Discharge Flashcards

1
Q

In what ways can a contract be discharged?

A
  • Performance
  • Expiry
  • Agreement
  • Breach; or
  • Frustration
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How is a contract discharged by expiry?

A

Will expire when it is completed according to its own terms; parties will often incorporate date when contract comes to an end, or specify the occurrence of an event (e.g. given time frame for delivery)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the entire obligations rule?

Re discharge by performance

A

A contractual obligation is discharged by complete performance of the obligation; only when performance is entirely complete is it entitled to payment

A promisor who performs only part of obligation is not discharged

Cutter - Cutter agreed to serve on a ship from Jamaica to Livepool in return from Powerll for 30 guineas (4x going rate) provided he di his duty from hence to port of Liverpool - Cutter died at sea 7 weeks into voyage and 19 days short of Liverpool - widow brought action to recover proportion of agreed price - action failed; widow entitled to nothing as Cutter did not perform entire obligation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the 4 exceptions to the entire obligations rule?

A
  • Acceptance of partial performance
  • Substantial performance
  • Divisible obligations
  • Wrongful prevention of performance
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

For acceptance of partial performance, what must the acceptance be (and what can the situation not be), and what is the defaulting party entitled to?

Re exceptions for entire obligations rule

A
  • At the innocent party’s discretion; must be a voluntary acceptance (not a ‘had no choice’ situation)
  • Party in default entitled to payment on a quantum merit basis; as much as deserved (assessed objectively)

Sumpter - Sumpter agreed to build 2 houses w stables on Hedges’ land in return for fixed price, completed half of work for approx half contract price before running out of money, meaning Hedges’ completed himself…

  • No voluntary acceptance - had no choice as he was in possession of what he could not fail to keep (on his land)
  • No voluntary acceptance means Sumpter not entitled to.a quantum meruit to compensate for value of work done - but was entitled to compensation for value of materials he had left on site which innocent party used to complete work (as innocent party had a choice here)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is substantial performance? What is the performing party entitled to here?

Re exceptions for entire obligations rule

A

Where a contract has been substantially performed it is possible for the perfroming party to obtain the contract price with a deduction to reflect the cost of remedying the ‘defect’

Defect = aspect not performed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the ‘defect’ in substantial performance? What happens if it is too serious?

A
  • Defect = the aspect which has not been performed
  • If too serious, party who rendered defective performance will not be entitled to recover any money

If not too serious - party who rendered substantive performance entitled to contract money subject to a deduction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How does the court decide what is ‘substantial performance’?

A

Question is whether the defect goes to ‘the root of the contract’; viewed with regard to purpose of contract + circumstances as a whole

Compare:

  • Hoenig: Redecoration/refurnishing job left some defects (£55 to remedy of £750 contract) = entitled to contract price - deduction for defects
  • Bolton: Central heating installation did not work = contract - to install central heating system - not substantially performed and not entitled to recover contract price (unless he had offered to remedy defects)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are divisible obligations? For what is the performing party entitled to payment?

Re exceptions for entire obligations rule

A

Where contracts are clearly intended to be divided into parts (e.g. salary under fixed contract of employment)

Performing party entitled to payment for each part performed

Depends on intention of the parties

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the wrongful prevention of performance? What is the innocent party entitled to?

Re exceptions for entire obligations rule

A

Where one party peforms part of agreed obligation but is prevented from completing rest by fault of the other party = entitled to payment despite not having completed rest of obligation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the two options of an innocent party upon wrongful prevention of performance?

A
  1. Sue for damages for breach of contract
  2. Claim a quantum meruit
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a tender of performance? What must promisor show?

Re defences to allegations of failure to perform

A

Promisor must show they unconditionally offered to perform their obligations in accordance with contract terms, but promisee refused to accept such peformance

A defence in an action for breach of contract for failing to perform obl

E.g. seller delivered goods but purchaser refused to accept delivery - seller relieved of liability for failing to deliver

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Can a tender of performance be used to discharge the payment of a debt?

A

No - but it would prevent the creditor from claiming interest/damages on debt subsequent to tender of performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How can a party discharge a contract by agreement?

