Time in Contracts Flashcards

1
Q

3 Main time Related issues

A
  1. Commencement
  2. Progress
  3. Completion
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Commencement involves

A
  • Giving possession to the contractor
  • Timing of this possession
  • Potential delays in possession
  • Possession normally not more than 6 weeks after award of contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Issues when possessing a site

A
  • Delayed possession may render employer liable to pay damages for breach of contract
  • Not with standing rights within the contract to delay works, the contract admin cannot delay whole of the works
  • If possession is delayed by aa third party ie pickets/squatter, the employer may not be liable
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Date for possession

A
  • Most contracts will give a date for posession
  • If posession is not given and contractor cannot access site, the employer may loose Liquidated and ascertained damages
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The contractor isn’t obliged to …., but must proceed …
… must be identifies in ….

A

The contractor isn’t obliged to start work on date of possession but must proceed regularly and diligently
Deferred possession must be identified in contract particulars

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Progress involves

A
  • Unless stipulated, the contractor can progress at any rate that they choose
  • Many contracts require the contractor to submit a programme of works
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Time is of the essence

A

Time and dates are a vital element of the performance of the contract. Any failure to adhere to the time stated is a breach of the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Define regularly

A

“Attend on a daily basis with sufficient labour and materials to progress the works”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Define diligently

A

“Need for contractor to apply their physical capacity industriously and efficiently”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Why is progress important to subcontractors?

A

because they depend on others progression in order to progress their own work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the meaning of completion?

A

No true completion until contract is totally performed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Who decides if a building is complete?

A

The contract Admin

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Delay in completion

A

A party can terminate the contract if the other party is late
However, if a contractor is late then they can make time is of the essence and give reasonable time for completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Sectional and partial completion

A
  • A desire for phased completion must be stated
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

The contractor is …… until issue of ….. or relevant ….

A

The contractor is allowed to keep possession of site until issue of practical completion certificate or relevant sectional

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Effects of completion

A
  • The employer takes possession of the site
  • The contractor stops insuring
  • Liability of the contractor for damages/Late completion cease
  • One half of retention is released to contractor
  • Defects correction period begins
  • Planning supervisor hands over H&S plan