HS&B Flashcards

1
Q

According to commercial and industrial insulation standards, which of the following pipe insulation’s is suitable for use on hot water piping

A

Elastomeric plastic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The minimum bracing for a trench 6’ deep x 30” wide is?

A

4x4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Which type of material will increase in volume most when excavated from it’s compact state

A

Clay

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Once wallpaper paste has been opened, it should be used within

A

1 day

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Bridge concrete mix that contains super plasticizers will

A

Require less water for the same workability

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Which of the following is a cause of concrete segregation

A

Excessive water to cement ratio

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Caissons are

A

Shafts with or without casings sunk into the desired depth and filled with concrete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the temporary structure used to hold back a water while work is being done?

A

Coffer dam

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

An approach to a bridge requires a fill operation. Proper compaction of the fill soil is achieved by

A

Using the right amount of water

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the color of deliniators installed on the left hand side of a one way road?

A

Yellow

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Red is used as a background color on all of the following traffic signs except

A

One way

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Highway warning signs will be placed in a highway construction site. The warning sign nearest the construction work site will be placed how many feet from the restrictions?

A

500’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Blue smoke rising from a batch of hot mix asphalt may indicate

A

Overheating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the difference between piers and pilasters used in masonry concrete?

A

Piers are isolated and freestanding whereas pilasters are built into a wall thickening a small wall section

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Pile drivers may consist of a drop, mechanical, or _____ hammer

A

Vibratory

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are all of the tests that may be required in the project specifications for concrete quality control

A

Strength, slump, air

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

When super plasticizers are used in a concrete mix

A

Less water will be needed for the same workability

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What does a standard Proctor test determine?

A

Optimum moisture content of a soil

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is the name for the pile that is formed by driving a casing into a set of depth and removing the casing while filling the hole with concrete?

A

Shell-less

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What should be the minimum distance between the sash and the edge of the glass

A

1/16”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Why should an operator preheat the pump and nozzles on an asphalt distribution machine?

A

To match the asphalt temperature

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What does a contour line grading plan indicate?

A

Location of constant elevation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

A slurry wall is used for what purpose?

A

Sub-surface de-watering

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

According to OSHA, corrective action to eliminate existing and predictable hazards and unsanitary working conditions can be performed by

A

A competent person

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Financial ratios make it possible for a company to

A

Compare a company’s performance with the average performance of businesses of similar age and size in the same industry

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

When an excavation is inspected by a competent person and evidence of a situation that could result in a possible cave in is found, OSHA requires that

A

Employees be removed from the excavation until the necessary precautions are taken

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

What do you do to increase the load capacity of a crane?

A

Increase the size of the counterweight

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

How often should wire rope be inspecting

A

After every use

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

What should be used to protect dry wall panels that meat on an outside corner

A

Corner bead

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

In obtaining proper soil compaction it is important to

A

Control the amount of water in the soil

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

What is the name used for the inside bottom elevation of the sewer pipe

A

Invert

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

What is used as a temporary set of walls to keep soil and or water from entering the excavation

A

Cofferdam

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

When preparing a road base, what soil reacts best to vibration?

A

Sand

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

What is the best foundation material for skyscrapers or large buildings

A

Bedrock

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

What device is bolted to the blade of a grader to help with grading a road around curbs

A

Curb shoe

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

Which is not one of the purposes of compacting soil

A

To decrease the resistance to erosion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

How many layers of concrete or in a slump test?

A

3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

What is a pile driven on an angle called?

A

Battered

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

What do you use to increase compression strength of concrete?

A

Vibration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

A _____ Is used for a test to measure compression strength in concrete

A

Cylinder

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

Prefabricated forms are used to form 12” wide x 8’ high foundation walls. When should reinforcing steel be installed?

A

After the outside forms are in place

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

A contractor is placing a pipe in a 6 inch thick concrete slab. What is the maximum outside dimension of the pipe?

A

2”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

Concrete strength is designated in pounds per square

A

Inch, compressive

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

Electrolysis would be caused by attaching which of the types of materials in direct contact with each other

A

Steel and copper

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

What best describes a pile driving head

A

A device placed on the head of a pile to receive hammer blows and to protect the pile from damage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

Where should the rear tires be on a rubber tire backhoe after stabilizers are placed?

