PMP Study Flashcards

PMP Exam Prep

1
Q

Point of Total Assumption Formula

A

PTA = ((Ceiling Price - Target Price)/Buyers Share Ratio) + Target Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Risk Formula

A

Risk Probability x Risk Impact = Impact/Probability Index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Cost of Risk Formula (Expected Monetary Value)

A

Risk Probability x Financial Impact = Expected Monetary Value = Contingency Reserve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Processes for Risk Management

A

1) Plan Risk
2) ID Risks
3) Perform Qualitative Risk Analysis
4) Perform Quantitative Risk Analysis
5) Plan Risk Responses
6) Implement Risk Response
7) Monitor Risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

11.5 Plan Risk Responses - Threats

A

Strategies for Threats

1) Escalate
2) Avoid
3) Transfer
4) Mitigate
5) Accept

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

11.5 Plan Risk Responses - Opportunity

A

Strategies for Opportunities

1) Escalate
2) Exploit
3) Share
4) Enhance
5) Accept

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

(8.2) Manage Quality - Steps for Problem Solving

A

Steps for Problem Solving

1) Define the Problem
2) ID the Root Cause
3) Develop Potential Solutions
4) Pick a Solution
5) Implement Solution
6) Verify the Solution effectiveness

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

(9.4) Develop Team: 5 Stages of Team Develop

A
5 Stages of Team Develop
□ Forming
□ Storming
□ Norming
□ Performing
□ Adjourning
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

(9.4) Develop Team: Conflict Mgmt. Types

A
Conflict Mgmt. Types
□ Withdraw/Avoid (Lose-Lose)
□ Smooth/Accommodate (Lose-Lose)
□ Force/Direct (Win-Lose)
□ Compromise/Reconcile (Lose-Lose)
□ Collaborate/Problem Solve (Win-Win)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

(9.5) Manage Team: Forms of Power

A
Forms of Power
□ Positional
□ Expert
□ Reward-Oriented
□ Punitive or Coercive
□ Referent
□ Informational
□ Situational
□ Personal or Charismatic
□ Ingratiating
□ Pressure-based
□ Guilt-based
□ Persuasive
□ Avoiding
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Maslow’s Hierarchy of Needs

A
  1. Self Actualization
  2. Esteem
  3. Social
  4. Safety
  5. Physiological
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Earned Value Analysis: Planned Value (PV)

A

The value of all the work completed (earned) to a point in time, usually the data date, or project completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Earned Value Analysis: Earned Value (EV)

A

The planned value of all the work completed (earned) to a point in time, usually the data date, without reference to actual costs
EV = Sum of planned value of completed work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Earned Value Analysis: Actual Cost (AC)

A

The actual cost of all the work completed to a point in time, usually the data date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Earned Value Analysis: Budget at Completion (BAC)

A

The value of total planned work, the project cost baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Earned Value Analysis: Cost Variance (CV)

A

The difference between the value of work completed to a point in time, usually the data date and the actual costs to the same point in time.
CV = EV - AC

17
Q

Earned Value Analysis: Schedule Variance (SV)

A

The difference between the work completed to a point in time, usually the data date, and the work planned to be completed to the same point in time.
SV = EV - PV

18
Q

Earned Value Analysis: Variance at Completion (VAC)

A

The estimated difference in cost at the completion of the project
VAC = BAC - EAC