Integration Flashcards

1
Q

An intentional activity that realigns the performance of the project work with the project management plan is called:

a. Defect repair
b. Preventive action
c. Corrective action
d. A change order

A

C. By definition, anything done to bring expected future project performance back in line with the baseline plan is called corrective action.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which of these processes is not part of Project Integration Management?

a. Develop project management plan
b. Monitor and control project work
c. Control resources
d. Close project or phase

A

C. Control resources is not a process in project integration management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A predetermined value of a measurable project variable that represents a limit that requires action to be taken if it is reached is called:

a. Threshold
b. Tolerance
c. Not to exceed
d. Performance measurement

A

A. By definition, a threshold is a value of a measurable project variable that represents a limit that requires action to be taken if it is reached.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Coordinating, unifying, and consolidating are associated with which of the nine knowledge areas?

a. Scope management
b. Risk management
c. Integration management
d. Communications management

A

The best answer choice is C because integration management comprises coordinating, unifying, and consolidating activities of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The project that Walter has been managing is coming to an end. He is in the closing activities. Prior to finalizing the Close Project process, he needs to verify that the project has achieved the project scope. To which of the following documents must he refer in order to determine this?

a. Work Breakdown Structure
b. Earned Value measurement
c. Stakeholder register
d. Project management plan

A

The best answer choice is option D because the project management plan contains the Scope Management plan and the scope baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

All of the following choices are inputs to the Develop Project Management Plan process except:

a. Project charter
b. Enterprise environmental factors
c. Project scope statement
d. Outputs from other processes

A

The best answer choice is C because the project scope statement is not an input to the Develop Project Management Plan process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

An intentional activity that ensures the future performance of the project work is aligned with the project management plan is known as

a. Defect repair
b. Preventive action
c. Corrective action
d. A change order

A

B. Preventive action is an intentional activity that ensures the future performance of the project work is aligned with the project management plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The document that enables the project manager to move forward with the project by enabling them to apply organizational resources is called:

a. The Statement of Work (SOW)
b. The business case
c. The communications plan
d. The project charter

A

D. By definition, the charter is a document that has been issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Your product, as currently configured, will not be accepted unless some minor changes are made. Your project team has delivered the results of those changes and verified that the product will now be acceptable to the stakeholders. This is an example of which process group?

a. Monitoring and Controlling
b. Planning
c. Initiating
d. Executing

A

A. The best answer choice is A because this question concerns monitoring and controlling the result of the executing process and initiating changes when necessary to meet the product requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Clyde is working for an audio systems manufacturer as the project manager of a new project to develop a high-quality audio monitoring system. Since the product of this project may be used by government surveillance agencies, the quality is critical. Clyde is in the process of using quality standards from the organization’s quality policy to develop the project charter. Which of the following best describes what Clyde is doing?

a. Using organizational process assets to develop the project charter
b. Using the Statement of Work to develop the project management plan
c. Using enterprise environmental factors to develop the charter
d. Using industry standards to develop the charter

A

The best answer choice is A. Clyde is using the existing organizational process assets to develop a new charter for the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Accurate and timely information is critical in a project environment. Which of the following process groups helps to assure that all information is accurate and timely?

a. Planning
b. Closing
c. Monitoring and Controlling
d. Initiating

A

The best answer choice is C. The processes in the Monitoring and Controlling process group help to monitor all project information to assure that it is accurate and timely.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

navigate. You are managing a project tasked with manufacturing a new consumer grade commuter airplane that has just been approved by the FAA. Production of the airframe is scheduled to begin the following week, but your lead assembly supervisor has just informed you that some specific fastening components for the fuselage are not going to be delivered on time. You decide to change the schedule and direct your team to work on the subassemblies for the navigation system. This is an example of which of the following?
a. Fast tracking
b. Crashing the schedule
c. Corrective action
d. Preventive action

A

The best answer choice is D because the project manager is taking preventive action to address the change in schedule tasks and in order to keep the project on schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Which of the following should be included in the project charter?

a. All supporting documentation
b. Risk register
c. The specific business need the project is designed to address
d. Stakeholder register

