Project financial control Flashcards

(42 cards)

1
Q

If asked by the client to produce a Cashflow analysis how would you do this

A

“Plotting S-Curve

Review of programme/ works to forecast the spend across the months”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What can cashflows be used for

A

To forecast the monthly spend

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the different components of a cost report

A
"Cover
QA/QC
Contract details
Executive summary (current condition, cashflow, programme etc)
Provisional Sums
EAI's
Potential EAI's
Contentious issues
Cashflow section
Warranty tracker
Last payment cert"
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the different types of contingency and how would you calculate an allowance

A

“Construction Risk - Ground risk, existing buildings
Design Development Contingency - Planning changes, procurement delays, statutory requirements
Employer Change Risk - Changes in scope, quality, time
Employer other risk - Early handover, acceleration, LAD’s

Properly considered assessment not percentage based on design completion , uncertainty and investigation done

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a provisional sum and how is it expended

A

“Provisional sum is a an allowance for an as yet undefined scope of works

Defined - Nature of the works, how to be fixed, programme included

Undefined - Cannot be defined or allowed is an allowance without detail”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a Final account

A

“Financial conclusion of works

It includes all adjustments made within the contract sum”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Are LAD’s included within a final account

A

No

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How do you agree a variation with a contractor

A

“Following the valuation rules within the JCT

Contract rate
Similar contract rate
Fair rate for works
Labour and materials”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Are verbal instructions legally binding under the JCT

A

Yes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Under JCT D&B who is responsible for issuing a Final Account statement

A

Contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is VE

A

Value Engineering - Re active approach to reduction of cost but maintain functionality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Can you pay for materials off site

A

“Yes

Listed items in the JCT

Through a Vesting cert”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a Vesting Cert

A

“Vests the ownership to the client

Ensure they are insured and stamped and separate”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Why is financial control so important

A

“Pre Contract

Allows the client to understand the cost of the current design and if this is inline with their budget

Allows the client to allocate their budget/VE if required

Post Contract

Allows the client to understand the predicted outturn cost (Final account)
Cashflow to ensure that finances are available through the scheme
Allows client to understand exposure to risk, anticipated variations & costs, Contentious items, EOT’s L&E “

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How do you agree a final account

A

“It can be a protected process. We review EAI’s agreed ensure included.

Provisional sums included adjusting for the actual cost

Resolution of contentious items

May require negotiation to resolve the final items of costs”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Who submits a final account and when

A

“Contractor submits final account

I. Following PC contractor must submit FA

ii. If not submitted within 3 months employer may give notice. If not submitted within a further 2 months employer can issue final account statement.”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is anticipated change

A

“A change that we expect to come through the works but have not yet been submitted or agreed between the parties

We would include a reasonable assessment of the cost”

18
Q

Why is cashflow important

A

“Provides client understanding of monthly spend to align internal finances

Can understand progress on site

If ahead why?
Ordered materials on site to mitigate potential delays
Making better progress of works on site
Instruction of variations

If behind why?
Slower progress being made - Delay
VE/Reduced scope

19
Q

What is a provisional sum

A

It is an allowance or estimate included within the contractors contract sum for works that cannot be clearly defined/ identified yet. These can be defined or undefined

20
Q

What is a defined provisional sum

A

Defined - has details of what is required and how these works will be fixed. For a defined provisional sum programme, planning & prelims pricing implications are included

21
Q

what is an undefined provisional sum

A

Undefined - Is an allowance programme is not included. Contractor entitled to EOT/ indirect costs as a result of specifying these works

22
Q

What is contained within your monthly cost report

A
"Cover
QA
Content
Contract details
Exec summary
Cashflow
Provisional sums
EAI's
Anticipated variations
Contentious issues
Collateral warranty tracker
Latest payment cert"
23
Q

