CH. 9 Flashcards

1
Q

This is the technique used by some contractors to determine the estimate value of work completed to date compared with actual cost of work complete.

A

Earned value (EV) or Earned Value Management (EVM.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the most effective use of earned value to a GC’s jobsite financial team?

A

The most effective use of earned value to a general contractor’s jobsite financial team is to track direct labor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

If calculating material quantity through the EV method, what is the % complete of the total window estimate if a sub installed 150 windows out of 200?

A

150/200 or 75% of the total window estimate has been earned, regardless of how much was spent on those 150 windows.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What can the EV curve tell us in regards to budget and schedule?

A
  • Are we right on budget, over budget, or under budget, and by how many hours?
  • Are he right on schedule, ahead of schedule, or behind schedule and by how many days?
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How is the schedule status determined?

A

Time scheduled for the work that had been performed -

actual time used to perform work = schedule status

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How is the cost status determined?

A

Earned value of work performed - actual cost of work performed = cost status

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How to determine EV curve?

A

Total number of man hours estimated X cumulative % completed = EV.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is ACWP?

A

actual cost of work performed. Plots actual point of hours or dollars when incurred, regardless of estimate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is BCAC?

A

Budgeted cost at completion. This reflects total value of work package @ end of schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is BCWP?

A

Budgeted cost of work performed. This plots the earned value of work performed when it was performed, regardless of actual cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is BCWS?

A

Budgeted cost of work performed. This is the estimated curve which reflects original estimate in hours or dollars and when the work was originally scheduled to have been completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

CPI: Cost performance index =

A

BCWP/ACWP, < 1 = under budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

CV: Cost variance =

A

BCWP-ACWP, < 1 = within budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

SPI: Schedule performance index =

A

BCWP/BCWS, < 1 = ahead of schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

SV: Schedule variance =

A

BCWP - BCWS, < than 1 = ahead of schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly