Ethics and Procurement & Risk Flashcards
What was the 19th Century ethics view?
Was viewed as personal rather than professional
When was the turning point in engineering ethics?
19th/20th century series of structural failures (Ashtabula River Railroad Disaster, Tay Bridge Disaster, Quebec Bridge Collapse).
This forced engineers to produce ethical standards and confront technical & construction practice
What are the current ethical problems?
- Bribery
- Corruption
- Kickbacks
- Embezzlement
- Competition
- Offshoring
- Sustainability
- Environmental Protection
- Health & Safety
What is the purpose of the EA code of ethics?
- Code of Ethics which means membership by-laws requires the professional regulation of members
- EA has disciplinary processes that enables it to take action against members who breach the Code
What are the main components of the EA code of ethics?
- Demonstrate Integrity
- Practise Competently
- Exercise Leadership
- Promote Sustainability
What are the components of Demonstrating Integrity?
- Act on the basis of a well-informed conscience
- be honest and trustworthy
- respect the dignity of all persons
Practise Competently
- maintain and develop knowledge and skills
- represent areas of competence objectively
- act on the basis of adequate knowledge
Exercise Leadership
- uphold the reputation and trustworthiness of the practice of engineering
- support and encourage diversity
- communicate honestly and effectively, taking into account the reliance of others on engineering
Promote Sustainability
- engage responsibly with the community and other stakeholders
- practise engineering to foster the health. safety and wellbeing of the community and the environment
- balance the needs of the present with the needs of the future generations
What is a critical path?
- Longest sequence of activities in a project plan which must be completed on time for the project to complete on due date
- An activity on the critical path cannot be started until its predecessor activity is completed; if it is delayed for a day, the entire project will be delayed for a day unless the activity following the delayed activity is completed a day earlier.
What are the four main essentials of a schedule?
- a list of all activities required to complete the project
- the time that each activity will take to complete
- The dependencies between the activies
- logical end points such as milestones or deliverable items
What is Finish-to-Start (FS)?
B cannot start before A is finished
What is Finish-to-Finish (FF)?
B cannot finish before A is finished
What is Start to Start (SS)?
B cannot start before A starts
What is Start to Finish (SF)?
B cannot finish before A starts
What is procurement?
The acquisition of goods, services or works from an outside external source