How do you include contingency

A

“Under NRM this is divided into:
 Construction Risks – Ground conditions, existing buildings, access restrictions
 Design Development Risks – Changes in estimating data, 3rd party risks (planning,
legal agreements, environmental issues), statutory requirements, procurement
methodology, delays in tendering
 Employer Change Risks – For use during design and construction for employer driven
changes (scope, quality and time)
 Employer Other Risks – Early handover, postponement, acceleration, availability of
funds, LADs, special contractual arrangements
· As risks occur, they are funded from this contingency pot. Once the risks are no longer an
issue, funds can either be returned to employer or transferred to another risk if required
(this is to be decided by the employer)”

24
Q

How do you forecast costs for unpriced variations

A

JCT pricing way

  1. contract rate
  2. similar rate
  3. fair assessment
  4. labour plant materials
25
How do you ensure effective control of costs on a project
"Proactive risk and contingency management Implementing a robust change control process Management of provisional sums within budget Regular cost reporting which is also forward looking Rolling final account with closure process for financial impact of change"
26
What are the risks to construction projects
"External risks: economic, legal, political Procurement Risks Choice of Contract Financial risks: exchange rate, funding Site risks: Restricted, occupied site, planning difficulties, access, environmental Client risks: lack of experience, multi-headed client, likelihood of post contract changes. Design risks: inappropriate consultant team, poor brief, incomplete design, co-ordination. Selection of appropriate contractor: inadequate selection process Construction and delivery risks: weather, constructability, H&S, availability of resources"
27
How do you value day works
"Either with a rate that excludes OH&P 'All inclusive rate' - includes OHP"
28
What is the purpose of change control
"Effective cost control Auditable instructions Method of assessing and managing change Ensure fully justifiable instructions and implications understood"
29
Why is the cashflow shaped like an S curve
"Costs are cumulative so it ascends Resources at start are minimal As construction kicks in more resources are required making it steeper Towards the end less resource needed to it flattens"
30
What considerations are needed when creating a cost report protocol
"Content & format Timing & frequency Interaction with other parties Distribution Method of presentation"
31
What are the JCT fluctuations provision
"3 Options Option A - Adjustment for legislation change Option B - Labour material & tax changes Option C - Formula adjustment subject to limitations in the contract"
32
What is included within a valuation
``` "Prelims Fees Works complete on site Materials on site Materials off site Prov sums Instructions deduction of retention" ```
33
What is a performance bond
Performance bond is an insurance back guarantee should the contractor default against their obligations
34
when would you need a performance bond
"New contractor No financial accounts"
35
Would you pay for insurance upfront
"No. I would draw it down monthly against the progress of works As the employer would not get the benefit if the contract was terminated"
36
What is included within a Final account
"Prov sums - Instructed expended or omitted Loss and expense Adjustments for approximate quantities Any other items affecting total cost"
37
What is the valuation process
"Planning - Agree with contractor the format Pre-evaluation - Review what the contractor has submitted Valuation - Attend site an check the works claimed have been completed Agreement - Discuss and agree with the contractor the value that will be paid Valuation documentation - Produce documentation get these QA'd Issue valuation - Issue to contractor and client Post valuation - maintain records of payments"
38
What are listed items
Items within the contract that can be paid when off site It is insured through the contract Contractor must evidence it is vested to them May be required to provide a bond for them Must be rigorously checked as you would with vested materials
39
3 questions to ask about a cashflow
"Is it based on valuation date or payment date Should it be gross or net Should it include retention and rectification periods"
40
Can you give me an example of when you have utilised GRAPHICAL communication skills in providing information to a client?
yes I have used the S curve graph to display the data of my cash flow for the project to the client
41
what would you do if a client asked you to remove the contingency from a cost report
advise against unless the risk had been resolved if still wants it done summarise in writing and do
42
can you advise on a change control procedure you have implemented on your schemes
Client change request/ contractor identification of change requirement Contractor Price CPC Review and negotiate or confirm with client intent to proceed CPC issues EAI to advise all parties of instructed change CPC record in Cost report issued to client to include within final account