2 ways

A
  1. By a subsequent binding contract between the parties (mutual waiver); or
  2. By operation of a term in the original contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What two elements are needed in a mutual waiver (subsequent binding contract) for it to be effective?

Very common in commercial situations where parties wish to end an existing contract and achieve commercial certainty. They will often agree the terms of a termination agreement to release and settle any liabilities under the original contract so that they can be sure that they will have no further liabilities or obligations arising from it in the future.

A
  1. Accord (agreement that obligation will be released) and
  2. Satisfaction (consideration for the promise to release a party from the obligation

Accord = A agrees to release B from obligations
Satisfaction = B agrees to release A from obligations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How is a mutual waiver carried out when one party has performed their obligations in their entirety but the other party still has some remaining?

There can be no satisfaction…

B cannot meaningfully agree to release A from obligations under old contract if it has already performed them!

A

The obligee may release the other party by a subsequent agreement under deed = avoids need for consideration because a gratuitous promise is enforceable if made in a contract in the form of a deed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is the alternative to using a deed for a mutual waiver?

A

Accept something different as consideration in place of the former obligation e.g. accelerated payment of a sum payable in instalments or third party paying

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What will a term providing for the discharge of obligations in a contract be?

(Moving on from discharge by subsequent contract; this is other option)

A

Will either be:

  • Condition precedent: condition which must be satisfied before any rights come into existence
  • Condition subsequent: condition which, if satisfied, releases a party from binding obligations
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

How does a condition precedent work? What happens if not fulfilled?

A
  • If a contract is subject to a condition precedent = no rights come into existence and contract suspended until condition satisfied
  • Where not fulfilled - rights and obligations were contingent on an event that never occurred (never came into existence in the first place)

E.g. company includes clause stipulating it is a condition precedent of a high value contract that approval provided by shareholders - if refuse to provide = contract never becomes binding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

How does a condition subsequent work?

A

Termination of contract/discharge from obligations occurs in the event of a specified occurrence

Common kind is a term providing the right for one or both parties to end agreement by giving notice to the other (condition transpires [notice given] and contract comes to an end)

21
Q

When does a repudiatory breach arise?

A

Where one party has breached a term of the contract which is either a condition or an innonimate term treated as a condition

NB not every breach gives party the right to terminate a contract, usual remedy will be compensatory damages

22
Q

What can an innocent party do when a repudiatory breach occurs?

A

Terminate or affirm the contract

No need for termination to be provided for in the contract

23
Q

What is an anticipatory breach?

A

Where a party indicates that they will not perform contractual obligation in advance of the date of performance

  • A party doing this has ‘renounced’ the contract
24
Q

If a party wishes to rely on an anticipatory breach to terminate, what must it demonstrate?

A

If a party wants to rely on an anticipatory breach to terminate - it must demonstrate that if breach occurred at time of performance was due it would have been repudiatory

Indication it will not perform in a minor regard does not give rise

25
Q

What is the effect of terminating a contract for repudiatory breach on..
1. Primary obligations remaining unperformed
2. The innocent’s right to claim damages
3. Any rights/obligations which have accrued before termination (e.g. if customer owes fees for services provided prior to termination)

A
  1. Puts an end to all primary obligations of parties remaining unperformed
  2. Innocent party can claim damages arising not only from specific breach but also loss of contract caused by termination
  3. Any rights/obligations which have accrued before termination remain enforceable (e.g. if customer owes fees for services provided prior to termination it would still be obliged to pay them); prospective only
26
Q

What is wrongful termination? What claim does the innocent party have?

A
  • A gives notice to terminate with B on grounds of a breach by B it believes to be a breach of condition.
  • Later transpires breach was only a warranty and A had no right to terminate
  • B now has a damages claim against A as they are actually in repudiatory breach

Unless term which has been breached has been defined as condition, the categorisation of term depends on the application of the Hong Kong Fir test (high bar!)

27
Q

In the case of wrongful termination, is it a defence that the terminator acted in good faith?

A

No - even if they believed that the ‘breach’ justified the remedial action taken

28
Q

What is the right of election? If it is exercised, what must the innocent party do?

