Objective 04: Preparing a Schedule Flashcards

1
Q

What is the purpose of scheduling?

A

To accomplish a set of tasks in the most efficient manner within existing constraints in order to meet certain objectives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why do tasks have to be organized in a logical and time-efficient manner?

A

They are normally dependent on each other in some way

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the detailed steps to scheduling?

A
  1. Identify all required tasks
  2. Estimate the duration of each task
  3. Identify required resources
  4. Organize tasks into a logical order and determine dependencies between tasks
  5. Apply resource and other constraints
  6. Review the critical path and adjust resources as needed to meet planned deadlines
  7. Estimate final cost and shutdown duration
  8. Make tradeoffs as needed
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the first step in scheduling?

A

To fill in the task description and estimate the duration of the task

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Early Start

A

The earliest time that the task can be started, which may depend on the timing of the related tasks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Early Finish

A

The earliest time that the task can be completed, which is determined by adding the early start time to the duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Late Finish

A

The latest time that the task can be completed without impacting overall completion time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Late Start

A

The latest time that the task can be started without delaying the overall completion time, which is calculated by subtracting the duration from the late finish time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Slack

A

The amount of time a task can be delayed after the early start time without impacting overall completion time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the data required for scheduling a task?

A
  1. Task Name
  2. Early Start
  3. Duration
  4. Early Finish
  5. Late Start
  6. Slack
  7. Late Finish
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are possible task dependencies?

A
  1. Parallel (no dependency)
  2. Finish to Start
  3. Start to Start with Delay
  4. Finish to Finish with delay
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Parallel (No Dependency)

A

The 2 tasks are independent and the shortest completion time is achieved by doing them in parallel, as long as sufficient resources are available

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Finish to Start

A

Task C cannot be started until Task B has been completed, leaving slack time for Task A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Start to Start with Delay

A

Task B cannot be started until after a delay following the start of Task A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Finish to Finish with Delay

A

Task B cannot be finished until after a delay following the finish of Task A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Which 2 dependencies are the most common?

A
  1. Parallel (no dependency)

2. Finish to Start

17
Q

What does PERT stand for?

A

Program Evaluation and Review Technique

18
Q

How are task times filled out for PERT Charts?

A
  1. The early start time is 0 for the first set of parallel tasks
  2. The early finish time is filled in for each task by adding the duration to the early start time
  3. The late finish time is the same for all parallel tasks and is determined by adding the longest duration (4 days) to the early start time (0)
  4. The late start time is calculated for each task by subtracting the duration from the late finish time
  5. The slack time is calculated by subtracting the early start from the late start time
  6. Unless a delay is required before the next set of parallel tasks begins, the early start time is equal to the late finish time of the previous set of parallel tasks
19
Q

How do Gantt Charts display information?

A

As a timeline

20
Q

What is a strong point of Gantt Charts?

A

Their ability to clearly display overall progress

21
Q

Critical Path

A

All the tasks that will increase project completion time if they take longer than planned

22
Q

How is total completion time calculated?

A

Using the tasks on the critical path

23
Q

Which tasks should be looked at if total completion time needs to be reduced?

A

Tasks on the critical path

24
Q

What is the slack time for tasks on the critical path?

A

Always 0