4506 Flashcards
What causes 12-RRV-285, radioactive liquid waste disposal effluent hdr to Circ Water Discharge Tunnel Shutoff Valve, to close?
Loss of Air
High radiation from RRS-1000 or failure
What are the interlocks on 2-RRV-286 and 1-RRV-287, Liquid waste to Circ Water Disch Tunnel Shutoff valve?
Won’t open unless at least one Circ Water Pump is in operation from their respective unit. Will trip closed if loss of all CW Pumps in that unit.
Where does the AOM take samples from? And what happens on a high O2 alarm?
Samples discharge of WGC Moisture Separator.
On high oxygen, swaps to standby GDT
Where does the AGA sample from? And, what is it monitoring for?
Samples GDTs and CVCS HUTs for high oxygen and Hydrogen
What are the miscellaneous header loads for the NESW system?
Glycol Chiller Condensers**
Ice Bin Cooling Loop Condensers
TRS Neutralization reign header
Fluidized Chiller Condenser and Air Precooler
Chem Cleaning Mixing Station
MUP Retention Tank and Degassifier Vac Pump
What are the NESW Pump Power supplies?
11B (21B)
11C (21C)
What are the auto starts of the NESW Pumps, including what the switch position may be?
Loadshed - Neutral and Auto
SI - Neutral and Auto
Low Pressure off 55 (60) pasig - Auto Only
What does 12-RRV-305, waste gas to aux building vents pressure reg valve do and why?
Maintains constant pressure on RRV-306 (set to 5 psig) so we have a known flow rate to determine our release
What will cause RRV-306 to close?
High Rad signal on 1505/1525 or 2505 / 2525
No Unit 1 AX Fans running
What ventilation is required for RRV-306 to be open?
Either unit 1 aux exhaust fan must be running (will cause trip)
Cross-tie damper will be closed when releasing
What could be the cause of an automatic swap to the standby GDT?
I/S tank reaches 100 psig
Hi Hi Oxygen from the AOM
***Standby tank must be selected
How do we ensure a continuous path to at least one waste HUT?
CWHUT and DWHUT valves are interlocked to make sure BOTH valves cannot be closed at the same time.
What are the Unit 1 Reactor Trips associated with Low Steam Generator Levels?
Low Low Level at 5% 2/3 on 1/4 SGs
Low Level at 15% 1/2 on 1/4 SGs with FF < SF at 0.71E6 lb/hr 1/2 on same SG
What are the U2 Reactor Trips associated with Steam Generator Level?
Low Low Level at 22% 2/3 on 1/4 SGs
Low Level at 26% 1/2 on 1/4 SGs with FF < SF at 1.47E6 lb/hr 1/2 on same SG
What are the NESW Pump Suction sources, listed in the preferred order?
Circ Water Suction (same unit, then opp unit)
Discharge Tunnels (same unit, then opp unit)
What happens to the NESW system on a loadshed when there is a SI Signal but no CTS Signal? (Load Cons)
The Loadshed Maximizes flow to CAC and CLVs
LO Cooler WMOs close
CUVs, CIRs, and MACs close, NOT CLVs
Unit Xtie to Misc HDR closes
What happens with CTS and Load Shed (Load Con)
Trips the train specific NESW Pump to prevent EDG Overload
What are the interlocks for letdown isolation valves QRV-111/112?
Close on PRZ Level at 17%
Will NOT open if any orifice isolation valve is open
Fail Close
What are the interlocks on the Letdown Orifices?
Close when either LD Isolation is closed
Close on Loss of both CCPs
Close at PRZ Level of 17%
Close on Phase A
Fail closed
What is the purpose of the LD Pressure Control valve QRV-301?
Maintains DP across orifice to prevent flashing.
At what temperature does QRV-302 bypass flow around the Demins?
143 degrees
What is the minimum VCT pressure at power operations and why?
15 psig during RCP Ops for RCP Seal #2 flow (back pressure)
What is the maximum VCT pressure at power operations and why?
37 psig to ensure adequate Emergency Boration Flow
Explain how the CCP Recirc Valves work on a SI.
Close on SI. 2 second delay, then maintain 1812 - 1825#