F-1 site layout Flashcards

1
Q

if the building is a tight fit to the allowable setbacks , what should be done to help layout the building

A

hire a registered surveyor to pin the building corners

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

what does a site survey often include ?

A

taking elevations over the entire building site and digging soil test pits

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

what does fg and ng stand for

A

finished grade and natural grade

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

what does 11% grade mean

A

a slope with an a elevation change of 11 feet over 100 feet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

how are grade stakes used

A

driven into the ground along grid lines and they’re marked with amount of cut or fill needed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

what are three methods for laying out over a sloped area

A

measuring and levelling down , using trig ,

How well did you know this?
1
Not at all
2
3
4
5
Perfectly