Quantification and Costing of Construction Works Flashcards
Why were the New Rules of Measurement introduced?
- Previous Standard Method of Measurement (SMM7) geared towards BoQ production for tender purposes
- Therefore lack of guidance when preparing cost estimates and cost plans
- NRM provides standardised framework for quantification and measurement, giving employers more confidence around what’s been included
When producing estimates and cost plans, what measurement rules represent industry best practice for capital building and building maintenance works in the UK?
NRM (new rules of measurement)
Why should you use the NRM?
- Standardised framework for quantification and costing for cost plans
- Adds confidence to clients
- Provides defence against negligence claims as using best practice
- If not following NRM, would need good defence why this approach taken
Can you name the 3 documents in the NRM suite?
- NRM 1 - Order of cost estimating and cost planning for capital building works (cost planning for capital buildings)
- NRM 2 - Detailed measurement for building works (detailed measurement for building works)
- NRM 3 - Order of cost estimating and cost planning for building maintenance works (cost planning for building maintenance)
Can you provide a brief overview of each of the NRM documents?
NRM 1: Early-stage cost estimating and planning for capital building projects.
NRM 2: Detailed measurement rules for tendering and preparing quantity documents.
NRM 3: Cost estimating and planning for building maintenance and lifecycle costing
How is risk dealt with under NRM?
- Risk allowances not a standard percentage
- Should be properly considered assessment of risk, considering completeness of design and other uncertainties such as extent of site investigation undertaken
What are the 4 categories of risk identified in NRM?
- Employer change
- Employer other (funding risks, policy / spending practices)
- Design development (items of work missed as design developed)
- Construction (site risk, contamination, obstruction)
Why is it important to measure the works according to industry standards and best practice?
- Greater consistency and accuracy of pricing
- Ensure all parties price on same basis, reduce risk of dispute
Is it mandatory for Chartered Surveyors to follow procedures set out in NRM?
No, however when allegation of professional negligence made against a surveyor, the adjudicator / court likely to take account contents of any relevant guidance notes published by RICS in deciding whether surveyor acted with reasonable competence
Structure of NRM 1?
o Part 1: General introduction explaining the purpose of the document and how it should be used.
o Part 2: Measurement rules for the production of order of cost estimates.
o Part 3: Measurement rules for the production of elemental cost plans.
o Part 4: Tabulated rules of measurement for elemental cost planning.
o Appendices: With references to the definitions for GIA, functional units, NIA, elemental breakdowns, templates and general information required for cost plan production.
How does NRM define the ‘cost limit’ for the project?
NRM 1
Max expenditure the client is prepared to make related to completed building (inc construction, professional services, other project costs, items required post completion, during operation and risk allowances
How does NRM define the ‘base cost estimate’ for the project?
NRM 1
Evolving estimate of known factors without allowances for risk / uncertainty / inflation. Sum of works cost estimate, project and design team fees estimate, other development and project costs
Structure of NRM 2?
- General Introduction
- Detailed measurement of building works
- Rules of measurement for building works
- Appendices
Key headings for contractor preliminaries identified in NRM 2?
- Employer’s requirements
- Site accommodation
- Site records
- Completion and post-completion requirements
- Main contractor’s cost items
- Management and staff
- Site establishment
- Temporary services
- Safety and environmental protection
- Control and protection
- Mechanical plant
- Temporary works
- Site records
- Completion and post completion requirements
- Cleaning
- Fees and charges
- Site services
- Insurance, bonds, guarantees, warranties
Types of BoQ under NRM2?
Firm
- Reliability of tender price increases in relation of accuracy of quants provided. If no design changes, firm BoQ at tender stage = final cost
Approximate
- Not enough detail to prepare firm, decided by client that time/cost to produce firm one not warranted
- No lump sum price provided, but tender price totals
- Qty’s subject to remeasurement on completion by QS / cost manager
How do you measure structural steelwork under NRM 2?
- Section 15 - measured in tonnes and itemised according to their respective lengths, weight and type
- Other items to measure in association with steelwork include framing erection, permanent formwork, cold rolled purlins and cladding rails, isolated structural member, filing hollow sections, surface preparation, surface treatment and localised protective coatings.
What items would you measure in association with structural steelwork under NRM 2?
- Framing erection
- Permanent formwork
- Cold rolled purlins and cladding rails
- Isolated structural member
- Filling hollow sections
- Surface preparation and treatment
- Localised protective coatings
How do you measure brickwork walls under NRM?
Masonry- section 14
- Measured in sqm, itemised according to wall thickness, type of construction and method of formation
Other items to measure in association with brickwork / masonry?
- Chimney stacks
- Arches
- Brick reinforcement
- Forming and closing cavities
How do you deal with ground water under NRM 2?
Section 5 - Excavating and Filling
- Measured on itemised basis, original below ground level stated and reference to whether water is polluted
- If post contract water level differs from pre-contract level, measurements must be taken and revised accordingly
- Method and place of discharge left to discretion of contractor unless stated otherwise
What are levels 1, 2, 3 [and 4] mentioned in NRM?
- [Section 4 and] Appendix B of NRM2, describes the logic and arrangement of the levels for elemental cost planning, in increasing amounts of detail
L1 - group element (i.e. facitating works)
L2 - element - key part of group element (i.e. major demolition works)
L3 - sub-element (i.e. soft strip works)
[L4 in Section 4 - component- building work forming sub-element)]
Structure of NRM 3?
- General introduction
- Measurement rules for building maintenance works
- Measurement rules for order of cost estimating
- Cost planning of repair and maintenance works
- Calculation of annualised costs for repair and maintenance works
- Elemental cost planning
- Appendices
Can you name some of the pricing documents we might use at tender stage?
- Bill of quantities (BoQ)
- Schedule of rates (SoR)
- Contract sum analysis (CSA)
- Schedule of work (SoW)
- Priced activity schedule
Why might a CSA make it difficult to agree post contract cost changes?
- Higher level breakdowns (usually elementally) so contractor substantiation is required to agree costs post contract
- More difficult to determine if an item has been costed for and how priced