Commercial Management Flashcards

1
Q

What is a Cost Value Reconciliation?

A
  • Cost value reconciliation is used to measure the projects ongoings costs and income against budgeted
    values at the start of the project.
  • This allows the profitability of the project to be determined at a given point in time throughout the
    project lifecycle.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How would you prepare a Cost Value Reconciliation?

A
  1. I would determine the cumulative costs and value of the project to a set given point in time.
  2. The cut-off date may coincide with an agreed accounting period or month end period which I would establish with the project management team.
  3. I would carry out cost checks to ensure that:-
    o No high value fluctuations in costs or value are expected during the reporting period.
    o That all work in progress is accounted for and the reported values are inline with
    subcontractor’s measures and liabilities.
    o Risk and contingency items have been included for items not yet agreed.
    o When all costs and value items are finalised I would then determine the current profitability of
    the project and compare this against the original budgeted values.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How do you ensure your Cost Value Reconciliation is accurate and up to date?

A
  • The forecast revenue on variations is only reported when variation items are agreed.
  • A reduced percentage profit is assumed if variations are paid on account or partly agreed.
  • Contingency items are retained with the CVR for any unknown or pending cost items.
  • I regularly arrange meetings to conclude the agreement of variations for each of the sub-contract
    packages so a backlog of items pending does not form.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a Cash Flow Analysis?

A
  • A cash flow analysis highlights the movement of income and expenditure into and out of a business
    over time.
  • If the level expenditure going out of the company is higher than the income, the cash flow is classed as cash negative and may highlight the need to make additional funding arrangements.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How would you compile a cash flow?

A
  • To calculate the project incomes I would look to utilise the agreed payment schedule set out under the
    terms of the contract, the programme and the BoQ or Activity schedule.
  • I would then accurately profile when the income is anticipated to be received and plot these dates on the cash flow forecast.
  • If this information is not available it may be possible to use information cash flow analysis software to plot a typical S-curve.
  • For the outgoings I would liaise with the supply chain to gain an insight of when invoices and payments are expected to become due taking extra care to account for any long lead items.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Please explain your understanding of the term ‘Accruals’?

A
  • Accruals are made within the financial accounting systems that are operated to take into account anticipated invoices that are not yet paid.
  • The accrual can be calculated as the difference in the total liability that is due to a sub-contractor or supplier against the amount already paid to date.
  • The accruals are retained as anticipated cash outflows not yet incurred and in theory the older the accruals are, the less likely they are to paid and may be released at a given point in time.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is Company Overhead?

A
  • Company overheads are ongoing expenses incurred as a result of the day-to-day operations of the
    business.
  • They are items that need to be incurred in order to provide critical support to the revenue generating
    arms of the company for example factory rental costs, heating and lighting.
  • They are classified as fixed overheads which do not change for example monthly rental costs and
    variable overheads which do change depending on business activity for example heating costs.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the purpose of maintaining cumulative accounts and payment procedures?

A
  • Reporting, invoicing and processing of payments is done on a cumulative basis to ensure the full extent
    of the financial information is accounted for.
  • If this is not adopted and invoices are made ‘in the period’ mistakes can be made and double counting
    may take place.
  • It is much safer to work on a cumulative basis as the risk of double counting or missing invoices is
    reduced.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Please explain your understanding of the term ‘Earned Value Analysis’?

A
  • Earned Value Analysis is a technique used to forecast the final financial position of a project.
  • The technique compares the current progress achieved to date with the planned progress at a given point in time.
  • It also considers the current costs incurred with planned costs over the same time period.
  • The EVA determines what value of work would have been achieved and what costs would have been incurred if the works had been on programme to forecast future performance and to highlight potential cost overspends and time overruns.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What Contract Administration Controls do you implement?

A
  • Utilisation of payment and valuation schedules to ensure all parties are aware of key dates in accordance
    with the contract and Housing Grants Construction and Regeneration Act.
  • Running final accounts to ensure each party is informed of any adjustments, claims and variations.
  • Regular review of revised drawings and contractor’s instruction to ensure all variation and claims items
    are captured.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What procedures do you adopt for supply chain and sub-contractor management?

A
  • My company maintains a database of potential suppliers that allows categorisation of specific trades
    with a current status of either pending approval, authorised or not to be used.
  • These categories are based on previous performance in combination with undertaking regular checks
    on items such as insurance certificates being provided, credit checks, maintenance of accident records
    and obtaining copies of quality management accreditations.
  • Performance checks will include items such as Health & Safety track record, quality reviews, remedial
    work requirements, programme delays, commercial and contract administration performance.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What procedures do you undertake to resolve sub-contract final
accounts?

