PMP Study Flashcards
PMP Exam Prep
Point of Total Assumption Formula
PTA = ((Ceiling Price - Target Price)/Buyers Share Ratio) + Target Cost
Risk Formula
Risk Probability x Risk Impact = Impact/Probability Index
Cost of Risk Formula (Expected Monetary Value)
Risk Probability x Financial Impact = Expected Monetary Value = Contingency Reserve
Processes for Risk Management
1) Plan Risk
2) ID Risks
3) Perform Qualitative Risk Analysis
4) Perform Quantitative Risk Analysis
5) Plan Risk Responses
6) Implement Risk Response
7) Monitor Risks
11.5 Plan Risk Responses - Threats
Strategies for Threats
1) Escalate
2) Avoid
3) Transfer
4) Mitigate
5) Accept
11.5 Plan Risk Responses - Opportunity
Strategies for Opportunities
1) Escalate
2) Exploit
3) Share
4) Enhance
5) Accept
(8.2) Manage Quality - Steps for Problem Solving
Steps for Problem Solving
1) Define the Problem
2) ID the Root Cause
3) Develop Potential Solutions
4) Pick a Solution
5) Implement Solution
6) Verify the Solution effectiveness
(9.4) Develop Team: 5 Stages of Team Develop
5 Stages of Team Develop □ Forming □ Storming □ Norming □ Performing □ Adjourning
(9.4) Develop Team: Conflict Mgmt. Types
Conflict Mgmt. Types □ Withdraw/Avoid (Lose-Lose) □ Smooth/Accommodate (Lose-Lose) □ Force/Direct (Win-Lose) □ Compromise/Reconcile (Lose-Lose) □ Collaborate/Problem Solve (Win-Win)
(9.5) Manage Team: Forms of Power
Forms of Power □ Positional □ Expert □ Reward-Oriented □ Punitive or Coercive □ Referent □ Informational □ Situational □ Personal or Charismatic □ Ingratiating □ Pressure-based □ Guilt-based □ Persuasive □ Avoiding
Maslow’s Hierarchy of Needs
- Self Actualization
- Esteem
- Social
- Safety
- Physiological
Earned Value Analysis: Planned Value (PV)
The value of all the work completed (earned) to a point in time, usually the data date, or project completion
Earned Value Analysis: Earned Value (EV)
The planned value of all the work completed (earned) to a point in time, usually the data date, without reference to actual costs
EV = Sum of planned value of completed work
Earned Value Analysis: Actual Cost (AC)
The actual cost of all the work completed to a point in time, usually the data date
Earned Value Analysis: Budget at Completion (BAC)
The value of total planned work, the project cost baseline