DOT Standards Flashcards

1
Q

You may dispose of concrete by incorporating it in adjacent embankments as long as it is:

A

Broke into max 10” dimension
Buried at least 3 feet below finished grade
Buries at least 10 feet from the drip line of trees or highway

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Cut tree branches that extend over the roadway and hang within _____ of finished grade

A

20 feet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

In embankment areas where the grading plane is ____ feet or more above original ground

A

2 feet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Disposal from clearing and grubbing activities you must reduce combustible material to chips with a ____ inch maximum thickness.

A

1/2”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

If a dust suppressant or dust control binder is to be used, submit a dust treatment plan at least ___ days before starting job site activitie

A

15 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Any point on the completed excavation slope must be within _____ feet of the planned slope, unless the excavation is in rock, in which case, any point on the completed slope must be within ____ feet of the
planned slope

A

0.5 foot ; 2 feet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Completed slopes must be within ____ foot from the grade established by the Engineer

A

0.2 foot

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

If you perform structure backfill compaction by ponding and jetting, the thickness of the backfill layer must not exceed __ feet

A

4 feet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Bring backfill up uniformly on all sides of structures or drainage facilities. Backfill layer thickness must not exceed ____ foot before compacting.

A

0.67 foot

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Compact structure backfill to a relative compaction of at least 95% percent except you may compact
structure backfill to a relative compaction of at least 90% percent at the following locations:

A
  1. Over side drains
  2. Footings for slope protection , slope paving and aprons
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

If slurry cement backfill is used for structure backfill, you may reduce the excavation width such that the clear distance between the outside of the pipe and the side of the excavation on each side of the pipe is at least (1) ___ inches for pipes 42 inches or less in diameter or span and (2) ___ for pipes over 42 inches in diameter or span

A

6 inches for ≤ 42

12 inches for > 42

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Construct embankment in layers. The loose thickness of each layer must not exceed __ inches

A

8 inches

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The grading factor used for excavated materials for determining payment quantity for imported borrow is ___

A

1.0

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Scarify the surface of lime stabilized soil at least _______ between each layer.

A

2 inches

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Mix lime on the same day it is applied. After the initial mixing, allow a mellowing period for at least ____ hours before final mixing

A

36 hours

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Compacting lime do not use what type of compactor ? Compact the lime stabilized soil to at least __% percent relative compaction.

A

Vibratory roller ; 95%

17
Q

Compact each AS (aggregate sub-base ) layer to at least ___ percent relative compaction.

A

95%

18
Q

Where biaxial geogrid is shown, compact AS with either (1) a _______________ or (2) a ___________________. Do not use vibratory devices during compaction.

A

Smooth-wheeled roller or rubber tire roller

19
Q

Where manholes are to be lowered, remove the top portion to ___ feet below finished grade or to an authorized depth

A

3.5 feet

20
Q

Obtain authorization before disposing of surplus material or using it for any of the following:

A
  1. Widening embankments uniformly
  2. Flattening slopes
  3. Placing along the roadway or at other locations