ACRONYMS Flashcards
(75 cards)
1
Q
AC
A
ACTUAL COST
2
Q
ADR
A
ALTERNATIVE DISPUTE RESOLUTION
3
Q
AT
A
ACTUAL TIME
4
Q
BAC
A
BUDGET AT COMPLETION
5
Q
BOOT
A
BUILD, OWN, OPERATE, TRANSFER
6
Q
CCB
A
CHANGE CONTROL BOARD
7
Q
COQ
A
COST OF QUALITY
8
Q
CPAF
A
COST PLUS AWARD FEE
9
Q
CPFF
A
COST PLUS FIXED FEE
10
Q
CPI
A
COST PERFORMANCE INDEX
11
Q
CPIF
A
COST PLUS INCENTIVE FEE
12
Q
CPM
A
CRITICAL PATH METHOD
13
Q
CV
A
COST VARIANCE
14
Q
DB
A
DESIGN BUILD
15
Q
DFX
A
DESIGN FOR X
16
Q
EAC
A
ESTIMATE AT COMPLETION
17
Q
EAD
A
ESTIMATED ACTIVITY DURATION
18
Q
EEF
A
ENTERPRISE ENVIROMENTAL FACTORS
19
Q
EF
A
EARLY FINISH
20
Q
EMV
A
ESTIMATED MONETARY VALUE
21
Q
ES
A
EARLY STATE OR EARNED SCHEDULE
22
Q
ETC
A
ESTIMATE TO COMPLETION
23
Q
EV
A
EARNED VALUE
24
Q
EVM
A
EARNED VALUE MANAGEMENT
25
FF
FINISH TO FINISH
26
FFP
FIRM FIXED PRICE
27
FPEPA
FIXED PRICE WITH ECONOMIC PROCE ADJUSTMENTS
28
FPIF
FIXED PRICED INCENTIVE FEE
29
FS
FINISH TO START
30
FV
FUTURE VALUE
31
IFB
INVITATION FOR BID
32
IRR
INTERNAL RATE OF RETURN
33
LOE
LEVEL OF EFFORT
34
LF
LATE FINISH
35
LS
LATE START
36
M
MOST LIKELY
37
MBO
MANAGEMENT BY OBJECTIVES
38
MBWA
MANAGEMENT BY WALKING AROUND
39
MSA
MASTER SERVICE AGREEMENT
40
NPV
NET PRESENT VALUE
41
O
OPTIMISTIC
42
OBS
ORGANIZATIONAL BREAKDOWN STRUCTURE
43
OPA
ORGANIZATIONAL PROCESS ASSETS
44
P
PESSIMISTIC
45
PDCA
PLAN DO CHECK ACT
46
PDU
PROFESSIONAL DEVELOPMENT UNIT
47
PERT
PROGRAM EVALUATION AND REVIEW TECHNIQUE
48
PESTLE
POLITICAL, ECNOMIC, SOCIAL, TECHNOLOGICAL, LEGAL, AND ENVIROMENTAL
49
PMBOK
PROJECT MANAGEMENT BODY OF KNOWLEDGE
50
PMI
PROJECT MANAGEMENT INSTITUTE
51
PMIS
PROJECT MANAGEMTN INFORMATION SYSTEM
52
PMO
PROJECT MANAGEMENT OFFICE
53
PMP
PROJECT MANAGEMENT PROFESSIONAL
54
PV
PLANNED VALUE OR PRESENT VALUE
55
QFD
QUALITY FUNCTION DEPLOYMENT
56
RACI
RESPONSIBLE, ACCOUNTABLE, CONSULT, AND INFORM
57
RAM
RESPONSIBILITY ASSIGNMENT MATRIX
58
RCA
ROOT CAUSE ANALYSIS
59
RBS
RISK BREAKDOWN STRUCTURE
60
RFI
REQUEST FOR INFORMATION
61
RFQ
REQUEST FOR QUOTATION
62
ROI
RETURN ON INVESTMENT
63
SD
STANDARD DEVIATION
64
SF
START TO FINISH
65
SMART
SMART, MEASUREABLE, ATTAINABLE, RELEVANT, AND TIMELY
66
SOW
STATEMENT OF WORK
67
SPI
SCHEDULE OF PERFORMANCE INDEX
68
SS
START TO START
69
SV
SCHEDULE VARIANCE
70
SWOT
STRENGTHS, WEAKNESSES, OPPORTUNITIES, AND THREATS
71
TCPI
TO COMPLETE PERFORMANCE INDEX
72
TQM
TOTAL QUALITY MANAGEMENT
73
VAC
VARIANCE AT COMPLETION
74
VUCA
VOLATILITY, UNCERTAINTY, COMPLEXITY, AND AMBIGUITY
75
WBS
WORK BREAKDOWN STRUCTURE