M&C: Cost Management Flashcards

1
Q

The process of monitoring the status of the project to update project budget and manage changes to the cost baseline

A

Control Costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Budgeted value of work planned to be done

A

Planned Value (PV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Budgeted value of work actually completed

A

Earned Value (EV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Actual cost of work completed

A

Actual Cost (total) (AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Total cost baseline +/- approved changes

A

Budget at Completion (BAC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Updated total cost forecast (based on progress)

A

Estimate at Completion (EAC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Expected costs remaining (now until end)

A

Estimate to Complete (ETC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Expected Variance over/under budget

A

Variance at Completion (VAC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The amount of budget deficit or surplus at a given point in time, expressed as the difference between the earned value and the actual cost

Negative (bad)
Positive (good)
Zero (on target)

A

Cost Variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

A measure of schedule performance expressed as the difference between the earned value and the planned value

Negative (bad)
Positive (good)
Zero (on target)

A

Schedule Variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

A measure of the cost efficiency of budgeted resources expressed as the ratio of EV to actual cost

Under 1 (bad)
Over 1 (good)
1 (on target)

A

Cost Performance Index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Formula for Cost Variance

A

EV - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Formula for Schedule Variance

A

EV - PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Formula for Cost Performance Index

A

EV / AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

A measure of schedule efficiency expressed as the ratio of EV to PV

Under 1 (bad)
Over 1 (good)
1 (on target)

A

Schedule Performance Index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Formula for Schedule Performance Index

A

EV / PV

17
Q
A