Project phases Flashcards
Phase 0:
Mission analysis/identification of requirements.
main outputs:
identification and characterization of…
• the proposed mission,
• user needs and expected performance
• mission constraints,
• definition of possible system concepts
• first assessment of project management (organisation, costs, schedules).
Phase A:
Feasibility phase:
Refinement (genauer definieren) of the needs expressed in phase 0.
main outputs:
• Critical mission elements, quantity and type
• Function tree of the mission,
• Evaluation various possible system concepts
• Determination of uncertainty and mission risks
• Discussion of the technical and industrial feasibility
At end: Preliminary Requirements Review (PRR) -> system concept selection
Phase B:
Preliminary design of the mission
Main tasks:
• Selection of technical solutions for the system concept
• Precise and coherent definition (performance levels, costs, schedules) at every level
• Product tree and products specifications,
• Identification of ‘Make or buy’ alternatives,
• Confirmation of the feasibility of the proposed solution
• Definition of mission risks and fall back options
• Assessment of manufacturing, production and operating costs
• Reliability and safety assessment,
At end: Preliminary Design Review (PDR)
Phase C:
Detailed design of the mission
main issues:
• Detailed definition and detailed design of the system and its components,
• Final ‘make or buy’ decision for the products,
• Confirmation of the set-up, test and qualification conditions,
• Final definition of the methods and means of production and verification,
• Procurement of the Production Master File,
• Production of the first models of the system,
• Development of interfaces within the configuration
• Preparation of phase E activities.
phase results in acceptance of Production Master File
Phase D:
Production and ground qualification testing
Phase D is the end of the system development.
goal at end: Production Master File and operational documentation
main objects:
• a qualified definition of the products, components and the system itself
• production of material, software and components
• confirmation and qualification of methods, procedures, production and verification
• manufacture, assembly, integration and verification, to conduct the Qualification Reviews,
• Ground qualification testing (design qualification and operational qualification).
end: Acceptance Review (AR), which comprises all mission elements.
Phase E
Utilisation phase
- launch campaign
- launch and in-flight acceptance of the satellites,
- operation and maintenance of the system.
Is often divided into two sub-phases:
• sub-phase E1: overall test and commissioning phase of the system
• sub-phase E2: utilisation phase itself
Phase F:
- covers all events from the end-of-life till final disposal of the product
- protected space regions beachten
- European Code of Conduct for Space Debris Mitigation: max. 25 jahre nach missionsende weg
This can be achieved by:
- direct re-entry of the space system (aktiv)
- limiting the orbital lifetime to less than 25 years after operational phase (passiv)
- transferring the space system to a graveyard orbit