A

The best answer choice is C because the project charter is the document that initiates the project and describes the specific business need that the project is designed to address.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

navigate. Stephanie is a YouTube v-logger. Her husband, Dave, works for photographic equipment manufacturer. Because of the advent of new technology and a unique wireless geo-location system, Dave has just developed a new video camera that has an input for a secondary camera lens, which allows Stephanie to videotape herself from two different points of view at the same time. Her YouTube subscribers, some of which are also v-loggers, have seen Stephanie’s review of the product on her YouTube channel and have started calling Stephanie and asking where they can buy one of these new cameras. Dave’s company decides to meet with some of the v-loggers to under stand their wants and needs for a new product line around the two-lens concept. Dave documents the initial assumptions and reviews previous lessons learned from a similar new product line before pitching the idea to the Project Selection Committee. This example illustrates the concept of
a. Market advance
b. Project feasibility assessment
c. Business need
d. Technology advance

A

The best answer choice is B because the scenario illustrates meeting with stakeholders and evaluating assumptions and lessons learned to evaluate the feasibility of a new project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

navigate. Darla’s project is coming to the end of a specific phase. She has scheduled a phase-end meeting with her team in order to get the required sign-offs on specific deliverables. This particular phase end is a natural time to evaluate the team’s performance in the phase that is ending. Darla is sending a communication to her team members regarding this meeting. Which of the following is the correct nomenclature for a meeting of this type?
a. Phase exit
b. Monitoring gate
c. Kill gate
d. Milestone review

A

The best answer choice is A. Typical terms include phase gate, kill point, and stage gate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

A written document that records the status and resolution of current situations that could have an impact on project objectives is a(n)

a. Communications plan
b. Issue log
c. Issue record
d. Work performance report

A

B. An issue is a current condition or situation that may have an impact on the project objectives. An issue log is used to document and monitor the resolution of issues.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

From the following documents, select the one that formally authorizes the project.

a. Business case
b. Statement of Work
c. WBS
d. Project charter

A

The best answer choice is D because the project charter is the document that formally authorizes and initiates the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Which of the following is not a subsidiary plan that is typically included in the project management plan?

a. Cost management plan
b. Scope Management plan
c. Performance improvement plan
d. Communications Management plan

A

The best answer choice is C because any performance improvement plan is not a subsidiary plan and is not included as part of the project management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

The overall focus of integrated change control is to

a. Maintain the integrity of performance baselines
b. Manage approved changes
c. Coordinate changes across the knowledge areas
d. All of the answer choices are correct

A

D. The overall focus of integrated change control is to
review all change requests
manage changes to deliverables, project documents, and the project management plan
communicate decisions
consider changes in an integrated manner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Variances that are within the ______ are considered acceptable.

a. Baseline
b. Threshold
c. Boundaries
d. 10% range

A

B. Variances within the threshold are acceptable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

At the end of a project when project documentation is being archived, which stakeholder is typically still working on the project?

a. The project team members
b. The project manager
c. The client and/or the client’s legal team
d. All stakeholders on the project

A

B. Archiving documentation is usually the last function prior to formally closing the project. The project manager is often the only remaining stakeholder actively working on the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

One of your project team members has indicated that she will need an additional four days to complete an activity assigned to her. She assures you that this delay will have zero impact on the project cost. As an experienced project manager what should you do?

a. Approve the request.
b. Ask your team to look for any impact in other areas.
c. Assign more resources to the activity.
d. Deny the request

A

The best answer choice is B. Although your team has indicated the anticipated delay will have zero impact on the project cost, you need to determine whether the delay will have any impact on other areas such as schedule, quality, and scope. In this case, an impact analysis should be done by your project team.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Reducing the project budget by 10% is considered what?

a. A product change
b. A quality change
c. A project change
d. A necessary requirement

A

C. Reducing the project budget is considered a project change. Because of balancing competing demands, it’s necessary to consider the impact a budget reduction will have on the scope, schedule, and quality constraints on a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

One of your team members at the software development company you work for has created a new coding process that results in decreasing development time by an average of 30%. You record this development in order to

a. Help the team member receive recognition
b. Make this information available for future projects
c. Motivate the other team members to be more creative
d. Document it as an exception to standard procedure

A

The best answer choice is B because this scenario specifically involves documenting lessons learned that may be valuable for future projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled is called a

a. Configuration management system
b. Project management plan
c. Change control system
d. Subsidiary plan

A

C. A change control system is a set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Reducing the budget by 3% is considered a

a. Project change
b. Product change
c. Project management plan change
d. Project document change

A

A. Reducing the budget is a project change. You have to change the project management plan, but the change to the project is the driver, not the plan itself.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Your company was awarded a contract to evaluate the environmental impact of a new but unproven technological advance in wind farming. When developing the project charter, to what documentation should a project manager pay special attention?

a. Requirements
b. The awarded contract
c. The business case
d. A stakeholder analysis

A

B. Because the contract was awarded following a bidding process, there will be contractual obligations that need to be fulfilled as outlined within the contract. These need to be reflected in the project charter that is being created.

