A.6. Discharge Flashcards
(100 cards)
Cutter v Powell
Was to be paid as working hand on boat for trip from Jamaica to Liverpool. Died on the way: entitled to nothing. If the contract requires entire performance: one is entitled to nothing if not fully performed.
Re Moore & Co
canned fruits to come in boxes of 30 came in boxes of 24 (although right total amount). Whole consignment rejected.
Boone v Eyre
SUBSTANTIAL PERFORMANCE. A party who has performed with only minor defects can claim price less any amount to correct defects. This will only apply to a breach of warranty: not of condition.
Hoenig v Isaacs
Hire to refubish a falt for 750. minor defect. Was allowed to claim price minus 56 pounds to correct.
Bolton v Mahadeva
unlike hoenig: price was 560: defects 174. Substantial performance found to not have taken place.
Sumpter v Hedges
contracted for building a shed: gave up halfway: and defendant had to finish the work himself. Quantum meruit didn’t apply: there was no choice for the defendant. Other party must accept for part performance: only if they have a real choice.
Planche v Colburn
contracted to write a book: but they cancelled the series - he was able to recover half amount.
Startup v McDonald
had until end of march to deliver oil. Arrived on last day: they refused to accept (it was late). Was allowed damages.
Lombard North Central plc v Butterworth [1987] QB 527.
Time is of the essence when the parties say so. The leased computer where it was stated late payment was a condition and would allow termination. Timely performance was a term and went to the root of the contract: C terminated.
United Scientific Holdings v Burnley BC
Time is of the essence where it can be seen from the nature of the contract - goods that spoil or vary quickly. Land not time of the essence. 99-year lease with the right to review rent every 10. landlord wanted to revise pricing after deadline and was allowed to do so. Time assumed to not be of the essence.
Valilas v Januzaj
Two dentists: one paying 50% of profits to the other to practice in his cabinet. 3 months late: it was a breach of warranty and not condition - could be some CF problems but not go under or anything. Allowed damages but not repudiation.
Charles Rickards v Oppenheimer
Time becomes of the essence after a delay and a notice of time is given.
Davies v Collins
coat given to clean: said every care is exercized. Subbed it and coat lost. This was a breach of contract because the language insinuated there would not be vicarious performance.
Stewart v Reavell’s Garage
liability stays with the original party when there is vicarious performance. Brake work to be done by a sub and this agreed by the other party. Brakes failed: got injured. Contracting party on the hook.
Taylor v Caldwell
Music hall rented for concerts: burned down. Performance became impossible: contract frustrated.
Davis Contractors v Fareham
Davis Contractors agreed with Fareham UDC to build 78 houses over eight months for £92,425. It ended up taking 22 months, because Davis was short of labour and materials. It cost £115,223. Davis submitted the contract was frustrated, void, and therefore they were entitled to quantum meruit for the value of work done. No, it just became more expensive. the frustrating event must render performance radically different and so must not be enforced. Frustation and mistake are similar: with the former happening after C: the other before.
Robinson v Davison
Unavailability of party frustrates the contract. Piano player got ill and couldn’t perform. Frustrated.
Nicholl and Knight v Ashton Edridge
Method of performance becoming impossible frustrates the contract. Shipment of cotton on specific boat. Boat sank: couldn’t perform as described.
Events making performance impossible
- Destruction/unavailability of something essential to performance. 2. death of either party if personal performance needed. 3. unavailability of party (Robinson v Davison): 4. Nicholl and Knight v Ashton Edridge
Fibrosa v Fairbairn
a change in the law after the c making performance illegal frustrates the contract. Machines to be delivered to Poland but by the time they were finished: Poland had been occupied.
Krell v Henry
rented a room to see coronation: which was postponed. Frustrated: there was no other point to rent the room
Herne Bay Steam Co v Hutton
rented a boat to see the coronation naval review. Coronation postponed. Contract upheld because there were other points to renting a boat.
AA v PM
call center hired to help with transition to central call center: but franchisees didn’t want it. Asked for frustation but was denied because: 1. whole purpose of contract not necessarily gone: 2. frustrating event has to be something the parties could not reasonably have foreseen: 3. actions after event are a clue (here the parties waited 5 months after supposed frustration).
Limits of Frustration: 1. Contractual Provision
- If there is a contractual provision against frustrating event: no frustration. A C may make specific provision for the type of event: usually by allocating the risk to one of the parties. A force majeure clause will also impede frustration if it is within scope.