Contract Administration Flashcards
What is the contractors design proportion?
-Agreement for contractors to design a specific part of the work
- contractor submits a proposal for review and approval
What is a PCSA (pre contract service agreement)
Letter of intent, typically part of a two stage tendering process.
In Rugby how did you deal with works not been completed on time?
- Issued certificate of non completion
- Time would be at large, no set completion date if didn’t.
- Contrator has responsibility to complete in reasonable time
What has to be in place to deduct LADS?
Non completion certificate
Witholding notice, similar to pay less.
How would you confirm if an EoT is warranted.
Refer to contract
Request evidence
How are variations managed
If an instruction constitutes a variation then a contractor should give a variations quote
works described should not begin until quotation agreed
what happens during snagging
undertaken before PC otherwise known as a schedule of defects.
How do you manage/review valuations?
- Prepared by contractor and reviewed by CA.
- Check on site and assess if works have been complete
What are prelims?
Describes the project and contractual procedures.
Does minor works outline relevant events/matters
no. would have to refer to JCT guidance note, can bring claim under common law
What is your understanding of making good defects and what does it involve?
- The contractor administrator issues an instruction to make good the defects.
- At the end of defects liability the CA prepares a schedule of defects nd agrees to a time to be remedied by.
- Once works are complete a making good is issued to trigger retention release and the final CFP.
- If the contractor does not undertake work, the cost is taken out of the retention.
What do you understand by partial possession?
Client takes occupation of site (or part of) even if works are on going or defects not remedied.
Contractor is not obliged to allow it if disrupts work.
could result In E0T claim
If you knew a contractor was in financial difficulty what would you do?
- Value works carefully
- Check materials on site
- Arrange meeting
- Review cash flow.
What is a framework agreement?
For on going construction works
reduces procurement timescales
Normally based on set pricing schedules
What is a final account?
Detailed statement of all adjustments to contract sum, total amount is liable to pay
What is a bill of quantities
-Ordinerily prepared by QS
-Project measured quantities
-
What is a termination mechanism in a contract.
When a party no longer intends to meet obligations:
- refusal to carry out works
-abandoning site
-failure to pay
-Failure to allow access
- failure to remedy defective works
What is your understanding of novations?
- Transferring contractual rights from one party to another
- ## Common in design and build scenarios
What is your understanding of non completion and when would one be agreed?
- Issued when works not complete by PC date outlined, this is when LADS can be deducted.
- When the client is responsible for delay an EoT may be issued and the completion date adjusted. Contractor can claim losses and expenses (additional prelims).
- Cert of non completion gives formal notice that contractor has not met PC
- Minor works do not require issuing non completion.
What are the impacts of partial possession?
The part possessed is deemed to have had PC
Half of the retention for that part is released.
Defect liability starts on that section
LADS reduce proportionally
What is insolvency?
Inability to pay debts
What does JCT stand for?
Joint contract tribunal
What do you consider when choosing procurement route?
Consider speed, cost, quality, constraints, risk. options include:
- Traditional (single stage)
- Two stage
- D&B
What is meant by loss and expense?
These can be claimed by the contractor in the event the works are affected by a relevant matter for which the client is responsible for?
- Failure to give contractor possession of site
- Delay in recieving instruction
- Opening up works or testing works
- failure by client to supply goods or materials
- Issues relating to CDM.
What is a contract instruction and when is it issued
- Vary the work
- postpone the work
- to sanction a variation
- to carry out tests
What is the definition of PC?
Ready for beneficial occupation and use.