A

As high as the stabilizers will lift them

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

Which is not a basic test used in concrete mix design as quality control

A

Density

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

Which of the following ad mixtures is commonly used to improve the durability of concrete?

A

Natural pozzolans

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

Which of the following is a cause of concrete segregation in bridge abutments?

A

Excessive water to cement ratio

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

You can increase concrete set up time and excellerate early strength development by adding

A

Calcium chloride

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

What is the name for an aggregate emulsified asphalt finish used to rejuvenate and seal an old asphalt surface?

A

Slurry seal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

Piles are specified for a new bridge. What action drives a single action pile driving hammer?

A

They fall by gravity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

Toe boards are required for protection from falling objects on scaffolds used to construct bridge falsework. According to OSHA, what is the required minimum height of the toeboard’s?

A

4”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

What are the purpose is for laying down a prime coat?

A

To protect the base course against weather, to prevent a slip plane between the base and surface course, and To prevent the base materials from shifting under traffic before the first course is placed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

Air entrainment in concrete is used primarily to

A

Improve freeze/thaw resistance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

Which of the following types of Portland cement Is used in massive concrete structures where low heat of hydration is required

A

IV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

What does the structural steel designation C 3 x 6 mean?

A

Channel 3” deep, 6# per linear foot

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

Corrugated metal pipe is used as a part of a drainage system. Which is used to join CMP?

A

Band and collars

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

What is true about a fiber tubular column? (Sonotube forms)

A

With proper care they are reusable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
60
Q

According to OSHA, a scaffold with a horizontal dimension less than 45 inches in either direction shall have standard guard rails on all sides and ends if it is over what minimum length?

A

12’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
61
Q

All of the following will affect the load capacity of a mobile crane

A

Hydraulic pressure limits, the quadrant in which it is working, and the boom angle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
62
Q

Lime is an affective stabilizing agent for

A

Expansive clay

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
63
Q

According to design in control of concrete mixturess, air entrained concrete is mainly used to

A

Reduce damage by freeze/thaw cycles

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
64
Q

Which of the following drawings is done on graph paper and shows natural ground, finish grade, gutter flow lines, and sewer and drainage line

A

Profile sheet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
65
Q

What is meant by a road “super”?

A

Continuous slope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
66
Q

A pile head is usually used when piles are driven. What can be substituted for the driving head?

A

Pile ring

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
67
Q

What is the shape of a permanent highway warning sign?

A

Diamond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
68
Q

What is the difference between using an official car and a pilot car for one-way traffic control during highway construction?

A

An official car follows the last car and a pilot car leads a line of cars

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
69
Q

When delineators are used to outline the required vehicle pass through a highway construction site, the reflective unit should be placed a minimum of _____ inches above the roadway

A

48”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
70
Q

Which of the following describes a test that measures concrete consistency?

A

Slump

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
71
Q

Which of the following is not a pre-draining de-watering system

A

Slump hole

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
72
Q

What is soil distress when you are performing benching work in a confined space?

A

Cave in imminent or likely to occur

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
73
Q

Which of the following has the least impact on the success of compaction of a new asphalt pavement service?

A

Environmental conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
74
Q

What is not an advantage of using rip rap for channel walls?

A

Uplift protection

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
75
Q

Safety nets which are to be used during construction shall extend beyond the edge of working surface, according to OSHA, by ____ feet

A

8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
76
Q

Leveling nuts securing a bridge column bearing plate are tightened and adjusted. What is the final operation performed for bearing support?

