River Landscapes Flashcards

1
Q

What is the name of the town in which embankments were constructed?

A

Banbury

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What date did the flood management scheme in Banbury begin?

A

2012

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How long was the earth embankment in Banbury?

A

2.9km

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What motorway was the embankment built paralell to?

A

M40

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What social impacts did the flood management at Banbury have?

A
  • Reduced anxiety
  • improved quality of life for people
  • A361 will open during a flood to minimise road disruption
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What economic impacts did the flood management at Banbury have?

A
  • Cost £18.5 million
  • Money was given from the environment agency
  • The embankment protects 441 houses and 73 businesses, this will save £100 million in savings
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What environmental impacts did the flood management at Banbury have?

A
  • 100,000 tonnes of earth taken from nearby creating a reservoir
  • creation of new habitats
  • part of the floodplain will be allowed to flood during high river levels
How well did you know this?
1
Not at all
2
3
4
5
Perfectly