The project manager is reviewing the program risks and issues with key stakeholders. One of the stakeholders wants to understand when the risk may potentially become an issue.
What artifact should the project manager share with the stakeholder?
D. Risk register
After 1 year Into the life cycle of an ongoing residential project, an announcement was received from the municipality regarding a new regulation that will greatly impact the project’s schedule and budget.
What should the project manager do next?
C. Update the issue log and discuss it in the next steering committee meeting.
During the initiating phase of a project, a key stakeholder requests frequent changes to the project scope.
What should the project manager do to improve the stakeholder’s engagement?
D. Discuss the project scope statement with the key stakeholder and build prototypes
A product company is transforming the way it develops and releases products in the market. Executives believe that this is a high-risk initiative, and this initiative must be successful.
What should the project manager do in this scenario?
C. Adopt an iterative rollout approach that delivers the highest business value earlier
A company is initiating a project to enhance one of its existing products. All of its products are developed internally.
What should the project manager do?
B. Review the lessons learned from the previous project
A project manager joins a startup and discovers that the chief technology officer (CTO) encourages the team to overlook some procedures in the interest of speed.
What should the project manager do to ensure that all the procedures are followed in the future?
C. Instruct the team that the procedures should always be followed.
The project manager of a hybrid project learns that a stakeholder has approached a team member directly to request a change. This change will impact the project in a significant way.
The project manager should
then tell the stakeholder that the correct procedure for new requirements is to provide a request directly to whom?
D. Project manager
A project manager is establishing a project management office (PMO) for a company-wide program to implement software based on artificial intelligence (AI). As part of the PMO tasks, some stakeholders need help understanding how to deal with difficult situations.
Which activity should the project manager use to help train the stakeholders?
C. Mentoring and coaching
A highly skilled team resource received a job offer and is leaving the project soon.
What should the project manager do to maintain project performance while a new team member is being onboarded?
D. Offer cross-training and mentoring to the new team member
A project manager is managing an internal project that was poorly defined. Recently, the project manager received several change requests raised by the organization’s upper management.
What should the project manager do first?
C. Request a provisional budget increase to avoid any budget overruns.
For an agile pilot project, the sponsor arranged an early product demonstration for the customer. During the meeting, the customer realizes that a new feature will significantly improve the product.
After collecting the new requirements, what should the project manager do?
A. Assess the impact of the new requirements and initiate the change request process.
Early in the execution phase, a project manager discovers that recent changes in enterprise environmental factors (EEFs) will severely reduce the implementation cost and shorten the project schedule.
How should the project manager address this situation?
D. Follow the project escalation policy and communications management plan
A project manager is in the process of creating a strengths-based team and is organizing a series of workshops to identify and document the strengths of each project team member.
During this session, there are multiple team members who are not actively participating. These meetings are becoming futile due to a lack of participation.
What should the project manager do?
D. Explain the benefits of the approach and the effects of positive psychology.
A project manager brings in a new team member from an agile environment to work in a predictive environment. The project manager expects to leverage the new team member’s agile experience with the existing team members.
What should the project manager do to integrate the new team member effectively?
C. Set expectations with the new team member and explain what is needed
A project manager who is new to an organization observes that an approaching deadline is likely to be missed because there have been some delays on the project due to a lack of resources.
What should the project manager do next?
D. Organize a team meeting to discuss the next course of action
An international client contacted a software development company to build out a software product, and an agile project manager was assigned. At one of the review meetings, the client complains that a feature mentioned at the initial debriefing was not implemented.
What should the project manager do?
C. Review the original project documentation to confirm.
A project for Company A was successfully delivered within scope schedule, and budget by the end of the last iteration.
However during the project celebration ceremony, one of the business stakeholders says they perceive the project as a failure as it did not add any business value.
What should the project manager have done to avoid this perception?
B. Defined product backlog priorities with the sponsor and key stakeholders to deliver business benefits
The project team follows a hybrid framework for its delivery.
During the execution of a project, the team learns of a new compliance requirement that has to be delivered before any other requirements.
How should the project manager address this situation?
D. Collaborate with the compliance team member to review and prioritize the requirement’s delivery
The marketing team is transitioning to using hybrid approaches for their projects. The marketing director is not knowledgeable about hybrid methodologies and the project manager needs the director’s support as
the marketing director is a key stakeholder.
What should the project manager do to obtain the support?
B. Mentor the marketing director on hybrid approaches
An agile project is running its second of six iterations. One new team member who does not have agile experience has just joined the team. In the daily meetings, the project manager observes that the team is
having problems meeting their goals.
What should the project manager do?
B. Provide feedback to the team and conduct a retrospective meeting to find a root cause.