3.5.4 Acquisition Logistics Flashcards

1
Q

Opportunity for Life-Cycle Cost Savings falls away before ____.

A

Preliminary Design Review (PDR) and Critical Design Review (CDR)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What (when and why) is Product Support Analysis (PSA) or supportability analysis?

A

 What: is a body of procedures and methods used to define system performance and supportability goals
– Failure Mode, Effects and Criticality Analysis (FMECA), Fault Tree Analysis (FTA), Reliability Centered Maintenance (RCM) Analysis, Level of Repair Analysis (LORA), Maintenance Task Analysis (MTA)

 When: Supportability analysis is conducted as part of the Systems Engineering process

 Why: Supportability analysis ensures supportability is included as a system
performance requirement, and the system is concurrently developed with the support system and infrastructure in order to optimize readiness and LCC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

 The DoD has made it a requirement that contract specifications (including
system design) contain reliability and maintainability as performance parameters
 Failure to satisfy those parameters will ____:

A

– Increase ownership costs
– Reduce RAM supportability metrics
– Decrease overall readiness of the system

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is an essential characteristic of supply support?

A

Establish Allowance Parts Lists
(APL) and Coordinated Shipboard Allowance List (COSAL)