A

Grout with non-shrink grout

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
77
Q

Horizontal members on the outside of pre-fabricated forms used to straighten align forms are called

A

Walers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
78
Q

A bridge deck is prepared for an asphalt overlay, what can be the result of an excess application of tack material

A

Asphalt slip

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
79
Q

Damping of the subgrade prior to placement of concrete will

A

Prepare rapid water extraction of the mixing water from the concrete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
80
Q

When tying reinforcing steel, a saddle or butterfly tie is used:

A

Where the reinforcing bars cross each other

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
81
Q

In addition to providing freeze/thaw resistance, air entrainment will also improve the _____

A

Workability

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
82
Q

According to the design control and concrete mixture, after 300 drum revolutions or ___ hours, structural concrete shall be rejected

A

1-1/2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
83
Q

Structural concrete slabs, columns and other members should be protected ____ percent of their design strength

A

70%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
84
Q

The datum point, property lines, read lines, and utility easements or shown on the _______ plan

A

Plot

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
85
Q

The most common gauge of tie wire are used in the installation of reinforcing steel is ____ gauge

A

16 gauge

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
86
Q

As concrete sets, water will rise to the top, this is known as

A

Bleed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
87
Q

In comparing normal concrete to high early concrete (type III), how much do you reduce the curing time for high early?

A

4 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
88
Q

The largest size of standard size rebar that can be lapped spliced is

A

11

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
89
Q

When using a vibratory roller, if rippling occurs what should you do?

A

Increase frequency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
90
Q

What components make up a screed?

A

Screed plate and adjusters with vibration bars

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
91
Q

When laying asphalt uphill, the breakdown roller (drive roller) should travel

A

Up hill behind the paver

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
92
Q

What is the minimum distance for posting construction signs on a construction site?

A

1500’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
93
Q

On a concrete highway project using a train slip form paver, the slump should be

A

Less than 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
94
Q

Corrugated metal pipe (draw pipe) comes in what multiple lengths?

A

2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
95
Q

You are placing concrete culverts and you know that problems will occur with the joints. To prevent this you should:

A

Place concrete embankments on the ends

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
96
Q

What type of pile has the most friction?

A

Wood

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
97
Q

Where is the Arrow Panel set?

A

Before the channelization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
98
Q

What is a cofferdam used for?

A

Temporarily hold back dirt and water

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
99
Q

What part of a headwall directs the flow of water?

A

Wing wall

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
100
Q

What is not used for the down stroke of a hammer on a pile driver?

A

Gasoline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
101
Q

What is used to guide a pile?

A

Leads

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
102
Q

What protects the top of a pile while driving?

A

Cushion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
103
Q

What type of hammer drives piles the fastest?

A

Vibratory

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
104
Q

A pile that is driven into the ground and leaves the shell or casing is called what?

A

Shell

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
105
Q

What type of pile is enlarged on the end in order to provide a larger bearing area?

A

Bell pile

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
106
Q

What piledriving operation uses high water pressure?

A

Jetting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
107
Q

What is the most commonly used type of equipment to drive a pile?

A

Hydraulic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
108
Q

What is the upper part of a pile called after it was driven?

A

Head

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
109
Q

Wide flange beams driven vertically to retain material are known as

A

Soldier beams

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
110
Q

What powers a single action pile driver?

A

Gravity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
111
Q

What can be used to drive a pile in place of a cushion?

A

Ring collar

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
112
Q

Two scrapers are being operated as a team for a highway excavation. The scrapers are equipped with bumpers and bales and each can provide power to help the other load. This type of operation has been described as

A

Push pull

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
113
Q

A scraper capable of operating by it’s self is known as a

A

Elevating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
114
Q

What does grade 40 on a piece of re-bar mean?

A

40,000 pounds per square inch tensile

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
115
Q

A stable mix of asphalt, cement, water, and soap is

A

Emulsified asphalt

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
116
Q

Asphalt compaction using a roller should begin:

A

When there is no undue lateral movement of the asphalt under the roller

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
117
Q

Freshly paved asphalt can be opened to vehicular traffic:

A

As soon as the final rolling is complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
118
Q

How do paving machine’s maintain crowned services?

A

The screed plate and tamping bar are hinged in the center

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
119
Q

Movement of the soil on a wet section of road caused by equipment is called

A

Pumping

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
120
Q

The most common bituminous paving materials in use today are

A

Petroleum asphalts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
121
Q

The setting of a floating screed for the desired asphalt depth is called

A

Leveling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
122
Q

The solvent usually used for medium - cure liquid asphalt is:

A

Naphtha

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
123
Q

What is the best type of sub base aggregates used in asphalt concrete for Highway paving?

A

Elongated

124
Q

How many cubic feet equal one cubic yard?

A

27

125
Q

What is the minimum height of a type III barricades?

