Module 12 Execution & Control Flashcards

1
Q

Question 1 of 201.0/ 1.0 Points
The Planned Value (PV) of a project is $10,000. the Actual Cost (AC) is $5,000, and the Earned Value (EV) is $15,000. What is the value of the cost performance index?

A. $20,000
B. 2
C. $5,000
D. 3

A

D. 3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

All of the following accurately describe earned value management EXCEPT:

A. It is used to make predictions concerning the project schedule and cost control until the project’s conclusion.
B. It is good for performance reporting but not for forecasting
C. It is used as a decision-making tool.
D. It enables a project team to understand progress in terms of both cost and schedule.

A

B. It is good for performance reporting but not for forecasting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

This Agile project reporting tool is useful to Scrum Masters as it projects how close to plan the team is within a given time box, by providing a graphical representation of work effort remaining in an iteration versus the days left in an iteration.

A. Run chart
B. Burndown chart
C. Control chart
D. Progress report

A

B. Burndown chart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

During schedule and cost control, when comparing performance to the schedule and cost baselines, if schedule or budget has changed these changes should be:

A. reviewed with the customer or sponsor to obtain approval for additional funding
B. implemented immediately and reported as variances from baseline in the next status report
C. formally recommended and managed through the integrated change control system
D. added to the original baselines, and baseline changes made to reflect the new status

A

C. formally recommended and managed through the integrated change control system

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Which statement about processes in the monitoring and controlling process group is most true?

A. They are optional, depending on the needs of the project.
B. They may be invoked at any time during a project.
C. They are primarily concerned with performing, monitoring, and reporting on the work of the project.
D. They happen at the same time as the executing process group.

A

B. They may be invoked at any time during a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The process “Direct and Manage Project Work” is best described as:

A. track, review and regulate project progress
B. make relevant information available as planned
C. process of leading & performing the work defined in the project plan and implementing approved changes to achieve the project’s objectives.
D. review change requests and manage changes to baseline

A

C. process of leading & performing the work defined in the project plan and implementing approved changes to achieve the project’s objectives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Work to be performed can come from the work package level of the work breakdown structure as well as other sources. Which of these is NOT a source of authorized work to be performed?

A. Corrective actions
B. Preventive actions
C. Scope creep
D. Defect repairs

A

C. Scope creep

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Which of the following is the most appropriate thing to do during the executing process group?

A. Define activities.
B. Develop project charter
C. Perform quality assurance.
D. Hold a final lessons learned review.

A

C. Perform quality assurance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Which of the following activities is not part of control schedule?

A. Try to avoid schedule slips.
B. Manage changes to schedule baseline.
C. Distribute information on schedule performance.
D. Monitor status of project progress.

A

C. Distribute information on schedule performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

With respect to performance reporting, which of these are the actual and raw observations and measurements gathered during execution of project activities?

A. Work performance information
B. Work performance data
C. Work performance reports
D. Work performance analysis

A

B. Work performance data

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Some organizations rely upon a formal group authorized and responsible for reviewing, evaluating, approving, delaying, or rejecting any changes to any aspect of the project plan by following a formal communication method of documenting the decision process. This group is typically known as a:

A. project evaluation committee.
B. change control board.
C. steering committee
D. stakeholder review board.

A

B. change control board.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

When an activity takes two days instead of the expected three, the Schedule Variance (SV) is:

A. 0
B. 5
C. -1
D. 1

A

C. -1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Work performance reports have:

A. baseline data and performance information
B. resource performance indicators
C. quality assurance and quality reports
D. business plan with project schedule and cost baselines

A

A. baseline data and performance information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Typically, what does a project manager spend the most time doing when directing and managing project work?

A. Updating the baseline.
B. Monitoring progress of work packages.
C. Writing reports.
D. Communicating or facilitating communication

A

D. Communicating or facilitating communication

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

While the manage communications process is underway, effective information distribution often requires the project manager and team to accomplish all of the following activities EXCEPT:

A. report progress to all stakeholders
B. determine any information needs not already uncovered
C. collect information on executed work and work in progress
D. develop responses to identified risks

A

D. develop responses to identified risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Monitor Communications is the process of ensuring the information needs of the project and its stakeholders are met and typically includes all of the following EXCEPT:

A. Using a PM information system
B. forecasting future performance.
C. status reporting.
D. identifying team members in the communications process

A

D. identifying team members in the communications process