preferred vendors list in your company.

283
Q

Sender

A

Part of the communications model: the person or group delivering the message to the receiver.

284
Q

Sensitivity analysis

A

This examines each project risk on its own merit to assess the impact on the project. Each risk is analyzed independently to see what its impact on the project may be while all other risks in the project are set at a baseline value.

285
Q

Sequential relationship of phases

A

Each phase of a project relies on the completion of the phase before it can begin.

286
Q

Share

A

Sharing is nice. When sharing the risk ownership is transferred to the organization that can most capitalize on the risk opportunity.

287
Q

Should-cost estimates

A

These estimates are created by the performing organization to predict what the cost of the procured product should be. If there is a significant difference between what the organization has predicted and what the sellers have proposed, either the Statement of Work was inadequate or the sellers have misunderstood the requirements.

288
Q

Simulation

A

This allows the project team to play “what-if” games without affecting any areas of production.

289
Q

Single source

A

A specific seller that the performing organization prefers to contract with.

290
Q

Smoothing

A

A conflict resolution method that “smoothes” out the conflict by minimizing the perceived size of the problem. It is a temporary solution, but it can calm team relations and reduce boisterousness of discussions. Smoothing may be acceptable when time is of the essence or any of the proposed solutions would work.

291
Q

SNET

A

A project constraint that demands that a project activity start no earlier than a specific date.

292
Q

Soft logic

A

The preferred order of activities. Project managers should use these relationships at their “discretion” and document the logic behind making soft logic decisions. Discretionary dependencies allow activities to happen in a preferred order because of best practices, conditions unique to the project work, or external events; also known as discretionary dependencies.

293
Q

Sole source

A

The only qualified seller that exists in the marketplace.

294
Q

Source selection criteria

A

A predefined listing of the criteria to determine how a vendor will be selected. For example, cost, experience, certifications, and the like.

295
Q

Staffing management plan

A

This subsidiary plan documents how project team members will be brought onto the project and excused from the project. This plan is contained in the human resources plan.

296
Q

Stakeholder analysis

A

A process that considers and ranks the project stakeholders based on their influence, interests, and expectations of the project.

297
Q

Stakeholder register

A

A document defines each stakeholder, their project requirements, influence on the project, phases of interest, details on the stakeholders’ contributions, and their contact information for the project.

298
Q

Start-to-finish

A

A relationship that requires an activity to start so that a successor activity may finish; it is unusual and is rarely used.

299
Q

Start-to-start

A

A relationship structure that requires a task to start before a successor task activity may start. This relationship allows both activities to happen in tandem.

300
Q

Statement of work

A

This fully describes the work to be completed, the product to be supplied, or both. The SOW becomes part of the contract between the buyer and the seller. The SOW is typically created as part of the procurement planning process and is used by the seller to determine whether it can meet the project’s requirements.

301
Q

Statistical sampling

A

A process of choosing a percentage of results at random for inspection. Statistical sampling can reduce the costs of quality control.

302
Q

Status reports

A

These provide current information on the project cost, budget, scope, and other relevant information.

303
Q

Storming

A

The second stage of team development; the project team struggles for project positions, leadership, and project direction.

304
Q

Subprojects

A

A subproject exists under a parent project but follows its own schedule to completion. Subprojects may be outsourced, assigned to other project managers, or managed by the parent project manager but with a different project team.

305
Q

Supporting detail for estimates

A

The project manager should document how time and cost estimates were created.

306
Q

System or process flowcharts

A

These show the relation between components and how the overall process works. They are useful for identifying risks between system components.

307
Q

Systems engineering

A

Focuses on satisfying the customers’ needs, cost requirements, and quality demands through the design and creation of the product. There is an entire science devoted to systems engineering in various industries.

308
Q

Teaming agreement

A

A contractual agreement that defines the roles, responsibility, considerations, and partnerships of two or more organizations that works together in a project. It’s not unlike a partnership or subcontractor relationship.

309
Q

Three-point estimate

A

An estimate that uses optimistic, most likely, and pessimistic values to determine the cost or duration of a project component.

310
Q

Time and materials

A

A contract type where the seller charges the buyer for the time and the materials for the work completed. T&M contracts should have a not-to-exceed clause (NTE) to contain costs.

311
Q

To-complete performance index

A

An earned value management formula that can forecast the likelihood of a project to achieve its goals based on what’s currently happening in the project.

312
Q

Top-down estimating

A

A technique that bases the current project’s estimate on the total of a similar project. A percentage of the similar project’s total cost may be added to or subtracted from the total, depending on the size of the current project.

313
Q

Transference

A

A response to risks in which the responsibility and ownership of the risk is transferred to another party (for example, through insurance).

314
Q

Trend analysis

A

Trend analysis is taking past results to predict future performance.

315
Q

Triggers

A

Warning signs or symptoms that a risk has occurred or is about to occur (for example, a vendor failing to complete its portion of the project as scheduled).

316
Q

Triple Constraints of Project Management

A

Describes the required balance of time, cost, and scope for a project. The Triple Constraints of Project Management is also defined by the Iron Triangle of Project Management.

317
Q

Unanimity

A

A group decision process where all participants are in agreement.

318
Q

Utility function

A

A person’s willingness to accept risk.

319
Q

Value analysis

A

Similar to value engineering, this focuses on the cost/quality ratio of the product. Value analysis focuses on the expected quality against the acceptable cost.

320
Q

Value engineering

A

Deals with reducing costs and increasing profits, all while improving quality. Its focus is on solving problems, realizing opportunities, and maintaining quality improvement.

321
Q

Variable costs

A

Costs that vary depending on the conditions within the project.

322
Q

Variance

A

The time or cost difference between what planned and what was actually experienced.

323
Q

Virtual teams

A

Project team that are not collocated and may rarely, if ever, meet face-to-face with other project team members. The virtual team relies on e-mail, video, and telephone conferences to communicate on the project.

324
Q

Voice of the customer

A

The initial collection of customer requirements that serve as part of the quality function deployment in a facilitated workshop.

325
Q

War room

A

A centralized office or locale for the project manager and the project team to work on the project. It can house information on the project, including documentation and support materials. It allows the project team to work in close proximity.

326
Q

Withdrawal

A

A conflict resolution method that is used when the issue is not important or the project manager is out-ranked. The project manager pushes the issue aside for later resolution. It can also be used as a method for cooling down. The conflict is not resolved, and it is considered a yield-lose solution.

327
Q

Work breakdown structure

A

A decomposition of the project scope statement into work packages. The WBS is an input to seven project management processes: developing the project management plan, defining the project activities, estimating the project costs, determining the project budget, planning the project quality, identifying the project risks, planning the project procurement needs.

328
Q

Work breakdown structure dictionary

A

A companion to the WBS, this document defines all of the characteristics of each element of the WBS.

329
Q

Work breakdown structure templates

A

Based on historical information, this is a WBS from a past project that has been adapted to the current project.

330
Q

Work performance information

A

The current status of the project work; includes the results of activities, corrective and preventive action status, forecasts for activity completion, and other relevant information.

331
Q

Work performance measurements

A

These are predefined metrics for measuring project performance, such as cost variances, schedule variances, and estimate to complete.

332
Q

Workarounds

A

Workarounds are unplanned responses to risks that were not identified or were accepted.

333
Q

IPECC

A

The five process groups: Initiating, Planning, Executing, Controlling and Closing

334
Q

How many processes in Project Integration Management knowledge area?

A

6

335
Q

Process

A

a set of interrelated activities that brings about a product, result, or service