3.1 Construction Issues Flashcards

(48 cards)

1
Q

What form is usually used to appoint BC

A

JCT form

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What O must BC pass down in sub-Cs - relating to practical completion

A

DLP - 12-month period in which to rectify defects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Why is Latent Defects Insurance unlikely

A

Premiums expensive

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Why is percentage of BC retained

A

For both Snagging List and Defect Liability Period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the traditional method

A

Developer engages architects + PC + BC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Why use deed for CW

A

Longer period to enforce + no need for consideration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

If C(RoTP)A is used as remedy instead of CW , check what

A

C/DoA will specify who can claim benefit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Tort as remedy - based on what + requirements

A

Negligence - need DoC + loss reasonably foreseeable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How much is the Performance Bond usually

A

Around 10% of BC sum

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the D&B method

A

Developer engages architect + BC, and then developer novates Cs to BC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Kind of contract with BC

A

Building Contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Key promise in CW as to standard of work

A

Exercise all reasonable care, diligence and skill

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Why obtain CWs

A

To give direct contractual relationship w/ those involved

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Remedies for defective works if beyond DLP

A

Turn to CW - 6 or 12 years depending on if C or D

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

In what method does developer hire employer’s agent

A

Design & build

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the relationship between CWs + DoA/BC

A

The two must be consistent w/ each other

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Who should obtain CWs

A

Purchaser/Tenant always, and employer if D&B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What member of the Professional Team must be appointed by statute

A

CDM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What Act implies certain terms into all construction Cs (w/ BC)

A

Construction Act

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What form is used to hire architect - form for DoA

A

RIBA standard form

21
Q

What might developer require from BC to ensure covenant strength

A

Performance Bond

22
Q

Two key terms implied into all construction Cs under Construction Act

A

Timing of payment and ADR

23
Q

Key statement in CW on T’s rights

A

Free licence to use designs and drawings

24
Q

Two kinds of methods for construction

A

Traditional and design & build

25
When is CW valid for 12 years
Deed
26
Who hires sub-contractors
BC
27
Three examples of members of professional team
Quantity surveyor, Employers' Agent and sub-contractors
28
What happens if delay in construction leads to late Certificate of Practical Completion - financial implications
Employer can claim liquidated and ascertained damages from BC
29
Last resort remedy for defective building works
Issues should have been caught by architect/EA, but pursuing under warranty costly + time-consuming
30
What is the DLP
12-month period where BC has O to rectify defects
31
How do you achieve forced enforcement of remedies
Side letter/supplemental deed
32
In what method is final control given to BC
Design & build
33
Kind of contract with Professional Team
DoA
34
Why might it be hard for T to rely on limited repair covenants
Issues of proving causation between disrepair + defect which is excluded
35
When does BC get paid
Once completion certified by either architect or EA
36
Why is it hard to force L to enforce remedies on behalf of T for defects
L has to prove loss to enforce - hard if lease is FR&I
37
What role does CDM have
Health & safety role to ensure compliance w/ CDM Regulations
38
Six other options for defective construction works (other than CW)
C(RoTP)A, tort, assignment/DoT, insurance, limiting repair covenants and forced enforcement of remedies
39
What loss cannot be recovered if tort as remedy
Pure economic loss
40
Remedies for defective building works if within DLP
Use second 1/2 of retained monies
41
Who certifies completion in traditional method
Architect
42
When is CW vaild for 6 years
Contract
43
What does practical completion trigger
Snagging List and DLP
44
What is the Snagging List
Minor defects to be corrected before 1st half of money retained paid to BC
45
What are liquidated and ascertained damages
Pre-agree sum as genuine pre-estimate of loss
46
Three main stages of construction
Tender & appointment, construction and practical completion
47
What percentage of BC fee is usually retained
3 - 5%
48
Key statement in CW on T's position
Deemed reliance by T on Consultant's skill, care and diligence AND T not liable to pay consultant