28
Q

By definition, any unique and verifiable product, result, or capability to perform a service that is required to be produced to complete a process, phase, or project is called:

a. Product
b. Service
c. Artifact
d. Deliverable

A

D. By definition, a deliverable is any unique and verifiable product, result, or capability to perform a service that is required to be produced to complete a process, phase, or project.

29
Q

The PMBOK Guide defines a project as having two specific characteristics. Which of the following comprise those characteristics?

a. Beginning and phased
b. Temporary and unique
c. Sponsor and client
d. Costly and time consuming

A

The best answer choice is B. The PMBOK Guide defines a project as a temporary undertaking designed to create a specific product, service, or result

30
Q

What type of knowledge can be codified using symbols such as words, numbers, and pictures?

a. Implicit knowledge
b. Tacit knowledge
c. Explicit knowledge
d. Informational knowledge

A

Explicit knowledge can be codified using symbols such as words, numbers, and pictures

31
Q

Which of the following documents would include the project objectives, identified risks, and approval requirements?

a. Strategic plan
b. Project charter
c. WBS dictionary
d. Scope statement

A

The best answer choice is B because the project charter contains the items described.

32
Q

You are the project manager on a project that exists in a matrix organizational structure. One of your team members is a director with the company and is consistently late with project deliverables. You have tried to schedule a meeting with her by leaving voice mails and sending e-mails, but she will not respond to your messages. The project is beginning to fall behind schedule because of her failure to meet deadlines, and you realize it is time to escalate the issue in order to keep the project on track. Of the choices below, which is the proper person to contact?

a. Her supervisor
b. The customer
c. Your sponsor
d. The CEO of the company

A

C. The best answer choice is C because your sponsor is the next level of authority on the project.

33
Q

navigate. Hank has been assigned as the project manager for an industrial waste disposal system construction project. During the development of the charter, the project budget initially designated for this project was estimated at $10 million. Recently, organizational cuts have resulted in decreased funding for this project and a reduced scope. If the sponsor reduces the project budget to $5 million just before the planning phase begins, what should Hank do?
a. Document the new budget as a constraint
b. Revise the project charter
c. Meet with the stakeholders to get their opinions
d. Update the summary budget in the charter

A

The best answer choice is B. If the funding is decreased and the scope reduced, the number of stakeholders, milestones, and other aspects of the project will change. Because the planning processes have not started yet, it is better to revise the project charter with the new project objectives, budget, and scope. Hank must also identify any new stakeholders and eliminate any stakeholders that are no longer involved based on the new project scope.

34
Q

navigate. David has recently inherited a project that is having significant difficulties and running behind schedule because of poor estimates for the activity durations. The project team had missed numerous deadlines, and customers are unhappy with the progress on the project. David has been analyzing the leads and lags in the schedule in an attempt to bring activities into alignment with the project plan without impacting the cost baseline. He has determined that he can schedule some of the activities in parallel rather than sequentially with no adverse effect on the project costs. Of the following choices, which describes David’s action?
a. Crashing
b. Fast-tracking
c. Re-baselining
d. Lessons learned

A

The best answer choice is B. David is involved in a schedule compression technique known as fast-tracking. Crashing is also a schedule compression technique, but it typically results in increased cost.

35
Q

Writing a performance assessment on a lead project resource is part of which closing activity?

a. Archiving financial information
b. Conducting a lessons learned/post-project audit
c. Releasing project resources
d. Acceptance of scope and project deliverables

A

C. One part of releasing project resources is to provide feedback to team members in the interest of their professional development

36
Q

You have just started working as a project manager for a guitar amplifier manufacturing company. Although your organization has been manufacturing amplification equipment for some time, the need for this project is due to industry changes and technological advances made in audio transcoding systems. You are in the process of creating the project charter for this project, and it’s necessary to create a Statement of Work in order to completely describe the end product. In order to create this Statement of Work, which of the following will you need to include?

a. Product scope description
b. Business need
c. Strategic plan
d. All of the above

A

The best answer choice is D because all of the items listed are referenced in the Statement of Work.

