3.3.6 Risk Management & Problem Solving Flashcards

1
Q

What is Acquisition Program Baseline (APB)?

A

Acquisition Program Baseline (APB)
– An agreement between the Program Manager (PM) and the Milestone Decision Authority (MDA) that documents the program cost, schedule, and
performance baselines

– Shall include sufficient parameters to describe cost, schedule, performance
thresholds and objectives
- APB IS NOT HOW WE HANDLE RISK, IT IS WHERE WE START FROM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What question does risk planning answer?

A

What is the program approach for addressing potential unfavorable consequences?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

In risk handling options, what is the definition of control? Examples?

A

Reduce probability/impact of occurrence to an acceptable level

Examples: Pre-planned Product Improvement (P3I), reuse software, parallel design, dual path,
test

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

In trade study fundamentals, what does the methodology provide?

A

Methodology provides rational, objective, and repeatable justification
and documented results