PMP Flashcards
Cultural norm
Describes the culture and style of how an organization operates. The accepted practices, culture, ideas, vision, and nature of an organization
Fast tracking
A schedule compression technique that allows phases to overlap in order to compress the schedule and finish the job faster. Fast tracking does increase project risk.
Phase-end review
Ensures that all the phase obligations have been met to allow the project to move onto the next phases of the project.
Adaptive project life cycle
changes happen often
Kill point
An opportunity to halt the project based on project performance in the previous phase. Kill point typically come at the end of a project phase and are also known as phase gates.
Deliverable
Something that can be verified and measures.
Projectized structure
Group of employees, collocated or not, by activities on a particular project. The project manager in a projectized structure may have complete, or very close to complete, power over the project team.
Level of failing for the project
Projects are most likely to fail at the start of the project. As the project moves closer to the project completion, its odds of finishing successfully increase.
Functional organization
PM has little to no power and the functional manager has all of the power.
Weak matrix organization
The functional manager has the power over the project funding. In a weak matrix, the functional manager is likely to be the project sponsor.
Application areas
The areas of discipline that a project may center upon.. Consider technology, law, sales, marketing, and construction among many others.
Assumption log
A document that clearly identifies and track assumptions that are made in the project. All assumptions need to be tested for their validity and the outcome of the test should be recorded.
Autocratic
The project manager makes all of the decisions
Avoidance
This is one response to a risk event. The risk is avoided by planning a different technique to remove the risk from the project.
Benchmarking
A process of using prior projects within or external to performing organization to compare and set standards for processes and results.
Benefit measurement methods
Project selection methods that compare the benefits of projects to determine which project the organization should select for investment.
Adjourning
The final stage of the team development; once the project is done, the team moves onto other assignments either as a unit or the project team ream is disbanded and individual team members to onto other work.
Affinity diagram
Clusters like ideas together and allow for decomposition of ideas to compare and contrast project requirements.
Analogous estimating
This relies on historical information to predict estimates for current projects. Analogous estimating is also known as top-down estimating and is a form of expert judgment.
Activity on node
A network diagramming approach that places the activities on a node in the project network diagram.
Activity sequencing
The process of mapping the project activities in the order in which the work should be completed.
Actual cost
The amount funds the project has spent to date. The difference between actual costs and the earned value will reveal the cost variance.
360-degree appraisal
A performance review completed by a person’s peers, managers, and subordinates. It’s called a 360-degree appraisal as it’s a circle of reviews by people at different levels of an organization.
Acceptance
This is a response to a risk event, generally made when the probability of the event and/or impact are small. It is used when mitigation, transference, or avoidance are not selected.
Active listening
This occurs when the receiver confirms that message is being received by feedback, questions, prompts for clarity, and other signs of having received the message.
Activity attributes
Activities that special conditions, requirements, risks, and other conditions should be documented.
Activity cost estimates
The cost of resources including materials, services, and when warranted, labor should be estimated.
Activity list
A listing of all of the project activities required to complete each project phase or the entire project. This list is an input to the project network diagram.
Benefit/cost analysis
The process of determining the pros and cons of any project, process, product, or activity.
Benefit/cost ratios
Shows the proportion of benefits to costs; for example 4:1 would equate to four benefits and just one cost.
Bid
A document from the seller to the buyer. Used when price is the determining factor in the decision-making process.
Bidder conferences
A meeting with prospective sellers to ensure all sellers have a clear understanding of the product or services to be procured. Bidder conferences allow sellers to query the buyer on the details of the product to help ensure that the proposal the seller creates is adequate and appropriate for the proposed agreement.
Bottom-up estimating
A technique where an estimate for each component in the WBS is developed and then totaled for an overall project budget, but it provides the most accurate estimate.
Brainstorming
The most common approach to risk identification; it is performed by a project team to identify the risks within the project. A multidisciplinary team, hosted by a project facilitator, can also perform brainstorming.
Budget at completion
The predicted budget for the project; what the project should cost when it is completed. Budget at completion represents 100% of the planned value for the project’s completion.
Cause-and-effect diagrams
Used for root cause analysis of what factors are creating the risks within the project. The goal is to identify and treat the root of the problem, not the symptom.
Centralized contracting
All contracts for all projects need to be approved through a central contracting unit within the performing organization.
Change Control Board
A group of decision makers that review proposed project changes.
Change Control system
A predefined set of activities, forms, and procedures to entertain project change requests.
Change log
As changes to the project time, cost, or scope enter the project they should be recorded in the change log for future reference.
Change management plan
When changes are approved for a project, including time, cost, scope, or contract, then there needs to be a plan on how the project team will manage these new changes within the project.
Chart of accounts
A coding system used by the performing organization’s accounting system to account for the project work.
Checklists
A listing of activities that workers check to ensure the work has been completed consistently; used in quality control.
Closing
The fifth of five project management process groups. It contains the processes responsible for closing a project, a project phase, or the procurement relationships.
Coercive power
The project manager uses fear and threats to manage the project team.
Collective bargaining agreements
These are contractual agreements initiated by employee groups, unions, or other labor organizations; they may act as constraint on the project.
Communications formula
The formula “N(N-1)/2” shows the number of communication channels in a project. N represents the total number of stakeholders.
Communications management plan
A plan that documents and organizes the stakeholder needs for communication. This plan covers the communications system, its documentation, the flow of communication, modalities of communications, schedules for communications, information retrieval, and any other stakeholder requirements for communications.
Composite structure
An organization structure that uses a blend of the functional, matrix, or projectized organization to operate and manage projects.
Compromising
A conflict resolution method; this approach required both parties to give up something. The decision ultimately made is a blend of both sides of the argument. Because neither party completely wins, it is considered a lose-lose solution.
Confidentiality
A project manager should keep certain aspects of a project confidential; consider contract negotiations, human resource issues, and trade secrets of the organization.
Configuration management
The control and documentation of the project’s product features and functions.
Conflict of interest
A situation where the project manager could influence a decision for personal gain.
Constrained optimization methods
Complex mathematical models to determine the likelihood of a projects’ success. These models are used to determine which project an organization should chose for investment.
Constaints
Anything that limits the project manager’s options; for example, time, cost, and scope are always project constraint.
Contingency reserve
A time or dollar amount allotted as a response to risk events that may occur within a project.
Continuous process improvement
A goal of quality assurance to improve the project’s processes and deliverables; meshes with the project’s Process Improvement Plan.
Contract
A legal, binding agreement, preferably written, between a buyer and seller detailing the requirements and obligations of both parties. Must include the offer, an acceptance, and consideration.
Contract administration
The process of ensuring that the buyer and the seller both perform to the specifications within the contract.
Contract change control system
Defines the procedures for how contracts may be changed. Includes the paperwork, tracking, conditions, dispute resolution procedures, and the procedures for getting the changes approved within the performing organization.
Contract closeout
A process for confirming that the obligations of the contract were met as expected. The project manager, the customer, key stakeholder, and, in some instances, the seller complete the product verification together to confirm the contract has been completed.
Contract file
A complete indexed set of records of the procurement process incorporated into the administrative closure process. These records include financial information as well as information on the performance and acceptance of the procured work.
Control charts
These illustrate the performance of a project over time. They map the result of inspections against a chart. Control charts are typically used in projects or operations that have repetitive activities such as manufacturing, test series, or help desk functions. Upper and lower control limits indicate if values are within control or out of control.
Cost baseline
This shows what the project is expected to spend. It’s usually shown in an S-curve and allows the project manager and management to predict when the project will be spending monies and over what duration. The purpose of the cost baseline is to measure and predict project performance.
Cost budgeting
A process of assigning a cost to an individual work package. This process shows costs over time. The cost budget results in an S-Curve that becomes the cost baseline for the project.
Cost change control
This is part of the Integrated Change Control System and documents the procedures to request, approved, an incorporate changes to project costs.
Cost control
An active process to control causes of cost change, to document cost changes, and to monitor cost changes, and to monitor cost fluctuations within the project. When changes occurs, the cost baseline must be updated.
Cost estimating
The process of calculating the costs, by category, of the identified resources to complete the project work.
Cost management plan
Explains how variances to the costs of the project will be managed. The plan may be based on a range of acceptable variances
Cost of conformance
The cost of completing the project work to satisfy the project scope and the expected level of quality. Examples include training, safety measures, and quality management activities. Also known as the cost of quality.
Cost of nonconformance
The cost of not completing the project with quality; includes wasted time for corrective actions, rework, wasted materials. This could mean loss of business, loss of sales, lawsuits. Also known as the cost of poor quality.
Cost performance index
The process of calculating the costs, by category, of the identified resources to complete the project work.
Cost plus award fee
This contract requires the buyer to pay for all the project costs and give the seller an award fee based on the project performance, meeting certain project criteria, or other goals established by the buyer. The award fee can be tied to any factor the buyer determines and the factor doesn’t have to be exact.
Cost variance
The difference between the earned value and the actual costs.
Cost-reimbursable contracts
A contract that pays the seller for the product. In the payment to the seller, there is a profit margin the difference between the actual costs of the product and the sales amount.
Crashing
A duration compression technique that adds project resources to the project in an effort to reduce the amount of time allotted for effort-driven activities.
Critical chain method
A network diagramming approach that considers the availability or project resources and the project’s promised end date to determine the critical path(s) in the project.
Critical path method
A network diagramming approach that identifies the project activities which cannot be delayed or the project completion date will be late.
Culture shock
The initial reaction a person experiences when they’re in a foreign environment.
Decision tree analysis
A type of analysis that determines which of two decisions is the best. The decision tree assists in calculating the value of the decision and determining which decision costs the least.
Decoder
This is a part of the communications model; it is the inverse of the encoder. If a message is encoded, a decoder translates it back to the usable format.
Decomposition
The breakdown of the project scope statement into the project’s work breakdown structure. The smallest item of the project’s decomposition into the WBS is called the work package.
Deliverable
A thing that a project creates; projects generally create many deliverables as part of the project work.
Delphi technique
A method to query experts anonymously on foreseeable risks within the project, phase, or component of the project. The results of the survey are analyzed and organized and then circulated to the experts. There can be several rounds of anonymous discussions with the Delphi technique. The goal is to gain consensus on project risks, and the anonymous nature of the process ensures that no one expert’s advice overtly influences the opinion of another participant.
Democratic
The project team is involved in the decision making process
Design of experiments
This relies on statistical “what-if” scenarios to determine which variables within a project will result in the best outcome; it can also be used to eliminate a defect. The design of experiments approach is most often used on the product of the project, rather than the project itself.
Dictatorship
A group decision process where the person with the most power forces the decision even though the rest of the group may oppose the decision.
Direct costs
Costs incurred by the project in order for it to exist. Examples include equipment needed to complete the project work, salaries of the project team, and other expenses tied directly to the project’s existence.
Discretionary dependencies
The order of the project activities do not have to completed in a particular order so they can be done in the order of the project manager or the project team’s discretion.
Duration estimates
The prediction of how long the project work will take to complete.
Earned value
The value of the work that has been completed and the budget for that work; EV=%Complete X BAC.
Earned value management
Earned value management integrates scope, schedule, and cost to give an objective, scalable point-in-time assessment of the project. EVM calculates the performance of the project and compares current performance against plan. EVM can also be an harbinger of things to come. Results early in the project can predict the likelihood of the project’s success of failure.
Effective listening
The receiver is involved in the listening experience by paying attention to visual clues by the speaker and to para-lingual intentions and by asking relevant questions.
Encoder
Part of the communications model; the device or technology that packages the message to travel over the medium.
Enhance
To enhance a risk is to attempt to modify it probability to and/or its impacts to realize the most gains from the identified risk.
Estimate at completion
A hypothesis of what the total cost of the project will be. Before the project begins, the project manager completes an estimate for the project deliverables based on the WBS. As the project progresses, there will likely be some variances between what the cost estimate was and what the actual cost is. The EAC is calculated to predict what the new estimate at completion will be.
Estimate to complete
Represents how much more money is needed to complete the project work: ETC = EAC-AC
Estimating publications
Typically a commercial reference to help the project estimator confirm and predict the accuracy of estimates. If a project manager elects to use one of these commercial databases, the estimate should include a pointer to this document for future reference and verification.
Ethics
Describes the personal, cultural, and organizational interpretation of right and wrong; project managers are to operate ethically and fairly.
