1st year gas theory Year Review Flashcards
(102 cards)
joints and piping less the 1/2 diameter cant be?
concealed
what are the types of copper tubing use for above and below ground for natural and propane gas lines
K G L
minimum piping to be stubbed out for ceiling, floor, wall
1”, 2”, 1”
34.5 lb/hr X 970 BTU/lb water (latent heat) =
33 475 BTU/hr/BHP
what color and name is coated on copper tubing
yellow, csst corrugated stainless steel tubing
spacing for gas pipe horizontal
5” - 8”
20 ft 6 m
how much heating value is there in 100 cubic ft of propane vapour
250 000 Btu
two main types of valves used natural gas and propane
ball valve or plug cock
1 lt of water weighs
1 kg 1000g
how many BTU required to change 1 lb of steam
970 BTU
how are High Temp water boilers rated
MBH or BHP and Comply with ASME section 1
what size is an out let on a branch off a main line before knowing what it supplies and left
same size as the run (full size)
bushing and be nested
T,F
false
atmosphere constants
14.7 psia
29.92 in HG
pressure at sea level
a flame that is lifting off the burner ports would be a result of what
poorly mixed fuel, to much air being supplied
10 000m would be ________ expressed as km
10 km
1 hot water EDR=
150 BTU/hr @ 71C (160*F)
when an appliance is not connected to an outlet of a piping system, the outlet must have
plug compatable with piping or tubing system/plugged valve/cap`
min. and max range for text gauge for gas testing
15% to 300%
Low Temp water boiler max pressure
Max 1100 kPa (160 psig)
except CI boilers- max 207 kPa (30 psig)
what must be done before concealing pipe
test must be done 15 psig for 15 mins
SI stands for
International System of Units
inches of water column for manifold piping
3 - 4” wc
min. working pressure of pipe fittings
125 psig (made to 150 psig)