Quantification + Costing Flashcards
(38 cards)
Q. On the Dorking Halls project you mentioned you advised using a schedule of works document. Can you explain why this was beneficial from a clients prospective?
o This was beneficial as the works were of a fairly simple nature o Meaning it was more efficient to both produce and for the contractor to populate.
Q. What is the difference between and Contract Sum Analysis and a Schedule of works?
o CSA = Produced by the contractor under D&B. o Schedule of works = Used for a standard building contract
Q. On the Quad Three project you mentioned that you proposed using IPMS to comply with best practice measurements instead of COMP6. Can you explain how and why you did this?
o I did this as IPMS is the best practice for measurement in the industry and is internationally recognised. o I advised my client in writing, alongside the architect, however they also confirmed in writing for us to proceed with COMP 6.
Q. You mentioned you used the valuation ruse on the GE3B project. Can you explain to me what the Valuation Rules are?
o If similar CHARACTER, QUANTITY and CONDITION – Tendered rates used. o If similar CHARACTER but DIFFERENT QUANTITY or CONDITION – Tendered rates with amendments o Fair allowances made If DIFFERENT CHARACTER o NON-MEASURABLE – Day works should be used
Q. Can you explain the difference between a tabulated rules of measurement and the elemental classification of works?
o Tabulated rules of measurement provides a detailed breakdown of how each element should be classified and measured. o Elemental is the overall summary allocation of those broken down in the tabulated rules (Group elements)
Q. Can you tell me some disadvantages of using CostX?
o Cost of licenses, time to train, technology errors / outages
Q. You state you are aware of NRM 1 and 2, can you tell me what NRM 3 is?
o Order of cost estimating and cost planning for building maintenance works
Q. You mention you have prepared an elemental cost plan. To what level of detail does this go to?
o Level 1 - group element o Level 2 - element o Level 3 - sub element o Level 4 - Component
Q. Can you give me an example of where you have used the valuation rules?
o When valuing changes on a number of my post contract projects.
Q. Can you give me some differences between IPMS and COMP 6?
Summary of Main Differences (there is more but just for memory) IPMS COMP6 GEA IMPS 1 Excludes balconies but states separately GEA Excludes Balconies GIA IPMS 2 Measures to the Internal Dominant Face (50% of the lowest 2.7m) GEA Measures to the Internal Dominant Face NIA IMPS 3.2 Measures different occupier area’s Includes Columns NIA Excludes columns and partitions.
Q. Why did you advise your client to adopt IPMS over COMP 6?
o IPMS is internationally recognised and best practice.
Q. How do you quantify works completed in a variation?
o Using the valuation rules and measurement, NRM 2.
Q. How have you re-based in-house data on your projects?
o By rebasing them based on both time and location factors. o Location indices o Time indices for inflation Formula for TPI = (Current TPI - Base TPI / Base Year) * 100
Q. What is the difference between a defined and undefined provisional sum?
o Both are where there is an element of works where the works are going to be required but the full scope is not completely known. For example a feature wall. o Defined = Contractor has made adequate allowances for programme implications and additional costs o Undefined = Contractor has not made these adequate allowances. Therefore entitling them to a L&E and EoT.
Q. How can you provide some element of cost certainty with a provisional sum?
o Get a target rate for the supply of the material to be used o Introduce a pain / gain mechanism to the contract
Q. What is BIM? Have you used BIM on any of your projects?
o BIM is Building Information Modelling o Allows for all design teams to work on the same model and each item (materials, specifications etc) are stored on the system too.
Q. Can you tell me the difference between NRM 1 and NRM 2?
o NRM1 is used when completing cost plans and cost estimates o NRM2 is used for completing detailed measurement, typically for other pricing documents such as a BoQ.
Q. Can you give me an example of when you have used NRM 2 to price something?
o Yes, when assessing a change / variation o Using the tabulated rules of measurement to ensure it has been measured correctly.
Q. Can you tell me the valuation rules?
o Outlined in Section 5 of the JCT D&B contract. o Where works are of a similar nature = Contract rates o Where works are similar but different = Contract rates with amendments o Where works are not of a similar nature = Fair and reasonable rates o Where works cannot be measured = Day works
Q. What if a quote comes in and it looks really high? Do you just accept it?
o No, I would expect the contractor to prove this to be reasonable or I would use in house data to assess the comparability of it.
Q. Describe the scenario on Brent Cross where you had to reconcile significant discrepancies between a sub-contractor’s interim valuations and your own assessments. How did you approach resolving these discrepancies, and what steps did you take to ensure both accuracy and fairness in the final valuation?
o I would refer to the Black Book document, interim valuations and payment o This ensures I am completing best practice. o If there is an area that I am different to the contractor on as they have overclaimed, I would see if there other areas where perhaps they have not claimed but have completed the works.
Q. You say you have experience using cost -x ? Can you outline any pro’s and con’s you think exist, relating to digital measurement software
o Upskilling of staff o Cost of the software itself and licenses o Technological issues, outages etc.
Q. On quad 3 there was back and forth on measuring standards - how does comp 6 differ from the IPMS?
Summary of Main Differences (there is more but just for memory)
IPMS COMP6
GEA IMPS 1 Excludes balconies but states separately
GEA Excludes Balconies
GIA
IPMS 2 Measures to the Internal Dominant Face (50% of the lowest 2.7m)
GIA Measures to the Internal Dominant Face
NIA IMPS 3.2 Measures different occupier area’s Includes Columns
NIA Excludes columns and partitions.
Q. How do you measure GIFA? What guidance do you advise to use?
o I would refer to IPMS – the “All buildings” latest version.
o The GIA would be measured in line with IPMS 2 = GIA
o Taking the internal floor plates of the building, up to the internal dominant face (50% of the lowest 2.7m as per IPMS)