A

5’

126
Q

Aggregate particles used for concrete should be shaped like

A

Cubes

127
Q

What of the following is the most danger for a long boom crane?

A

Wind

128
Q

When laying slip ring pipe it is necessary to:

A

Lubricate the spigot end before connecting together

129
Q

Which is not an advantage of hydraulic shoring over the use of screw jacks?

A

The pump cylinders are all activated at the same time

130
Q

What would you call grade stakes set in the roadway for fine trimming?

A

Blue tops

131
Q

What is wedge leveling?

A

Patches of asphalt used to level sags and depression in an old pavement

132
Q

What finish does a drainage ditch invert get?

A

Bull float smooth

133
Q

When boring under a road, which method is not acceptable?

A

Sheeting

134
Q

What earthmoving equipment does not require additional help dumping?

A

Elevating scraper

135
Q

On schedule 40 pipe, when does the standard wall thickness change?

A

10”

136
Q

When laying concrete bell pipe, the

A

Female end upstream fully bedded

137
Q

At what speed do you set a pedestrian crosswalk signal?

A

4 ft per second

138
Q

What is the size of a stop sign?

A

30” x 30”

139
Q

What is used to divide a 2 Lane Rd.?

A

A broken yellow stripe

140
Q

According to OSHA all scaffolding over ____ feet high shall have guard rails and toe boards

A

10

141
Q

What is the weakest form of sheet piling?

A

Flat

142
Q

A curve has a 200 foot radius, what is the suggested spacing for the delineators?

A

35’

143
Q

And advisory speed plate sign is what color?

A

Yellow background with black letters

144
Q

Which of the following colors are allowed to be used for pavement marking?

A

White yellow and red

145
Q

Which of the following is a common field test used to determine soil settlement?

A

Field density

146
Q

What size sieve is used to measure filler material in asphalt?

A

200

147
Q

What test is used to determine particle size for aggregate?

A

Sieve analysis

148
Q

A slope of 1/4” per foot is what percent?

A

2

149
Q

What would be power injected into soil to improve its stability?

A

Lime

150
Q

What can be used in place of a cushion to keep the head of a pile from splitting?

A

Ring

151
Q

What is the height of all construction signs?

A

7’

152
Q

2” x 2” stakes left on the side of the roadway that are used for grading are known as ___

A

Crows feet

153
Q

Concrete pavement is being laid, in the afternoon it is stopped and then started the next day. What type of joint has been created between the old and new pavement?

A

Construction

154
Q

What is used to mark an island median?

A

Double solid yellow line

155
Q

What color line is used to mark the left edge of a rural Highway?

A

Yellow

156
Q

All of the following are overhead signs except

A

Speed limit

157
Q

The shape of all construction signs are

A

Diamond

158
Q

Which of the following signs it is not mandatory?

A

Hi speed traffic ahead

159
Q

What is the background color for all highway exit signs?

A

Green

160
Q

How can a motorist become involved in traffic control on a paving project?

A

By becoming a flag carrying car

161
Q

According to OSHA all equipment manufactured on or after September 1, 1972 shall be equipped with ROPS systems. Which of the following statements is true?

A

All equipment with a ROPS system are required to have seatbelts and any equipment without a ROPS system cannot have a seatbelt

162
Q

If a station is 467’ from 0, how is it designated?

A

4 + 67

163
Q

What is a nail “stripper” used for in shingle operations?

A

A box worn by a roofer to orient nails

164
Q

According to OSHA the minimum clearance between power lines that are below 50 kVA and any part of an operating crane or load shall be

A

10’

165
Q

Concrete bridge decks require a final finishing within one hour of placement. The final age of bridge decks require:

A

Brooming perpendicular to the finish operation

166
Q

The purpose of bull floating a freshly placed slab is to:

A

Embed large aggregates and level the surface

167
Q

What is the size of a flagman’s hand held sign paddle?

A

18’ wide

168
Q

According to the occupational safety and health rules and regulations when employees are required to be in trench at least ____ feet deep or more and unstable soils where there is danger at Cave in the sides shall be shored, sheeted, braced or sloped

A

5’

169
Q

According to ASTM standards a number six rebar will fit which of the following?

