Project Delivery Methods Flashcards

1
Q

construction manager as advisor

A

serves as an independent adviser to the owner throughout all phases of construction, consults on constructability early on, does not actually build the building
- Benefit is lower risk for owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

construction manager as agent

A

manages and administers the contracts b/w architect & contractor, hires the architect and contractor, is an expert at being on schedule and on budget
- Good for inexperienced client who doesn’t want to be super involved, low risk for owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

construction manager as constructor (cm at risk)

A

Takes place of contractor in the triangle diagram
Owner engages architect and construction manager at the same time
- Fast schedule and low risk for owner, most risky for CM
- However, inherent conflict that the CM is incentivized to drive up cost or drive down quality because that translates to higher profit for CM
- Final price (GMP) is known by end of SD
- Architect must maintain a stricter process of quality control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

traditional design bid build

A

Architect creates contract docs, contractors bid a fixed price, usually the lowest competent bidder wins
- Takes longer, costs less, less likely to be corruption in contractor selection, so almost always used in public projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

design build

A

Architects and contractor are one business entity, fewer conflicts between them, but less oversight of building quality by architects, construction cost determined before design is complete, one contract for owner
- Less risk for owner
- Quicker because no bid process
- Quality can suffer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

negotiated select team project

A

Subcategory of design/bid/build
Bring in contractor early in design process, give them a contract that guarantees the contractor a profit and covers contractor overhead
Portions of project that are difficult to fabricate can begin earlier
- Better quality, faster
- More expensive because there is no low bidder

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Cost plus fixed fee: regardless of scope of final project

A

Contractor is selected after construction documents and promised a fixed profit, regardless of building cost
- Disincentivizes contractor from allowing construction costs to balloon
- Gives lots of flexibility for change of program or issues come up on site

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

bridged design build

A

Design architect hired to create 35% of design, then the drawings are handed off to a besign build firm. More oversight than design build because the bridging consultant (design architect) is independent of design build firm
- Low risk for owner, more expensive, takes longer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

integrated project delivery

A

All 3 join together as a single entity that shares risks and profits
Share info with eachother without fear of litigation
Share benefits and risks of the project
Everyone profits if the project comes out ahead
More collaborative, more transparent, less lawsuits, less clarity on who is responsible for what, whose insurance is responsible, and who owns IP

3 types:
- Single purpose entity - creates a temporary legal agreement to create a new company, share losses and profits, high risk
- Project alliance - agreement to work together as partners and not sue eachother, less risky
- Relational contract - 3 entities form a team but they can sue eachother and owner retains authority to make the final call

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

unit cost

A

paying per housing unit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

cost plus fixed fee

A

the estimated cost of the project plus a fixed profit for the contractor
- no limit on change orders, which can net contractor additional profit
- lower risk for contractors
- project price is initially unknown

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

guaranteed maximum price (GMP)

A

like a cost plus fixed fee, but if the project is delayed or the price of materials goes up beyond a total project cost, the contractor has to complete the project and eat the extra cost
- allows contractor to give the owner a price early on in the process using design development drawings
- requires additional cost risks if the contractor uses incomplete drawings to set the price
- reserved for projects with known scope and challenges
reduces risk for owners

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

stipulated (lump) sum

A

owner pays contractor one price to build everything in the contract
- best for projects with a well defined scope of work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

time & materials

A

Contractors bill for all material costs and labor at an hourly rate.
- Helpful for projects with uncertain scope.
- tracking costs is burdensome
- increases risk for owners (unless there is a not to exceed clause)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

what would be a good contract method if the scope of work is well defined?

A

lump sum

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

what would be a good contract method if the scope of work is unclear?

A

time and materials

17
Q

what would be a good contract method if the project involves repeated materials?

A

unit price

18
Q

what would be a good contract method if the project has a fixed budget?

A

guaranteed maximum price

19
Q

what would be a good contract method if there is uncertainty in estimating?

A

cost plus fixed fee

20
Q

if the driving factor is scope

A

cost plus fixed fee
because contractor isn’t motivated to let costs balloon, they don’t profit from it

21
Q

if the driving factor is time

A

ones that skips bidding (design build or CM as constructor

22
Q

If the driving factor is quality

A

negotiated select team

23
Q

If the driving factor is cost

A

design bid build

24
Q

What method poses less legal risk?

A

Design build
two of the main parties that sue are tied to eachother

25
Q

What type of projects limit risk?

A

Any project method with a CM