A

Where there has been a repudiatory breach of contract, the contract is terminated only if aggrieved party makes the election (choice) to treat breach as repudiating the contract
Innocent party must make decision to terminate contract known to party in default

Innocent party allowed period of time to decide between two

29
Q

What are the benefits of affirmation

Affirm = contract survives, innocent party rights preserved

A
  • Allows innocent party to continue with major project; contractor can finish
  • Financially better: right to charge contractual charges as a debt v (uncertain) value of damages
  • Can perform own obligations and claim sum due under contract in debt action (where party indicates intention not to perform)
30
Q

If a contract is affirmed, what happens to the claim for damages? What would that claim not include?

A
  • Claim for damages arising from breach is retained but innocent party cannot terminate as a result of it
  • This means that damages would not include compensation for loss of performance/of contract as a whole

Election is not a waiver of damages from relevant breach

31
Q

How is a contract affirmed by an innocent party?

A

Must be evidence of a very clear and unequivocal commitment to continuing with contract

32
Q

What are the 2 limitations on affirming a contract in response to a repudiatory breach?

What is required? Legitimate interest…

A
  1. The cooperation of the breaching party is required for continued performance of the contract
  2. The innocent party has no ‘legitimate interest, financial or otherwise’ in affirming contract and continuing with performance (can only operate if shown that i) damages are adequate remedy and ii) keeping contract alive would be unreasonable)

Only in extreme cases will innocent party not have legitimate interest

33
Q

What is frustration?

A

Refers to events beyond control of the parties occurring after contract formation which render performance radically different from that agreed to at time contract formed

34
Q

What is the effect of frustration?

A
  • Relieves party from further obligation under contract (do not have to meet radically different obligations)
  • Contract brought to an end automatically and parties have no choice in matter

Can be raised as a defence to an action for breach of contract

35
Q

What renders performance radically different?

3 things

A
  • Performance is impossible
  • Performance is illegal; or
  • Common purpose of the contract is frustrated

Not exhaustive and may overlap

Illegal example Fibrosa - contract for sale of machinery provided it to be shipped to port in Poland which was occupied by enemy during WW2 - performing obligation would have been illegal

36
Q

What makes performance impossible?

3 things

Total/partial ______, _______ of party , _________

A
  • Total/partial destruction of the subject matter of the contract (music hall Cs were granted a licence to use) or something essential for performance of contract (contract to install machinery in factory frustrated when factory caught on fire)
  • Death/illness of one of the parties in a personal contract; especially where specified individual engaged to render a particular service (drummer in band taken ill and only capable of working 3-4 nights a week when group had engagements for 7 nights a week)
  • Unavailability e.g. ship requisitioned for 5 months out of a year’s charterparty
37
Q

Will unavailability always make performance impossible?

A

No
E.g. Tamplin: a requisition of a ship for war did not frustrate a five year charterparty as the war would be over soon and a considerable amount of charterparty would remain

The amount of time left to run in contract is only a starting point to determine frustration

NB re unavailability a ‘multifactorial approach’ to decide whether unavailability can amount to frustration: terms, content, party’s knowledge or expectaions, risk

38
Q

When is the common purpose of the contract frustrated? What happens if it can still be physically carried out?

A

When the joint (not one party’s) purpose is frustrated even when it is still physically possible to carry out contract

Not enough that it is one party’s purpose!

Krell - room hired for purpose of viewing coronation procession but no provision of this in contract - processions did not go ahead as planned - court held that purpose had been frustrated as *both parties understood only purpose of hiring rooms was to have a view of procession *

Herne - steamboat hired to D for purpose of viewing Naval Review and cruise around fleet - review cancelled but cruise could still go ahead = contract not frustrated (even if principal motivation - naval review - is) - would have been if this was sole express purpose

Canary Wharf - EMA argued lease of HQ premises had been frustrated when it was forced by Brexit to move to Amsterdam - court found no common purpose which was frustrated and parties had divergent purposes when they entered into bargain set out in lease (EMA wanted flexibility as to exit and low rent, landlord wantd secure long term cash flow opportunity) and had bargained with possibility that EMA might not fulfil full term

39
Q

What does not count as frustration?