A

1.50 lbs per foot

170
Q

When superplasticizers are used in a concrete mix with less water for the same workability, they will:

A

Accelerate set up time

171
Q

When lifting a load with a crane, what is used to stabilize the load?

A

Balance beam

172
Q

What type of pile is used when there is no bearing foundation? (Sand or earth with no bed rock)

A

Friction pile

173
Q

When grooves are cut into concrete to act as control joints, what percentage of the depth of the slab should they be cut?

A

25%

174
Q

When pouring concrete underwater with a tremie, the end of the tremie should always be kept

A

Below the concrete

175
Q

What is not a mandatory highway control sign?

A

Movement series

176
Q

Large diameter culverts can be fitted together using all of the following except

A

Spud bar

177
Q

The advantages of using emulsified asphalt are of the following except

A

Has a higher cost over petroleum asphalt

178
Q

Which is not an option for a survey company holding a contract on a construction project and in the event a contractor files bankruptcy?

A

Pay back all monies spent on project

179
Q

What is the most practical method for cleaning metal in the shop?

A

Power wire brush

180
Q

What are the size of the numbers and letters on a mile post sign?

A

6” numbers 4” letters

181
Q

The responsibility for the design, placement, operation, and maintenance of traffic control devices rests with

A

The governmental body having jurisdiction

182
Q

Which of the following paint applications leaves the flattest finish?

A

Spraying

183
Q

What is the minimum depth of setting a pole that is 20 feet long in soil?

A

5’

184
Q

What is the minimum depth that an 80 foot pole can be set?

A

10 (10% of the height + 2)

185
Q

What does 1 + 50 on a station marker mean?

A

150’

186
Q

Floating concrete is done when?

A

After the surface water is not visible

187
Q

What test do you use to find the maximum density of soil?

A

An unconfined compressive strength tests

188
Q

When should concrete be reshored?

A

As the original forms and shores are removed

189
Q

When using a concrete vibrator, what is a sign that the vibrator should be with drawn?

A

When air bubbles are no longer coming to the surface

190
Q

What is used to determine the density of asphalt?

A

Nuclear density test

191
Q

When are concrete cylinders tested?

A

Day 3 and 28

192
Q

When is bull floating performed?

A

After screeding when there is no visible surface water

193
Q

What size lifts are used for asphalt placement?

A

6” to 8” lifts

194
Q

What is used to test the thickness of asphalt?

A

Probe

195
Q

What is a silt fence used for?

A

To prevent material from leaving a designated area

196
Q

What type of aggregate has the highest sheer point?

A

Coarse

197
Q

What is the lowest temperature in the shade that asphalt should be laid?

A

45°

198
Q

Which soil would water drain the fastest from?

A

Gravel

199
Q

What bulldozer blade would be used for clearing?

A

A-blade

200
Q

What is the height of a road speed limit sign?

A

7’

201
Q

What color are the reflectors on a yellow road stripe?

A

Yellow

202
Q

How should a concrete cylinder be stored for testing?

A

Similar conditions to the job site

203
Q

How is a slump test performed?

A

You fill the cone 1/3 of the way, tamp 21 times then fill another 1/3 of the way and repeat until completely full, level with the top

204
Q

If after starting a job you find that marsh vegetation must be moved who do you contact?

A

Department of environmental quality

205
Q

When joining two culverts under a driveway what should be used to seal the joints?

A

Cretex wrap

206
Q

When placing a 48 inch culvert in a trench how wide should the trench be?

A

72”

207
Q

What size pipe is used when pouring concrete with a tremie?

A

10”-12”

208
Q

Which step in concrete finishing is to level?

A

Screeding

209
Q

How far must a net extend beyond a bridge?

A

8’

210
Q

How long is a buoy lifeline?

A

90’

211
Q

What is the order for rolling asphalt?

A

Wheel, smooth, smooth

212
Q

Where is the safest place for a backhoe loading a truck on a slope to be?

A

Behind the truck

213
Q

If an asphalt mix is stiff and has large amount of rocks. What happened?

A

The mixture content was not properly portioned for the specific pour

214
Q

How many inches of fill can be compacted around a culvert?