A
  • Throughout the project I would maintain a running final account of the sub-contract package and look
    to agree any variation items with the sub-contractor on an ongoing basis.
  • Having the running final account in place in my experience has supported with reaching a swift final account agreement.
  • Prior to arranging the final account meeting I would collate the following items to support the discussion:-
    o The subcontract order agreement including the BoQ or pricing schedule.
    o The final account submission or final subcontract application for payment.
    o Details of all variations or changes with full substantiation
    o Supporting quantities or take-offs for any re-measurable items.
  • During the meeting I would run through the agreed and any pending adjustments with the sub-
    contractor.
  • Following discussions and agreement during the meeting I would circulate the final account statement
    for signature by both parties and hold this on file.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How did you gather and analyze data to estimate that the project would only spend £900k in the 23/24 financial year?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How did you create the resourcing profile?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How did you determine the project management cost for each team member involved in the project?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Can you explain how you spread out the project management cost across the program?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

How did you integrate the timing of contractors’ work and costs into the cost forecast?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What factors did you consider when establishing the timing for contractors’ work and associated costs?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Can you elaborate on how you incorporated quotes provided by contractors into the cost forecast?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

How did you ensure that the cost forecast was adjusted accurately each month based on progress on site?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Did you encounter any challenges or difficulties while preparing the cost forecast for the Mercury House project? If so, how did you address them?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Can you provide an example of a situation where you had to revise the cost forecast based on unexpected changes or developments during the project?

A
22
Q

Can you describe the process you followed to carry out the cost value reconciliation for the Horton in Ribblesdale project?

A
23
Q

How did you break down the initial budget figure into components such as overheads, plant, and labor?

A
24
Q

What methods did you use to compare the updated project costs to the budgeted figures?

A
25
Q

Can you explain how you plotted the budgeted figures on a cumulative basis?

A
26
Q

What specific efficiencies did you identify in labor and plant costs during the project?

A
27
Q

How did you determine whether the project was behind schedule or within budget based on your analysis?

A
28
Q

Did you encounter any challenges or limitations in conducting the cost value reconciliation for the Horton in Ribblesdale project? If so, how did you overcome them?

A
29
Q

Can you provide an example of how your findings from the cost value reconciliation influenced decision-making or project management on the Horton in Ribblesdale project?

A
30
Q

What lessons did you learn from this experience that you could apply to future cost value reconciliations or similar projects?

A
31
Q

Can you describe the process you followed to monitor and advise the project manager on the cost forecast for the Mercury House project?

A
32
Q

What specific steps did you take to assess the accuracy and reliability of the initial cost forecast committed by the project management team?

A
33
Q

How did you gather and analyze data to estimate that the project would only spend £900k in the 23/24 financial year?

A
34
Q

What factors influenced your decision to advise the project manager to move funds to another project?

A
35
Q

How did you determine which project would be more suitable for the reallocation of funds?

A
36
Q

Can you explain the rationale behind your recommendation to move funds before the end of the financial year?

A
37
Q

What financial metrics or indicators did you consider when evaluating the efficiency of fund allocation between projects?

A
38
Q

Did you perform any risk assessments to identify potential drawbacks or challenges associated with reallocating funds from the Mercury House project?

A
39
Q

How did you assess the potential impact of reallocating funds on the overall financial performance of both projects?

A
40
Q

How did you communicate your recommendation to the project manager, and what considerations did you take into account to ensure effective communication?

A
41
Q

How did you ensure that the project would have sufficient cash to continue operations despite any potential fluctuations in income or expenses?

A
42
Q

What lessons did you learn from this experience that you could apply to future cashflow forecasting or contract negotiation processes?

A
43
Q

Did you identify any potential risks or challenges related to the project’s cashflow, and if so, how did you mitigate them?

A
44
Q

Can you provide an example of how you effectively communicated complex financial information to stakeholders during the negotiation of new payment terms?

A
45
Q

Were there any other stakeholders involved in the decision-making process, and how did you collaborate with them?

A
46
Q

How did you communicate with the commercial director about the projected cashflow for the Gigaclear project?

A
47
Q

Were there any challenges or uncertainties you encountered in analyzing the impact of the new payment terms, and if so, how did you address them?

A
48
Q

What specific changes were made to the payment terms of the NEC 4 contract, and how did these changes impact the project’s cashflow?

A
48
Q

Can you explain how you assessed the potential impact of the amended payment terms on the project’s cashflow?

A
49
Q

What methods or tools did you use to liaise with contractors and suppliers to understand their payment terms?

A
50
Q

When creating a cost value reconciliation what do you need to be careful of?

A

You need to account for when the value is actually earned of a project. For example if £1000 worth of electrical works is complete in June, but cash is received in July, you need to report this for June.

Prudence concept also needs to be applied, value is not overstated and costs are not understated

You want to include measure, variations and claims that are likely to be agreed.

51
Q

Tell me about how you carried out a cost value reconciliation on the Horton project.

A

Strictly speaking this was only used for the expenses as I was acting on behalf of the client, however the initial step I took was to understand the programme and all costs associated with each activity. For example number of labour for each activity and plant and any material delivered.

Then I could plot this cumulatively along a timeline to understand the outturn cost.

Once work started I was able to monitor cost to date + cost to go and this allowed me to understand that the cost outturn is 2m not 2.2m and so we had to understand if the project is behind or if the project is efficient and determine actions.

52
Q

Tell me then how you went about doing earned value analysis

A