River Exe Case Study Flashcards
1
Q
Location
A
- Devon
- Source is in the hills of Exmoor
2
Q
Physical geography of the upper catchment
A
- maximum elevation 514m
- minimum elevation 26m
3
Q
Land use in the upper catchment
A
65% of the catchment is agricultural grassland
4
Q
Geology of the upper catchment
A
underlain by impermeable rocks
5
Q
water balance
A
- high rainfall
- low percolation and groundwater flow due to the impermeable rock
- surface runoff accounts for 65% of water balance
- drainage ditches also reduce the amount of soil water storage
6
Q
The Wimbleball reservoir
1) What does it do?
2) How has it impacted the water cycle?
A
- supplies water to Exeter and East Devon
- regulates water supply throughout the year
- prevents peaks and troughs of river discharge, reducing flood risk
7
Q
Peatlands in Exmoor
1) What was it like in the past?
2) How did it impact the water cycle before the project?
A
- drainage ditches were previously dug into the peatlands to make the land suitable for farming
- the increased the water flow to the river
- as the peatlands dried out, the carbon that was stored got released into the atmosphere
8
Q
What was the Exmoor Mires Project?
A
- Blocked previously dug drainage ditches in order to restore water supply to the peatlands
9
Q
give 4 benefits of the Exmoor Mires project?
A
- improved water quality
- improved grazing and water supply for animals
- increased carbon storage
- more water storage in the upper catchment ensures a steady supply of water throughout the year