A

6 to 8 inches at a time until it is even with the top of the culvert

215
Q

When is the best time to plant Stenotaphrum Secundatum? (Saint Augustine grass)

A

Spring

216
Q

Which of the following is done to an asphalt roller?

A

Saturate with water

217
Q

What are railroad right of ways marked with?

A

Concrete barriers

218
Q

“Tighten the nut” technique means what?

A

Tighten the nut all the way

219
Q

What type of shoring is used in 10’ trench?

A

Hydraulic

220
Q

How long after forms are removed from concrete columns do you wait before you can fix bulges, voids, or make rebar holes?

A

Immediately

221
Q

What is the purpose of a long handled bull float with a magnesium or wooden blade?

A

To embed/push down concrete

222
Q

When installing steel joists which of the following is done last?

A

Place platform on top

223
Q

Where do you go to get information on allowable clearing and grubbing techniques used in a certain area?

A

Local city government office

224
Q

When is the air content test done on concrete?

A

5 min

225
Q

What is the best way to connect Geo textile’s?

A

Staples

226
Q

When transplanting oysters from public waters to another area who must be notified?

A

Department of natural resources

227
Q

What must a worker in the bottom of a bell hole be supplied with?

A

A lifeline and safety lanyard

228
Q

What is a true statement about putting down concrete?

A

The manhole covers should be removed before and not replaced until after completion

229
Q

How far off the roadway do overhead signs need to be?

A

6 feet

230
Q

What color are the barrels in a construction site zone?

A

Orange

231
Q

How long do construction lights flash for?

A

During working hours and at night

232
Q

What is the number for LaOneCall?

A

811

233
Q

What is the minimum width of scaffolding?

A

18”

234
Q

How is a mesh roll installed?

A

Nail around the frame

235
Q

If you have to use the bent rebar where is it usually bent?

A

The shop

236
Q

How is rebar marked when it is delivered to the job site?

A

Tagged

237
Q

How much are geotextiles overlapped?

A

18” overlap

238
Q

How is geo textile placed?

A

Under the rip rap

239
Q

If you are driving a back hoe up a hill which of the following will not improve steering?

A

Extending the boom out over the back of the backhoe

240
Q

What is the best way to turn cement?

A

Rotary drum

241
Q

What is the best way to dry out clay?

A

Plow and pulverize

242
Q

What is the minimum width of the lane markers?

A

4”

243
Q

What is used to compact asphalt?

A

Smooth roller

244
Q

When pouring concrete in a hole what is put first?

A

Sand and gravel

245
Q

When putting a pile in marshy area what do you use?

A

Friction pile

246
Q

When repairing a pothole how high do you fill it beyond the existing asphalt?

A

1”

247
Q

When repairing a crack in a concrete slab how far beyond the crack do you replace?

A

2”

248
Q

How deep should concrete sealant be placed?

A

A minimum of 3/8 inch

249
Q

What equipment is best for drying soil?

A

Sheep’s foot roller

250
Q

What is the percentage of cement in concrete?

A

7%-15%

251
Q

What causes lung problems when the sandblasting?

A

Crystalline silica

252
Q

When building an embankment how do you place the fill if it is on both sides of a masonry wall?

A

Equal Heights on both sides as you work up

253
Q

What is the next step after soil and cement?

A

Smooth drum roller

254
Q

What size lifts are used for cold mix?

A

Maximum of 2 inch lifts

255
Q

How many lifts are required for a cold mix?

A

Minimum of three

256
Q

When is a cylinder tested?

A

3-28 days

257
Q

How are beams stored at a job site usually?

A

The way they are transported to the job site

258
Q

Who can give the emergency stop signal to a crane operator?

A

Anyone

259
Q

How long should the slump test take approximately?

A

2 1/2 min

260
Q

How is a slump test filled?

A

1/3 at a time

261
Q

Before digging, who do you call?

A

La. One Call

262
Q

If no backfill is to be placed over a culvert what is done?

A

Concrete walls on the ends

263
Q

How long do construction lights flash for?

A

During the hours of darkness

264
Q

What type of life jacket is worn when working over a body of water?

A

US Coast Guard approved life jacket or buoyant work vest

265
Q

What type of aggregate has the highest sheer point?