Increase…., caused….,, could reasonably have _____ , provided for

A
  • Mere increse in expense/onerousness
  • Something caused by the default of a party
  • Something which the parties could reasonably have contemplated
  • Something provided for in the contract
40
Q

Will a contract which becomes more difficult/expensive to perform mean it has become frustrated?

Davis - 78 houses in 8 months for Council - due to lack of skilled labour, bad weather and shortages of material, work took longer and contractors incurred additional cost of £17,600 on top

A

No - an uexpected turn of events rendering a contract more onerous will not itself amount to frustration

41
Q

What is is self-frustration, how is it proved and what is the result if it is proved?

A
  • Where frustrating event was induced by one of the parties
  • For the party alleging self-induced frustration to prove that it is - if they succeed = defence of frustration fails and D in breach of contract

E.g. Super Servant Two - Ds could choose Super Servant One or Two to transport C’s oil rig, chose Two and, before performance, contracted One in another contract. Two sank and Ds could obviously not use One. This was self-induced frustration as D’s choice to allocate One to other contracts

42
Q

How do foreseeable events limit the doctrine of frustration?

A

If you could have foreseen an event, but failed to make a provision for it in your contract, frustration is less likely to apply

Flying Music Company - Greek economic crisis/civil unrest could not amount to frustration because contract was made when there wer already signs of unrest

43
Q

What is the key test for foreseeability of events in frustration? Will parties be scrutinised for every theoretical possibility?

A
  • Whether the event would have informed the manner in which the parties assessed the risk of entering into contract
  • Will be many cases where something can be foreseen as theoretical possibility, but neither party will be criticised for failing to take into account
44
Q

What express contractual provision can be used to limit frustration? What is the impact of its inclusion?

A

Frustration cannot override express provision for frustrating event, like a force majure clause: states what happens to contractual relationship should a particular set of circumstances materialise

  • Can allow for continuance of relationship in circumstances that would otherwise amount to frustration; unlikely to be able to rely on frustration where risk already provided for by force majure
45
Q

What are the consequences of frustration on future and prior obligations?

A
  • All future obligations are automatically discharged by common law
  • Obligations prior to frustrating event are dealt with by the Law Reform (Frustrated Contracts) Act 1943
46
Q

What happens to money that has been paid, money that should have been paid in the event of frustration?

A
  • Money paid before the frustrating event can be recovered
  • Money that should have been paid (i.e. that which was outstanding) before the frustrating event no longer needs to be paid
47
Q

For expenses incurred by payee (usually supplier) before frustrating event which can be recovered, what must the expenses be and what can the amount recovered not exceed?

Expenses incurred here means the costs in attempting to perform the contract. The payee will want to retain a sum of this once the contract has been frustrated; the contract cannot be completed so they are ultimately wasting their money

A
  • Expenses incurred must be directly related to attempt to perform
  • Amount retained/recovered cannot exceed i) actual expenses incurred and ii) amount paid (e.g. advance payments) or payable prior to frustrating event

Recovery of expenses at discretion of court

I think contractor can only recover 1500 (rather than 1600) because 1600 would exceed amount paid (1500) by client

Sum retained/recovered to account for expenses may not be actual expenses but only what court considers to be a just sum having regard to all circumstances

48
Q

How does a judge decide what would be just to allow a supplier to maintain? What about benefits gained by a party before frustrating event?

A
  • Broad discretion; provided it does not exceed actual expenses incurred/sums paid or payable in advance of frustrating event
49
Q

What is a ‘valuable benefit’ and what happens if a party gains one under a contract before frustrating event?

A
  • Valuable benefit = end product of the C’s services, not the services themselves
  • Party who gained a valuable benefit under contract before frustrating event may be required to pay just sum for it (where the value of the benefit has been reduced to nil by frustrating event = the provider of the ‘benefit’ has no claim)

BP v Hunt: BP provided expertise in finding and extracting oil on Hunt’s land - BP’s half stake appropriated by Libyan GOV - ‘benefit’ meant the end product of the C’s services and not the services themselves (in this case the end product was Hunt’s stake which was significantly devalued by expropriation of Libyan GOV also)