37
Q

From the list of choices below, select the process that is considered to be the most dependent on the type and nature of the work being performed and the process in which the project deliverables are created.

a. Control Scope
b. Collect Requirements
c. Monitor and Control Project Work
d. Direct and Manage Project Work

A

The best answer choice is D. Because the output of the Direct and Manage Project Work process are the deliverables, it is this process that is most dependent on the type and nature of the work being performed and process in which the deliverables are created.

38
Q

The overall project performance measurement baseline typically includes

a. Cost baseline, schedule baseline, quality baseline
b. Scope baseline, configuration baseline, cost baseline
c. Schedule baseline, scope baseline, quality baseline
d. Cost baseline, scope baseline, schedule baseline

A

D. There is no such thing as a quality baseline or configuration baseline.

39
Q

navigate. Which of the following best defines the formal closing of a project or phase?
a. The comparison of the financial results against the plan to determine the project’s overall profitability using real project data
b. The informal review of the project after the project’s final deliverable has been given to the client.
c. The process of finalizing all activities for the project, phase, or contract.
d. The published documentation of how project events were addressed, or should be addressed, on future subsequent projects.

A

C. Close Project or Phase is the process of finalizing all activities for the project, phase, or contract.

40
Q

Which of the following is used to provide a comparison between the actual work performed and the schedule baseline?

a. Quantitative analysis
b. Qualitative analysis
c. Performance reviews
d. Work Breakdown Structure

A

The best answer choice is C. Performance reviews are used as a comparison tool to evaluate the work performed as it relates to the schedule baseline

41
Q

When considering completing the final lessons learned document, which information should NOT be considered?

a. Techniques used for team building
b. Risk analysis that was performed as part of planning the project
c. Which team members were given performance bonuses
d. Methods used for requirements gathering

A

C. Information regarding team member performance, bonuses, or feedback is not appropriate for lessons learned documentation

42
Q

An artifact that is produced, is quantifiable, and can be either an end item in itself or a component item is a(n)

a. Deliverable
b. Product
c. Result
d. Artifact

A

B. An artifact that is produced, is quantifiable, and can be either an end item in itself or a component item is a product

43
Q

Which of the following is NOT a component of the project management plan?

a. Change management plan
b. Communications Management plan
c. Cost baseline
d. Requirements Traceability Matrix

A

The Requirements Traceability Matrix is a project document.

44
Q

navigate. Which knowledge area defines the “processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the project management process groups?”
a. Project Integration Management
b. Project Scope Management
c. Project Quality Management
d. Project Procurement Management

A

A. In the project management context, Integration Management includes characteristics of unification, consolidation, communication, and interrelationships. These actions should be applied from the start of the project through completion

45
Q

navigate. What document is sometimes referred to as the initiation document, project description document, or project authorization document?
a. The integration management plan
b. The project charter
c. Integrated change control
d. Project SOW

A

B. Different organizations have different terms for their project charter document.

46
Q

What project document is often a key repository of information that is used to capture explicit knowledge that can be shared on the existing project and on other projects?

a. Risk register
b. Lessons learned register
c. Project charter
d. Stakeholder register

A

B. The lessons learned register is often a key repository of information that is used to capture explicit knowledge that can be shared on the existing project and on other projects

47
Q

During a project kick-off meeting for getting stakeholder approval for the project charter on a software development project, one of the key stakeholders suggests moving the project end date. What should you do next after the kick-off meeting is concluded?

a. Schedule a meeting with the stakeholder to understand his position
b. Meet with all stakeholders to get their approval
c. Ignore the request
d. Move the project end date as suggested

A

A. The best answer choice is A because the project charter needs to be approved by all stakeholders prior to moving into the planning phase. Since ignoring this key stakeholder’s request could result in project failure, gaining a better understanding of the argument is critical to making the right decision.

48
Q

Completion of the project is measured against the

a. Project scope statement
b. Requirements documentation
c. Project management plan
d. Scope baseline

A

C. Project completion is measured against the project management plan.

49
Q

A quantifiable deviation, departure, or divergence away from a known baseline or expected value is called:

a. A variance
b. A gap
c. A lag
d. A float

A

A. By definition, a variance is any quantifiable deviation, departure, or divergence away from a known baseline or expected value. It is often preceded by a modifier, such as cost or schedule.

50
Q

Which term is defined as the processes and activities needed to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management process groups?

a. Project Plan Development
b. Project Plan Execution
c. Integrated Change Control
d. Project Integration Management

A

D. Project Integration Management includes the processes and activities needed to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management process groups.

