Module 3 Flashcards

1
Q

Which of the following are purposes of Major Capability Acquisition pathway?

A

Develop Technology; produce weapons system; provide logistics support

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Documents produced by the Joint Capabilities. Integration and Development System (JCIDS) process are used to support the Major Capability Acquisition pathway milestone decisions

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Which of the following are characteristics of the Materiel Solution Analysis (MSA) phase?

A

Promising technologies are analyzed to determine which one is best suited to meet validated requirements

A Program Manager (PM} is selected and a program office is established

The Analysis of Alterative (AoA) is conducted

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The results of the Analysis of Alternative (AoA) provide the basis for which of the following?

A

Acquisition Strategy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

A successful Milestone A decision leads to entry into which phase?

A

Technology Maturation and Risk Reduction (TMRR)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The Milestone Decision Authority (MDA) must approve which of the following for a program to successfully complete Milestone A?

A

The proposed materiel solution

The Acquisition Strategy

A Product Support Strategy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When does a program enter the TMRR phase?

A

When the Analysis of Alternatives (AoA) has been completed and the MDA has approved the AS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Which of the following are goals of the Technology Maturation and Risk Reduction (TMRR) phase?

A

Reduce technology risk

Demonstrate critical technologies through prototyping

Conduct a Preliminary Design Review (PDR)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

One of the requirements for a project to exit the Technology Maturation and Risk Reduction
(TMRIR) phase is that the technology has been demonstrated in a relevant environment

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the purpose of Milestone B?

A

Initiates Engineering and Manufacturing Development phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Which of the following are key considerations of the Engineering and Manufacturing Development (EMD) phase?

A

Completes all needed hardware and software detailed design

Systematically retires any open risks

Prepares for production and deployment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Which of the following is a responsibility of the PM during the Engineering and Manufacturing
Development (EMD) phase?

A

Finalizing designs of the product support elements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Which of the following are considerations for Milestone C?’

A

Cost estimates

Environmental issues

Manpower estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Milestone Decision Authority (MDA) decisions made during the Production and Deployment phase are documented where?

A

Acquisition Decision Memorandum (ADM)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Which of the following are key considerations of low Rate Initial Production (LRIP)?

A

Establishes an initial production base for the system

Provides Initial Operational Test and Evaluation (IOT&E) test articles

Provides an efficient ramp-up to Full Rate Production (FRP)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Acquisition programs enter into Full Rate Production and Deployment after completing the Product Support Strategy

A

False

17
Q

The Operations and Support phase is based on what?·

A

An MDA approved Product Support Strategy (PSS)

18
Q

PM’s are encouraged but not required to establish organic depot maintenance capabilities

A

False

19
Q

Which of the following are Program Manager (PM) considerations during the Disposal work effort?

A

Complete reuse or recycling of system components and materials

Sale or donation to the private sector or other governments

Wasted disposal

20
Q

Which one of the following is considered a primary goal of an Acquisition Strategy?

A

Minimize the time and cost needed to satisfy validated needs

21
Q

The AS must be approved by the Milestone Decision Authority (MDA) prior to what?

A

Release of a formal solicitation

22
Q

Which item is defined as the minimum acceptable value for performance that is necessary to
satisfy an identified need?

A

Threshold

23
Q

Which of the following are considered parameters of the Acquisition Program Baseline (APB)?

A

Cost

Schedule

Performance

24
Q

Milestone A

A

initiates Technology Maturation and Risk Reduction

25
Q

Milestone B

A

initiates Engineering and Manufacturing Development

26
Q

Milestone C

A

initiates Production and Deployment

27
Q

What are the 5 phases of the Major Capability Acquisition (MCA) Pathway

A

Materiel Solution Analysis (MSA)

Technology Maturation & Risk Reduction (TMRR)

Engineering & Manufacturing Development (EMD)

Production & Deployment (P&D)

Operations & Support (O&D)

28
Q

Four Decision points of MCA pathway

A
  1. Materiel Development Decision (MDD)
  2. Capability Development Document Validation (CDD-V)
  3. Development Request for Proposal (RFP) Release Decision
  4. Full-Rate Production (FRP) Decision)
29
Q

Milestone B authorizes entry into?

A

Engineering and Manufacturing Development (EMD) phase

30
Q

When can EMD phase end

A

Design is stable

System meets validated capability requirements

Manufacturing processes are under control

Industrial production capabilities are available

System has met or exceeds all directed EMD Phase exit criteria

31
Q

The Deployment Phase of DAS begins at which milestone?

A

Milestone C

32
Q

Purpose of Milestone C is?

A

To authorize entry into:
Low-Rate Initial Production (LRIP) for MDAPs and Major Systems

Production or procurement (for systems that do not require low-rate production)

Limited deployment for Major Automated Information Systems (MAIS) or software-intensive systems with no production components