3.6.2 EVM Data Analysis Flashcards

1
Q

What 3 variables form the basis of almost all EVM calculations?

A
  1. Budgeted Cost of Work Scheduled (BCWS)
  2. Budgeted Cost of Work Performed (BCWP)
  3. Actual Cost of Work Performed (ACWP)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the equation for Schedule Variance (SV)?

A

SV = BCWP – BCWS = EV – PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the equation for Cost Variance (CV)?

A

CV = BCWP – ACWP = EV – AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

For SV and CV, what sign (positive or negative) is favorable?

A

SV and CV: + is favorable, - is unfavorable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Schedule Variance (SV) by itself, reveals _______.

A

reveals no critical path information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is required to determine causes of cost variance and overall effect on contract cost?

A

With regard to Cost Variance:
– Further analysis is required to determine causes of cost variance and overall
effect on contract cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are 6 common indicators of problem areas or risks in Earned Value Management (EVM) Data Analysis?

A
  1. Application of management reserves
  2. Significant revisions of PMB
  3. Zero variance
  4. Sudden change in monthly performance trends
  5. Linear downward cost variance
  6. Unreasonable TCPI
How well did you know this?
1
Not at all
2
3
4
5
Perfectly