02C - Concrete - Post-Tension Cables Flashcards

(32 cards)

1
Q

Reverse curvature of tendons in post-tensioned concrete construction can be avoided by _________________.

A

Providing additional support bars for the tendons (Training of Field Personnel for Unbonded Post-Tensioning Page 37)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A watertight cap should be installed on an encapsulated system for post-tensioned concrete within ______hours after stressing is complete.

A

24 hours (Training of Field Personnel for Unbonded Post-Tensioning Page 62)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Where two or more extensions of the stressing jack are required to achieve the required elongation for post-tensioned concrete, the final pull on the jack should not exceed _____________%.

A

60 (Training of Field Personnel for Unbonded Post-Tensioning Page 48)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Tendons in post-tensioned concrete should not be stressed until the concrete has reached about ________% of its full strength.

A

75 (Training of Field Personnel for Unbonded Post-Tensioning Page 8)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

A minimum clearance of _________inches should be maintained around all block outs in post-tensioned construction.

A

6 inches (Training of Field Personnel for Unbonded Post-Tensioning Page 34)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

If a tendon used in a post-tensioned concrete slab is to be stressed from both ends, at least ____ inches of tendon tail should be left outside the edge form at each end for stressing.

A

12 (Training of Field Personnel for Unbonded Post-Tensioning Page 32)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The back-stressing force applied to barrier cables should be equal to _____% of the ultimate strength of the cable.

A

80 (Training of Field Personnel for Unbonded Post-Tensioning Page 67)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Not more than _______ 0.5” diameter tendons should be banded together in a group in post-tensioned concrete.

A

5 (Training of Field Personnel for Unbonded Post-Tensioning Page 34)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the maximum that sheathing should be cut back on tendons?

A

1 inch (Training of Field Personnel for Unbonded Post-Tensioning Page 32 & 33)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Which of the below would be the best order to install post tension cables?

A

Forms set, install sleeves and embeds, cables, cable supports and install plumbing and electrical sleeves (Training of Field Personnel for Unbonded Post-Tensioning Page 30)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Which of the below would be proper way of unloading tendon coils?

A

Cradle coils by passing nylon straps through the center of coils (Training of Field Personnel for Unbonded Post-Tensioning Page 27)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the minimum spacing between bundles of tendons?

A

1 ½ inches (Training of Field Personnel for Unbonded Post-Tensioning Page 37)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the purpose for post-tensioning concrete?

A

To increase compressive strength in the bottom of a joist or girder to offset tensile stress (Training of Field Personnel for Unbonded Post-Tensioning Page 10)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Which of the below would be correct method of storing tendon coils?

A

Stored in a dry area on dunnage to keep the tendons off the ground (Training of Field Personnel for Unbonded Post-Tensioning Page 27)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

In most field applications the amount of force that will actually be applied to the strand will be approximately what percentage of the MUTS (Minimum Ultimate Tensile Strength) of the strand?

A

80% (Training of Field Personnel for Unbonded Post-Tensioning Page 46)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What a method for strengthening reinforced concrete in which steel tendons are stretched through conduits and mechanically fastened is called what?

A

Post-tensioning (Training of Field Personnel for Unbonded Post-Tensioning Page 4 )

17
Q

On concrete beams, what is the recommended distance between tendons/cables?

A

1 ½ inches (Training of Field Personnel for Unbonded Post-Tensioning Page 37)

18
Q

Which of the following is not acceptable when grouting stressing pockets?

A

Having chlorides as an additive (Training of Field Personnel for Unbonded Post-Tensioning Page 62)

19
Q

The maximum number of or .60 of an inch tendons / cables in a group is _____.

A

4 (Training of Field Personnel for Unbonded Post-Tensioning Page 34
Maximum number of .50 of an inch tendons / cables in a group is 5)

20
Q

When installing post tension cables, you are allowed to have 1 inch of the cable exposed in the concrete at the end tying into the form without plastic sheathing. What procedures are required if more than 1 inch is exposed?

A

Grease cable and tape (Training of Field Personnel for Unbonded Post-Tensioning Page 33)

21
Q

What does post tension cables have to have before concrete can be poured on them?

A

Covered in grease and plastic covering in place (Training of Field Personnel for Unbonded Post-Tensioning Page 13)

22
Q

What is the definition of a post tension cable?

A

Reinforcing steel is housed in a plastic coating or sheath that prevents the concrete from bonding with the cable so it can be stressed after the concrete has hardened. (Training of Field Personnel for Unbonded Post-Tensioning Page 13 – 15 )

23
Q

How are post tension cable / tendons installed?

A

Wrapped in plastic with PT applied (Training of Field Personnel for Unbonded Post-Tensioning Page 5 )

24
Q

When performing the final operation where two extensions of the stressing jack are used, what is the percent of the final stroke of the jack?

A

60% (Training of Field Personnel for Unbonded Post-Tensioning Page 5 )

25
What is the last step before pouring concrete on post tension cables?
Install additional support bars (Training of Field Personnel for Unbonded Post-Tensioning Page 37)
26
How many years of experience are needed to be a lead man for post tension cables?
5 years (Training of Field Personnel for Unbonded Post-Tensioning Page 29)
27
What is the minimum support bar needed for cables in a post tension beam?
4 (Training of Field Personnel for Unbonded Post-Tensioning Page 37)
28
What is the purpose for putting composite sheathing over a post tension tendon?
Cable can move more freely in concrete (Training of Field Personnel for Unbonded Post-Tensioning Page 5 Note: Composite is just plastic sheathing)
29
Concrete in which wires are tensioned on the jobsite after the concrete has been hardened by running the wires through ducts is called:
Post-Tensioned concrete (Training of Field Personnel for Unbonded Post-Tensioning Page 5)
30
What is the maximum allowed vertical deviation tolerance in post tension cables in concrete?
1 inch (Training of Field Personnel for Unbonded Post-Tensioning Page 30)
31
What is the maximum number of post tension cables allowed in a group?
5 (Training of Field Personnel for Unbonded Post-Tensioning Page 34 Note: They do not give you the size so go with 5.)
32
What is the minimum distance to the slab edge that a post tension fixed-end anchor can be installed?
1 inch (Training of Field Personnel for Unbonded Post-Tensioning Page 36)