51
Q

navigate. Identifying, approving, or rejecting modifications to documents deliverables, or baselines associated with the project are identified, approved, or rejected is called:
a. Change Control
b. Configuration Management
c. Project Management Plan
d. Subsidiary Plan Component

A

A. By definition, Change Control is a process whereby modifications to documents, deliverables or baselines associated with the project are identified, documented, approved or rejected

52
Q

The project purpose, summary milestones, and project manager (PM) authority are described in which document?

a. Statement of Work (SOW)
b. Stakeholder analysis
c. Business case
d. The project charter

A

D. All these items are documented in the charter. The business case may provide relevant charter pulls it together and documents it in one place.

53
Q

Examples of monitoring include all of the following EXCEPT:

a. Collecting project performance data
b. Defect repair
c. Performance measures
d. Reporting and disseminating performance information

A

B. Defect repair is an intentional activity used to modify a nonconforming product or component, often associated with quality management activities.

54
Q

Your company has won a bid to conduct research on the impact of CO2 in a remote part of the Northwest Territories. What document should you pay particular attention to as you develop the charter?

a. Requirements documentation
b. Business case
c. Agreement
d. Stakeholder analysis

A

C. Because this project was won in a bidding situation, there will be contractual obligations that are outlined in the agreement. These need to be reflected in the project charter.

55
Q

As your project team executes the activities required for the work packages listed in the WBS, they have been reviewing information from previous projects to determine best practices for completing the activities necessary to complete the work. This information is found in which of the following?

a. Communication Management plan
b. Enterprise environmental factors
c. Project charter
d. Lessons learned

A

The best answer choice is D because the lessons learned database contains details from previous projects and can be a valuable resource in completing new projects.

56
Q

Which of the following is a component of the project charter document?

a. Work Breakdown Structure (WBS)
b. Network document
c. Quality management plan
d. Project exit criteria

A

The project charter often contains the conditions needed to close the project or phase.

57
Q

In which of the following situations would it be appropriate to change a project baseline?

a. When the integrated change control board approves a change request
b. When the project management plan changes
c. When the project life cycles enters a new phase
d. At no time prior to the completion of the project

A

The best answer choice is A because project baselines are only changed when the integrated change control board approves a change request

58
Q

From the following documents, select the one that formally authorizes the project.

a. Business case
b. Statement of Work
c. WBS
d. Project charter

A

The best answer choice is D because the project charter is the document that formally authorizes and initiates the project allowing the project manager to apply organizational resources.

59
Q

navigate. Richard is managing a project for a major client. The project sponsor has just informed Richard that the client is terminating their contract for convenience. Which of the following should Richard do now?
a. Control procurements
b. Create a change request
c. Close the project or phase
d. Perform qualitative risk analysis

A

The best answer choice is C. Because the client is canceling the contract, it means there is no justification for the project to continue. Richard needs to close the project.

60
Q

Charlie has advised a client that although half the work of a project is complete, less than half the budget has been spent at this point. What has Charlie just provided to the client?

a. Schedule forecast
b. Corrective action
c. Preventive action
d. Status report

A

D. A status report describes the overall state of the project at any point during the project

61
Q

Which information is NOT relevant for a lessons learned document?

a. Which team members received bonuses
b. Methods to improve requirements gathering
c. An effective technique for team building
d. A risk response that worked well

A

A. Information on team member performance, bonuses, or feedback is not part of the lessons learned document.

62
Q

According to the PMBOK® Guide, a document where information about issues is recorded and monitored is called:

a. An issue log
b. An issue record
c. An action log
d. A work performance report

A

A. An issue log is used to document and monitor the resolution of issues

63
Q

During the Close Project or Phase process, which of the following is the project scope measured against?

a. Quality Management plan
b. Earned Value
c. Project management plan
d. Schedule Variance

A

C. The best answer choice is C because, of the choices listed, only the project management plan is an input to this process

64
Q

An example of a monitoring task is

a. Collecting project performance data
b. Monitoring implementation of changes
c. Developing preventive action plans
d. Submitting change requests

A

A. To monitor is to collect project performance data, produce performance measures, and report and disseminate performance information

65
Q

Completion of a project scope is best measured against which of the following project documents?

a. The scope baseline
b. The project management plan
c. The project scope statement
d. Requirements documentation

A

B. Final project completion is always measured against the project management plan.