L&E - DONE Flashcards

1
Q

What is loss and expense claim?

A

Reimburses the contractor for direct loss and/or expense incurred in carrying out additional work or from an employers breach of contract (Relevant matter)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the procedures for claiming loss and expense?

A
  • The contractor notifies the Contract Administrator as soon as they become aware of any matter that would cause them to incur L&E (Relevant matter)
  • The contractor submits any info as requested by the CA to enable the amount of loss and expense to be ascertained

Key Points:
- Contractor cannot claim for cost of preparing claim
- No automatic right of recovery solely because an extension of time (relevant event) has been granted
- L&E can occur without EOT
- Its duty of CA to ascertain amounts due

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the key thing to remember when assessing L&E claims?

A

It should be the ACTUAL loss incurred by the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Do you need an EOT for L&E claims?

A

No, L&E can be due without an EOT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the common items of claim in L&E applications?

A
  • Prolongation (extra site overheads i.e. prelims)
  • Thickening of prelims (e.g. extra supervision required due to variation)
  • Disruption (causing plant / labour to be underemployed - hard to prove)
  • Increases in labour / material costs during the period of delay
  • Head office overheads
  • Loss of profit (commonly combined with head office overheads)
  • Finance charges (i.e. interest)
  • Acceleration costs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Can the cost of preparation for the claim be included in the claim?

A

The cost of preparing a claim is a not a legitimate head of claim and must be covered by the contractors overheads

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Once L&E is ascertained how is it added to the contract sum?

A
  • It should be added to the contract sum immediately and paid in the next interim certificate
  • It is not subject to retention
How well did you know this?
1
Not at all
2
3
4
5
Perfectly