Ethnocentrism
Happens when individuals measure and compare a foreigner’s action against their own local culture. The local typically believe their own culture is superior to the foreigner’s culture.
Evaluation criteria
Used to rate and score proposals from sellers. In some instances, such as a bid or quote, the evaluation criterion is focused just on the price the seller offers. In other instances, such as a proposal, the evaluation criteria can be multiple values: experience, references, certifications, and more.
Exceptional
The project manager only pays attention to the top ten percent of the project performers and the bottom ten percent of the project team performers.
Executing
The project management process group that carries out the project management plan to create the project deliverables.
Expectancy theory
People will behave on the basis of what they expect as a result of their behavior. In other words, people will work in relation to the expected reward of the work.
Expert power
A type of power where the authority of the project manager comes from experience with the area that he project focuses on.
Exploit
The organization wants to ensure that the identified risk does happen to realized the positive impact associated with the risk event.
Facilitated workshops
A collection of stakeholders from around the organization that come together to analyze, discuss, and determine the project requirements.
Feedback
Sender confirmation of the message by asking questions, requesting a response, or other confirmation signals.
Finish-to-finish
A relationship between project activities where the predecessor activities must finish before successor activities may finish.
Finish-to-start
A relationship between project activities where the predecessor activities mush finish before the successor activities may start; this is the most common network diagramming relationship type.
Fixed costs
Costs that remain the same throughout the project.
Fixed price with economic price adjustment contracts
A contract for long-term projects that may span years to complete the project work. The contract does define a fixed price with caveats for special categories of price fluctuation.
Fixed-price contracts
Fixed-priced contracts are also known as Firm-Fixed-Price and Lump-Sum contracts. These contracts have a pre-set price that the vendor is obligated to perform the work or provide materials for the agreed price.
Float
A generic term to describe the amount of time an activity may delayed without delaying any successor activities start date.
Flowcharting
A chart that illustrates how the parts of a system occur in sequence.
FNET
A project constraint that requires an activity to finish no earlier than a specific date.
Focus groups
A conversation of stakeholders led by a moderator to elicit project requirements.
Force majeure
A powerful and unexpected event, such as a hurricane or other disaster.
Forcing
A conflict resolution method where one person dominates or forces their point of view or solution to a conflict.
Forecasting
An educated estimate of how long the project will take to complete. Can also refer to how much the project may cost to complete.
Formal power
The type of power where the project manager has been assigned by senior management to be in charge of the project.
Forming
The initial stage of team development; the project team meets and learns about their roles and responsibilities on the project.
Fragnets
A portion of the project that is usually contracted to a vendor to complete yet the project work is still represented in the project network diagram.
Function analysis
Related to value engineering, this allows team input to the problem, institutes a search for a logical solution, and tests the functions of the product so the results can be graphed.
Functional managers
The managers of the permanent staff in each organizational department, line of business, or function as sales, finance, technology. Project managers and functional manages interact on project decisions that affect function, projects, and operations.
Functional structure
An organization that group staff according to their expertise. Entities that have a clear division regarding business units and their associated responsibilities. Project manages in functional organization have little power and report to the functional managers and the project team all exist within one department.
Future value
A formula to predict the current amount of funds into a future amount of funds. The formula is: Future value = Present value(1+i)n where i is the value of return and n is the number of time periods.
Halo effect
When one attribute of a person influence a decision.
Hard logic
The project activities must be completed in a particular order; this is also known as mandatory dependencies.
Herzberg’s theory of motivation
Posits that there are two catalysts for workers: hygiene agents and motivating agents. Hygiene agents do nothing to motivate, but their absence demotivate workers. Hygiene agents are the expectation all workers have: job security, paychecks, clean and sage working conditions, a sense of belonging, civil working relationships, and other basic attributes associated with employment. Motivating agents are components such as reward, recognition, promotion, and other values that encourage individuals to succeed.
Histogram
A bar chart; A Pareto diagram is an example of a histogram.
Historical information
Any information created in the past that can help the current project succeed.
Human resources plan
Defines the management of the project human resources, timing of use, and enterprise environmental factors the project manager must adhere to in the organization when it comes to human resources management
Inappropriate compensation
The project manager is avoiding compensation, such as bribes. The project manager is to act in the best interest of the project and the organization.