3.3.4 Critical Path Analysis Flashcards

(22 cards)

1
Q

critical path analysis

A

process of planning the sequence of activities in a project in order to identify the most efficient way of completing an integrated task or project, aim is to complete project in short time as possible

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

information needed for critical path analysis

A
  1. activities to complete project
  2. duration of each activity
  3. dependencies
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

features of critical path analysis

A
  1. nodes
  2. activities (events or tasks that link the nodes
  3. duration (time taken to complete activity
  4. pre requisite ( activities must be completed before next activity can start)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

nodes

A
(circle represent point in time identified by completion or start of activity) 
-split into 3, 
left half = number of node 
right half split into 2 
top segment = earliest start time (EST) 
bottom segment (shows latests finish time ) (LFT)

bottom always same as top unless simultaneous activity has a node

more than 1 path to a node = need to take highest for EST and lowest for LFT
only 1 node at beginning one at end

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

rules for critical path

A
  1. draw a node
  2. identify task with no pre requisite
  3. draw a line for each activity and connect to first node (label activity above line) (duration below lines)
  4. identify next activity with pre requisite
  5. for 2 or more prerequisites link to 1 node
  6. repeat task 3-4 until all nodes are drawn
  7. add the EST
  8. add the LFT
  9. identify critical path activities that have LFTs identical to ESTs and represent the longest path between nodes
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Earliest Start Time

A

EST for NEXT task

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Latest finish time

A

LFT for PREVIOUS task

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Calculating EST

A

first node EST = 0
EST calculated from left to right
add duration of activity to EST of previous node
more than 1 activity leads to a node highest figure = new EST

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Calculating LFT

A

give last node of project an LFT = to the EST
work backwards from left to right
subtract duration of activity from LFT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

critical path

A

tasks that cant be delayed without delaying whole project (longest path)
if on critical path LFT =EST

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

float

A

duration of an activity can be extended or postponed so that the project still finishes within minimum time

LFT - activity duration - EST

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

identifying critical path

A

activities with a float of 0 cant be delayed without delaying entire project
such activities represent “critical path”
on critical path activities have equal EST and LFT

float = o days activity must be completed on time or whole project will be delayed therefore critical activity

identifying all critical activities firm can see which activities must be finished on time = critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

identifying critical path

A

activities with a float of 0 cant be delayed without delaying entire project
such activities represent “critical path”
on critical path activities have equal EST and LFT

float = o days activity must be completed on time or whole project will be delayed therefore critical activity

identifying all critical activities firm can see which activities must be finished on time = critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

for/adv of critical path analysis:

A

allow business to meet deadlines (especially for time sensitive projects)
some projects expensive and complex CPA = minimise risk of missing deadlines/overspending
allow business to plan resources and plan contingencies (JIT/Lean)
understand critical tasks and which cant be delayed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

against/dis of critical path analysis

A

unforeseen incidents = delays despite CPA (unexpected events)
time consuming
less necessary with experienced company in delivering similar projects (or 1 big project is just a series of small projects)
too much focus on deadline = not enough on quality
only as good as data put into it

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

business implication of CPA

A
  1. efficiency benefits
  2. business decision making benefits
  3. time based management benefits
  4. working capital benefits
17
Q

efficiency benefits of CPA

A

increase efficiency = decrease time taken to complete project = reduce costs
business knows when activity due to take place
control and review (monitor progress against original plan)

18
Q

business decision making benefits of CPA

A

managers involved in planning and decrease risk of delays/other problems
detailed info to customers = improve relationships
used to change allocation of resources or order of events

19
Q

time based management benefits

A

estimate minimum time to complete project identify activities that cant be delayed
resources allocated at appropriate time
activities carried out simultaneously

20
Q

working capital benefits of CPA

A

organisation plan when needs particular resources

know when stock needed and therefore hold lower stock levels

21
Q

problems with CPA

A

can be fixed and some managers = dont want to move from fixed sequencing
complex activities = difficult to represent accurately on network
project has to be managed and monitored all the way through and not just at the end
if done too quick = reduction in quality

22
Q

evaluation of CPA

A

planning and project management tool
helps ensure project is completed as quick as possible, resources used efficiently but it does depend on accuracy of the information used
just drawing a CPA doesnt ensure project runs to plan, most project encounters delays/unexpected = managers need CPA to monitor project and take swift action to rectify problems