Case study - Hard Engineering - China's south-north water transfer project Flashcards

1
Q

Why does China have a water supply problem?

A

Half a China’s population and two thirds of the farmland are in the north of the country whilst 80% of its water is in the south.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How much has the water table under Beijing fallen by since the 1970’s?

A

300 meters

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What percentage of China’s rivers are polluted?

A

60%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When did China begin a huge south north water diversion project?

A

2003

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How much water can the diversion project deliver from the Yangtze River in the south to the drier north?

A

25 billion meters cubed of freshwater per year

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the projected cost of the project?

A

$100 billion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How long is the project expected to take to complete?

A

50 years

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The project involves the building of three canals that run how many kilometres across the eastern, middle and western parts of China?

A

1,300 kilometres

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How much water will be transferred each year as a result of the scheme?

A

44.8 billion cubic meters of water per year.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What percentage of the cost of the project will the central government cover?

A

50%
Local authorities will cover the rest of the cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Give some disadvantages of the project?

A
  • There is a likelihood of significant ecological and environmental impacts along the waterways
  • Resettlement issues are likely to occur
  • The Yangtze River is already severely polluted
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How many people were displaced during the construction of the central route?

A

More than 300,000 people were displaced during the construction of the central route.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly