Discharge of Contract By Performance Flashcards

1
Q

What is discharge of contract?

A

The contract ends and parties are no longer legally binded by its terms

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the requirements for a discharge by performance?

A

Performance wasnt complete and exact

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What was held in Cutter v Powell?

A

No wages could be recovered as Cutter’s performance hadn’t been complete and exact

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a divisible contract?

A

If each obligation is separately enforceable, non-completion doesn’t constitute a breach

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What was held in Ritchie v Atkinson?

A

He only carried some of the cargo agreed:
- so was only entitled to payment for the cargo he had carried
- He was liable for damages in not carrying the whole cargo

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a substantial performance?

A

A party has done substantially what was required of them

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What was held in Daken v Lee?

A

Some aspects were poorly performed so the contract was performed substantially but not precisely

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is meant by the prevention of the full performance?

A

One party prevents the other from fulfilling the contract in its entirety so the innocent party can claim on a ‘quantum merit’ basis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is meant by ‘quantum merit’?

A

‘As much as it is worth’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is meant by acceptance of part performance?

A

There must be a specific acknowledgement and agreement without undue pressure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What was held in Sumpter v Hedges?

A

There was no entitlement to be paid as the customer had no choice but to accept part performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

When may time be a warranty rather Than a condition?

A
  • Expressly stated time is of the essence
  • Time for completion is critical
  • Failed to complete on time and new date is set which makes time of the essence
How well did you know this?
1
Not at all
2
3
4
5
Perfectly