A

Coarse

266
Q

What is the proper order of finishing concrete?

A

Screed, tamp, float, trowel

267
Q

Basis of payment for culvert pipe is

A

Linear foot

268
Q

When demolishing a building, when should the brakes be applied for a wrecking ball?

A

Immediately when the ball hits the building

269
Q

Concrete culvert going into catch basin will have an elbow on it. The elbow will be facing which way?

A

Downward

270
Q

Anchor bolts are held in place by:

A

Template

271
Q

Removal of a concrete driveway may be performed by

A

Anyone

272
Q

When delivered to a job site how is the rebar tagged?

A

By the bundle

273
Q

When separating and straining aggregate, what device is used?

A

Sieve

274
Q

What type of washer has protrusions on the face which flatten as the bolt is tightened?

A

Load indicator washer

275
Q

When laying welded wire fabric in a form, what is done at the ends?

A

Lapped a full mesh

276
Q

When safety nets are required on steel erection and bridge construction and are placed 10 feet below the working surface, what is the minimum required horizontal distance of the outer edge of net from the edge of the working surface?

A

13’

277
Q

What is the minimum length of safety line attached to a ring life buoy

A

90’

278
Q

When would arrow panels be used?

A

Channelizing traffic

279
Q

When driving a pile and the head is damaged, what would be the best way to proceed?

A

Lower pressure

280
Q

What is the proper number of roddings needed at each level of a slump test?

A

21

281
Q

What is the orientation of the rotation of rotors on a pugmill?

A

Rotate toward each other

282
Q

When painting a steel member of a bridge with a three coat-poly, the primer coat is placed first, how long till primer is cured?

A

Minimum of two hours

283
Q

Soil and cement is rolled to apply pressure and compact

A

Heavy clay

284
Q

When compacting soil and cement, it is rolled best with

A

Tampering vibrating sheep’s foot roller

285
Q

Which of these hammers is the quietest during operation?

A

Double action vibratory extractor

286
Q

Other than water, soap, and asphalt what else makes emulsified asphalt?

A

Emulsifying agent’s

287
Q

What tool is used to make a joint in asphalt straight?

A

Lute

288
Q

What material may be used to seal cast iron soil pipe?

A

Elastometric compression gaskets

289
Q

When driving a pile 1 foot above the floor of 10 foot deep water way you would

A

Have a lead and hammer in water if it’s sealed and rated for underwater use

290
Q

While setting a concrete form, you see a crack in the lap splice of rebar. What should you do?

A

Place a clamp over it or remove that section

291
Q

Soil and cement is placed, what is the best type pneumatic roller to compact with?

A

Waffle roller

292
Q

A single 2 Lane Rd. within a construction project, with traffic going in different directions. Delineators would be what colors?

A

White delineators on the outside of the lanes. Yellow between lanes

293
Q

When ordering large sizes of lumber from a mill, you should order in lengths as you choose?

A

In even lengths

294
Q

What is the name of that text book that governs the street signs and roadway markings?

A

UTCD

295
Q

What is the best choice for aggregate to use when mixing asphalt?

A

Crushed angular aggregate and fine sand

296
Q

How is rip rap sheathing used?

A

Overlapping layers

297
Q

If two cars are moving in the same direction and the cars can’t pass each other, what type and color of line is required between the lines?

A

Single solid white

298
Q

What type of bulldozer blade has a pointed edge extended at one side used for clearing and grubbing work?

A

Rome K/G

299
Q

What is the safest way to use a front end loader to fill a dump truck that is parked on a hill at an incline?

A

From behind the truck, facing downhill

300
Q

When you straighten welded wire mesh to place in slab, what is the best method?

A

Cut bent areas in parallel

301
Q

What is the typical diameter of tremie pipe?

A

10-12”

302
Q

According to OSHA specifications, at what minimum depth is a shoring or sloping required to protect workers in a trench?

A

5’

303
Q

According to OSHA specifications, at what minimum distance from a worker is a ladder required to exit a trench?

A

25’

304
Q

According to OSHA specifications, at what maximum distance can ladders be placed in a trench?

A

50’

305
Q

What is the minimum height of the bottom of traffic signs where pedestrians are present?

A

7’