Scheduling, Budget and Cost Estimating, Delivery Methods & Fees Flashcards

1
Q

Area / Volume Cost Estimates

A

Cost estimate based on cost per square foot of area or cubic foot of volume. Best for firms that extensive information or specialty knowledge.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Construction Budget

A

85% of Project Budget • Anticipated contract price • Small contingency allowance for change orders • Other cost incurred during construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Critical Path Method

A

A system of planning and scheduling construction operations that analyzes sequences and durations of time using network diagrams and identifies construction tasks that have great impact in schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Design-bid-build project delivery method

A

Traditional method or hardbid, is a project delivery method in which the agency or owner contracts with separate entities for both the design and construction of a project. There are three main sequential phases: • The design phase • The bidding (or tender) phase • The construction phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Design-build project delivery method

A

The Owner contracts with a single entity that is responsible for both the design and the construction of a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Detailed Cost Estimates

A

A forecast of construction prepared on the basis of a detailed analysis of materials and labor for all items of work, as distinguished from preliminary estimate of construction cost based on current area, volume, or similar conceptual estimating techniques.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Cost-plus-fee

A

An owner agreement under which the contractor or architect is reimbursed for stipulated direct and indirect costs of performance of the agreement and, in addition, is paid a fee for services.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Fast track project delivery method

A

A construction technique by which construction on each element of a project is begun as soon as the design for that element is completed, without waiting for completion of the design for the entire project. Its principal objective is to shorten the overall construction time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Fixed-price method (stipulated sum or lump sum method)

A

The contractor (or architect) give the owner a set price for completing the project. Contractor receives cost savings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Float Time

A

The amount of time that a construction activity can be delayed without causing the project completion to be delayed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Cash Allowance

A

An amount established in the contract documents for inclusion in the contract sum to cover the cost of prescribed items not specified in detail, with provision that variation between such amount and the finally determined cost of the prescribes items will be reflected in change orders appropriately adjusting the contract sum.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Guaranteed Maximum Cost (Guaranteed Maximum Price - GMP)

A

The amount established by agreement between owner and contractor as the maximum cost of performing specified work. Client receives cost savings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Network Diagram

A

The path in the network diagram that has the longest total required time is called the critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Percentage Agreement

A

An owner-architect agreement under which the professional fee is based upon a percentage of the construction cost of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Project Budget

A

Cost for: • Construction AND Other (15%) • Fees • Surveys • Tests • Inspections • Utility Connections • Furnishings • Equipment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Subsystems Cost Estimates

A

Estimate on a projects function units or assemblies. These prices are usually stated in dollars per square foot.

17
Q

Turnkey

A

A construction process in which one party agrees to deliver to another party a fully completed project, ready for the other party’s use and occupancy by “turning the key”

18
Q

Gantt Chart

A
19
Q

Cost Estimating: Unit Cost Method

A

Based on cost per unit or cost per sauare foot where $ amounts are based on similar bldg. type. programming and pre-design.

20
Q

Cost Estimating: Systems Method

A

Each bldg. system, such as foundation, structure, HVAC is categorized and assigned a cost. SD phase.

21
Q

Cost Estimating: Parameter Method

A

Each component of a building system is itemized by type, quality and quantity. DD and early CD phases.